9. Utilization of Transferable Development Right Certificate
General Terms and Conditions:
a) TDR generated in an urban area can be utilized within the same urban area only.
b) In case the applicant is holder of power of attorney or limited company or corporate body of registered societies and trust, the registered power of attorney or relevant resolution regarding authority to file application or request for transfer, together w ith certified copy of the Memorandum & Article of Association and / or Bye-laws should accompany the application and utilization form.
c) The TDR shall be utilized in various receiving zones over and above the prescribed standard FAR subject to the maximum FAR in Building Regulations or as per the directions issued by the Government from time to time.
d) In case there are two Competent Authorities in any urban area, before permitting utilization of TDR, NOC will be obtained from the agency in whose jurisdiction land falls where it is proposed to be used,
e) The utilization of TDR in favour of an NRI and a foreign national will be subject to rules and regulations of the Reserve Bank of India/Government of India.
f) The utilization of TDR shall be in multiples of 50 sq. mts. only except the last remainder. Any request of the transferor or of transferee for utilization of TDR other than in multiples of 50sq.mts. shall not be considered.
g) The Competent Authority may reject the application for utilization of TDR in the following circumstances: -
I. if any dues payable by the owner of the property, to the State Govt. / ULB prior to the date of submission of project or surrender of land, then the Competent Authority can withhold utilization of the TDR unless all the State Govt. / ULB dues are paid by the owners.
II. If the property is handed over to the ULB's and TDR is obtained by fraudulent means (illegal title of land surrendered/ wrong measurement etc.), then the Competent Authority shall reserve the rights for granting permission to transfer / utilize the TDR and or forfeiting TDR.
h) In case of a utilization of TDR jointly held all the joint holders of TDR Certificate shall have to sign the application form to be used for utilization.
i) The utilization of the TDR shall not be accepted unless and until the entry for utilization of TDR is authenticated by the Competent Authority.
j) Any utilization of TDR shall be charged at the rate of Rs. 10/- per sq. mts. subject to minimum of Rs. 1000/- as utilization fees.
k) The utilization of TDR can be considered by the Competent Authority only if the application for utilization is submitted in prescribed form along with the necessary documents and on making payment of utilization fees. The procedure for utilization of TDR shall be as under:-
I. The applicant seeking to use the TDR shall obtain a letter in the prescribed format from the building plan approving officer of the concerned local body stating the extent to which TDR can be utilized on the proposed plot of land. Building Plan approving officer shall issue this certificate within a period of 3 months.
II. The applicant shall submit the above letter with an application to the
competent authority of ULB for issue of authority letter for utilization of TDR in the name of building plan approval authority with full details where the TDR is proposed to be used.
III. The competent authority (who had issued TDR certificate) after examination of the TDR certificate and records shall issue a authority letter for the full or part utilization of FAR to the concerned local body (who will approve the building plan) in a prescribed format after cancellation or deduction of FAR used as the case may be.
IV. It shall be the responsibility of the competent authority to ensure that necessary entries are made in the records prior to issue of authority letter.
V. The applicant shall submit the authority letter to the local authority for utilization of TDR. The building plan approving authority shall inform the competent authority on utilization of authority letter so that the utilization of authority letter can be entered as final settlement as the office of competent authority.
l) The Competent Authority may reject the application for utilization of TDR under the following circumstances: -
I. Under direction from the competent court.
II. If the Competent Authority is of the opinion that transfer has been obtained by fraudulent means and in such situation, the TDR Certificate will be forfeited
III. If the agreement of utilization of TDR is not duly signed by the transferor(s) and transferees(s).
IV. If the agreement utilization is riot accompanied by the original TDR Certificate.
m) Every utilization of the TDR shall be got approved from the Competent Authority and it shall be entered on the Certificate.
n) In case the TDR Certificate holder is minor, the utilization will be considered only if application is made by the natural guardian or a guardian appointed by the competent court.
o) The application for utilization of TDR shall be considered provided: -
p) The TDR Certificate holder(s) intends to utilize the TDR shall have to submit the proof showing that the building plans on the land situated in a Receiving zone are approvable as per building regulations.
q) For each request to utilize the TDR, separate application shall be submitted.
r) The prescribed utilization form requesting the Competent Authority of ULB's to utilize the TDR shall be valid only for 6 (six) months.
s) The TDR generated from any area and proportionate TDR proposed to be transferred in any eligible receiving zone, shall be eligible for residential use only in case of Affordable Housing, whereas for other cases use at generating zone shall be proportionate to same use in receiving zone i.e. if commercial land is surrendered for facilities and TDR is generated will be eligible for proportionate TDR at receiving zone for the same use.
t) The TDR receiving plot should satisfy the following minimum requirement:
I. There shall be no change in the setbacks of the receiving plot.
II. Receiving plot must satisfy the additional parking requirement (if any)
in proportion to TDR being utilized to be worked out in accordance with the prevailing building byelaws.
III. Receiving plot should satisfy the minimum fire safety norms as specified in the building byelaws.
IV. Receiving plot shall be eligible to receive a maximum TDR, within the
maximum permissible FAR in accordance with the building byelaws.
u) The movement of TDR from the generating zone to receiving zone shall be in proportion of the prevailing Minimum Guidance Value of the concerned area as specified by the State Govt. The TDR shall be subject to proportionate increase or decrease as per Minimum Guidance Value. For example, if the residential Minimum Guidance Value in generating zone is
Rs 2000 per sqm. from where TDR has generated and the residential Minimum Guidance Value is Rs. 20,000/- per sqm. in receiving zone then the proportionate TDR to be transferred shall be 1/10th of the total TDR generated subject to minimum of 10% of total TDR.
v) If a holder of TDR intends to transfer it to any other person, he will submit the TDR Certificate to the Competent Authority with an application for an endorsement of the new holder's name i.e., transferee on the said Certificate. It is important to note that without such an endorsement by the Competent Authority, the transfer shall not be valid.
w) A TDR Certificate holder who desires to use the FAR out of the TDR available in credit, on a particular plot of land shall attach TDR Certificate with his application for building permission.
x) TDR shall not be valid for use on receiving plots in the areas listed below, identified as No-TDR Zone which will be notified before the issue of TDR certificate.
i. Any congested area looking to the traffic intensity as notified by the concerned ULB/ State Government.
ii. Restricted Area notified by the concerned urban local bodies/ Airport Authority/state Government.
iii. Beyond the prescribed height on Street/roads/areas on which the height is restricted as per prevailing Building Regulations.
iv. On structures listed as heritage precincts or structure identified by ASI or State Archaeology Department. TDR should not be permitted within the radius as prescribed by ASI or State Archaeology Department from time to time from the periphery of these identified structures.