14.1 Environmental conditions for compliance during Building Approvals
The Ministry of Environment, Forest and Climate Change has now decided to integrate the environmental concerns into building plan approval process and empowering the concerned local body/development authority to approve and certify compliance of stipulated requirements. The new building construction proposals are classified in the following 3 categories:-
-
Conditions for Category ‘A’ Buildings: Built-up Area 5000 sqmt – 20000 square meters
-
Conditions for Category ‘B’ Buildings: Built-up Area 20000 sqmt – 50000 square meters
-
Conditions for Category ‘C’ Buildings: Built-up Area 50000sqmt – 150000 square meters
A local Authority, i.e. ULB/DA/any other body authorized to sanction building plans shall approve the building plans by ensuring the stipulated conditions in Table 14.1, 14.2 and 14.3 for the respective categories of buildings.
These environmental conditions may be suitably integrated in the building permission conditions so that their effective implementation could be ensured by the local authority while sanctioning building plans in their respective urban areas.
However, in order to empower the Local Authority, the State/UT Governments will be required to amend their building by-laws to incorporate a specific set of conditions as given in the Tables 14.1, 14.2 and 14.3. Once these conditions are incorporated through due process adopted by States/UTs into the Building Bye-Laws and made applicable and enforceable by their local authority, States / UTs will be required to approach M/o Environment, Forest and Climate Change along with the Draft notification for seeking clearance that the requirements have been met and after getting the clearance from M/o EFCC, State/UT shall issue notification of Building Bye-laws along with stipulated conditions. Copy of the notification shall be forwarded to Ministry of Environment, Forest and Climate Change so that they may notify the particular
Chapter 14
Climate Resilient Construction-Integration of Environmental Clearance with Sanction
State or part thereof for which conditions have been suitably integrated to delegate the powers to the Local Authority. Thereafter, for such notified area no separate prior Environmental clearance will be required. However, for those States/UTs or part of the States/UTs where these conditions have not been incorporated in the Building Bye-Laws, the existing arrangement of mandatory prior Environment clearance by State Environment Impact Assessment Authority shall continue to hold.
States are, therefore, advised to amend their building by-laws by incorporating the set of conditions for each category A, B and C as mentioned above either for the entire State/UT or clearly identified part thereof, where they would like to integrate the environmental clearance conditions with building permissions and empower the local authority to examine, stipulate and ensure compliance of conditions required to address environmental concerns. The State/UT should submit such proposal/ notification at draft stage as well as a copy of the final notification to the M/o Environment, Forest and Climate Change.
i. For building plans with a total built-up area between 5,000 sqm and 1,50,000 sqm, environment clearance will be required to be synchronized with the bye-laws.
ii. The concerned Urban local body, authorized to sanction building plans, shall ensure at the time of sanctioning a building plan that the environmental requirements stipulated in Table 14.1 (for above 5,000 sqm and up to 20,000 sqm), Table 14.2 (for above 20,000 sqm and up to 50,000 sqm) and Table 14.3 (for above 50,000 sqm and up to 1,50,000 sqm), as the case may be, are complied with.
| Sl. No. | Medium | Environmental conditions | APBBL Ref. Clause |
|---|---|---|---|
| 1 | Natural Drainage | The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water. | - |
| 2 | Water conservations - Rain Water Harvesting and Ground Water Recharge | A rain water harvesting plan needs to be designed where the recharge bores (minimum one per 5000 sqm of built-up area) shall be provided. The rain water harvested should be stored in a tank for reuse in household through a provision of separate water tank and pipeline to avoid mixing with potable municipal water supply. The excess rain water harvested be linked to the tube well bore in the premise through a pipeline after filtration in the installed filters. | Table 9.1 |
| 2(a) | The unpaved area shall be more than or equal to 20% of the recreational open spaces. | 10.2.1 (iv) | |
| 3 | Solid Waste Management | Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste. | 10.2.5 (b) |
| 4 | Energy | In common areas, LED/ solar lights must be provided. | 10.2 3c) |
| 5 | Air Quality and Noise | Dust, smoke and debris prevention measures such as screens, barricading shall be installed at the site during construction. Plastic/ tarpaulin sheet covers must be used for trucks bringing in sand and material at the site. | - |
| 5 (a) | The exhaust pipe of the DG set, if installed, must be minimum 10m away from the building. In case it is less than 10m away, the exhaust pipe shall be taken up to 3mabove the building. | - | |
| 6 | Green cover | A minimum of 1 tree for every 80 sqm of land shall be planted and maintained. The existing trees will be counted for this purpose. Preference should be given to planting native species. | 10.2.1 (i) |
| 6(a) | Where the trees need to be cut, compensatory plantation in the ratio of 1:3 (i.e. planting of 3 trees for every 1 tree that is cut) shall be done with the obligation to provide continued maintenance for such plantations. | 10.2.1 (ii) |
Chapter 14
Climate Resilient Construction-Integration of Environmental Clearance with Sanction
| Sl. No. | Medium | Environmental conditions | APBBL Ref. Clause |
|---|---|---|---|
| 1 | Natural Drainage | The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water. | - |
| 2 | Water Conservations - Rain Water Harvesting & Ground Water Recharge | A rain water harvesting plan needs to be designed where the recharge bores (minimum one per 5000 sqm of built-up area) shall be provided. The rain water harvested should be stored in a tank for reuse in household through a provision of separate water tank and pipeline to avoid mixing with potable municipal water supply. The excess rain water harvested be linked to the tube well bore in the premise through a pipeline after filtration in the installed filters. | Table 9.1 |
| 2(a) | The unpaved area shall be more than or equal to 20% of the recreational open spaces. | 10.2.1 (iv) | |
| 3 | Solid Waste Management | Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste. | 10.2.5 (b) |
| 4 | Energy | In common areas, LED/ solar lights must be provided. | 10.2 3c) |
| 4(a) | At least 1% of connected applied load generated from renewable energy source such as photovoltaic cells or wind mills or hybrid should be provided. | 10.2 | |
| 4(b) | As per the provisions of the Ministry of New and Renewable energy solar water heater of minimum capacity 10 litres/4 persons (2.5 litres per capita) shall be installed. | 1-.2.4 - IV | |
| 4(c) | Use of flyash bricks: Fly ash should be used as building material in the construction as per the provisions of Fly Ash Notification of September, 1999 and as amended from time to time. | 10.2.6 (b) | |
| 5 | Air Quality & Noise | Dust, smoke and debris prevention measures such as screens, barricading shall be installed at the site during construction. Plastic/ tarpaulin sheet covers must be used for trucks bringing in sand and material at the site. | - |
| 5(a) | The exhaust pipe of the DG set, if installed, must be minimum 10m away from the building. In case it is less than 10m away, the exhaust pipe shall be taken up to 3m above the building. | - | |
| 6 |
| Sl.No. | Medium | Environmental conditions | APBBL Ref. Clause |
|---|---|---|---|
| 1 | Natural Drainage | The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water. | - |
| 2 | Water conservations-Rain Water Harvesting & Ground Water Recharge | A rain water harvesting plan needs to be designed where the recharge bores (minimum one per 5000 sqm of built-up area) shall be provided. The rain water harvested should be stored in a tank for reuse in household through a provision of separate water tank and pipeline to avoid mixing with potable municipal water supply. The excess rain water harvested is to be linked to the tube well bore in the premise through a pipeline after filtration in the installed filters. | Table 9.1 |
| 2(a) | The unpaved area shall be more than or equal to 20% of the recreational open spaces. | 10.2.1 (iv) | |
| 2(b) | The ground water shall not be withdrawn without approval from the competent authority | ||
| 2(c) | Use of potable water in construction should be minimized. |
Chapter 14
Climate Resilient Construction-Integration of Environmental Clearance with Sanction
| Sl.No. | Medium | Environmental conditions | APBBL Ref. Clause |
|---|---|---|---|
| 2(d) | Low flow fixtures and sensors must be used to promote water conservation. | ||
| 2(e) | Separation of grey and black water should be done by the use of dual plumbing system. | ||
| 3 | Solid Waste Management | Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste. | 10.2.5 (b) |
| 3(a) | All non-biodegradable waste shall be handed over to authorized recyclers for which a written tie-up must be done with the authorized recyclers. | ||
| 3(b) | Organic waste composter/ vermiculture pit with a minimum capacity of 0.3 Kg/tenement/day must be installed wherein the STP sludge may be used to be converted to manure which could be used at the site or handed over to authorized recyclers for which a written tie-up must be done with the authorized recyclers. | ||
| 4 | Energy | In common areas, LED/ solar lights must be provided. | 10.2 3c) |
| 4(a) | At least 1% of connected applied load generated from renewable energy source such as photovoltaic cells or wind mills or hybrid should be provided. | 10.2 | |
| 4(b) | As per the provisions of the Ministry of New and Renewable energy solar water heater of minimum capacity 10 litres/4 persons (2.5 litres per capita) shall be installed. | 10.2.4 - IV | |
| 4( c) | Use of flyash bricks: Fly ash should be used as building material in the construction as per the provisions of Fly Ash Notification of September, 1999 and as amended from time to time. | 10.2.6 (b) | |
| 4(d) | Use of concept of passive solar design of buildings using architectural design approaches that minimize energy consumption in buildings by integrating conventional energy-efficient devices, such as mechanical and electric pumps, fans, lighting fixtures and other equipment, with the passive design elements, such as building orientation, landscaping, efficient building envelope, appropriate fenestration, increased day lighting design and thermal mass. | 10.2 (3) | |
| 4(e) | Optimize use of energy systems in buildings that should maintain a specific indoor environment conducive to the functional requirements of the building by following mandatory compliance measures (for all applicable buildings) as recommended in the Energy Conservation Building Code (ECBC) 2007 of the Bureau of Energy Efficiency, Government of India. | 10.2 (3) |
Chapter 14
Additional Provisions in Development Control Regulations for Safety in Natural Hazard Prone Areas