(a) The staircase and corridor lighting shall be on separate service and shall be independently connected so as it could be operated by one switch installation on the ground floor, easily accessible to firefighting staff at any time irrespective of the position of the individual control of the light points, if any.
(b) Staircase and corridor lighting shall also be connected to alternate supply from parallel high-tension supply or to the supply from the stand by generator.
(c) Emergency lights shall be provided in staircase and corridor passageway, horizontal exits, refuge area and all wires and other accessories used for emergency light shall have fire retardant properly.
2. Electrical services
(a) The electrical distribution cables/wiring shall be laid in separate duct the duct shall be sealed at every floor with non-combustible materials having the same for resistance as that of the duct. Low and medium voltage wiring running in shaft and in false ceiling shall run in separate conduits.
(b) Water mains, telephone cables, intercom cables, gas pipes or any other service line shall not be laid in the duct for electric cables. Use of bus ducts/ solid rising mains instead of cables is preferred.
(c) The provision of dedicated telecommunication ducts for all new building proposals is mandatory for conveyance of telecommunication and other data cables.
(d) Separate circuits for water pump lifts, staircases and corridor lighting and blowers for pressurizing system shall be provided directly from the main switchgear panel refer NBC 2005.
3. Alternate source of electric supply
A stand by electric generator shall be installed to supply power to staircase and corridor lighting circuits, fire lifts, the stand by fire pumps, pressurization, fans and blowers, smoke extraction and damper system in case of failure of normal electric supply. The generator shall be capable of taking starting current of all the machines and circuits stated above simultaneously. If the stand by pump is driven by diesel engine, the generator supply need not be connected to the stand by pump.
4. Air conditioning
Air conditioning shall conform to the following
(a) Escape routes like staircases, common corridors, lift lobbies etc shall not be used as return air passage.
(b) The ducting shall be constructed of sufficient gauge metal in accordance with good practice.
(c) Where ever the ducts pass through fire walls or floors, the opening around the ducts shall be sealed with materials having fire resistance rating of the compartment.
(d) Where duct crosses a compartment which is fire rated, the ducts shall be fire rated for same fire rating. Further depending on services passing around the duct work, which may get affected in case of the temperature rising, the ducts shall be insulated.
(e) Metallic ducts shall be used even for the return air passage instead of space above the false ceiling.
(f) Where plenum is used for return air passage, ceiling and its fixtures shall be of non-combustible material.
(g) The materials used for insulating the duct system (inside or outside) shall be of non-combustible material; glass wool shall not be wrapped or secured by any material of combustible nature.
(h) Air ducts serving main floor areas, corridors etc shall not pass through the staircase enclosures.
(i) The air handling units shall be separate for each floor and air ducts for every floor shall be separated and in no way inter connected with the ducting of any other floor.
(j) If the air unit handling serves more than one floor, the recommendations given above shall be complied with an addition to the conditions given below.
(1) Proper arrangements by way of automatic fire dampers working on smoke detector/or fusible link for isolating all ducting at every floor from the main riser shall be made.
(2) When the automatic fire alarm operates, the respective air handling units of the air conditioning system shall automatically be switched off.
(3) The vertical shaft for treated fresh air shall be masonry construction.
(4) The air filters of the air handling units shall be of non-combustible materials or fire rated.
(5) The air handling unit room shall not be used for storage of any combustible materials.
(6) Inspection panels shall be provided in the main trunking to facilitate the cleaning of ducts of accumulated dust and to obtain access for maintenance of fire dampers.
(7) No combustible material shall be fixed nearer than 150 mm to any duct unless such duct is enclosed and protected spy glass with neoprene facing enclosed and wrapped with aluminium sheeting) at least 3.2 mm thick and would not readily conduct heat.
5. Transformers
(a) If the transformers shall be dry type and shall be kept in an enclosure with walls, doors and cut outs having fire resistance rating of 4 hour. The entrance to the room shall be provided with a steel door of fire rating of 2 hours. A curb of suitable height should be provided at the entrance in order to prevent the flow of oil from ruptured transformer into other parts of the basement. The switchgear should be housed in a separate room with fire resistance not less than 4 hours.
(b) The transformer shall be protected by an automatic foam sprinkler system. If they are housed on the ground floor, they should be cut off from the other portion of the premises by fire resistant walls of 4 hours rating.
(c) A tank of R.C.C construction of adequate capacity shall be provided at lower basement level to collect the oil from the catch pit in case of emergency. The pipe connecting the catch pit to the tank shall be of non-combustible construction and shall be provided with a flame arrester.
(d) The electric sub-station shall be located in a separate building in accordance I.E Rules 68(I) and 64 (I)(a).
(e) If this is not possible due to site conditions, the sub-stations shall be located on the ground floor. As far as possible due to site conditions the sub-station shall not be installed in a basement, for such situations special provisions like mechanical ventilation, wherever required, cable ducting, cable trays, top/bottom entry of HV/LV cable, hooks on Transformers and HV Panels, adequate fire detection and fire-fighting arrangement, adequate drainage, effective measures
to prevent flooding etc. shall be provided. Adequate precautions shall also be taken for water proofing to prevent seepage of water. A ramp shall also be provided with a slope, not steeper than 1 in 7, for easy movement of equipments to and from sub – station.
(f) Fire regulation- The installations shall be carried out in conformity with the local regulations and rules there under wherever they are in force. At other places NBC Guidelines shall be followed.
6. General
(a) Architectural elements such as louvers, pergolas other sunshine materials should be free from FAR
(b) Followings are also permitted out of FAR if not used for habitable or commercial purposes.
(c) Building elements such as sky bridges and landscapes terraces which are meant for community purposes only shall be permitted free of FAR.
(d) Services can be permitted on roofs with adequate screening for the same.
(e) Service floor.
(f) Atrium /Atria at any floor will be counted only once in the FAR. Atrium may be enclosed by light roofing or R.C.C.
(g) Scissor staircase will be permitted provided all travel distance and fire norms are adhered to.
(h) Stilts in high rise will not be restricted to height of 2.4 m as long as it is used for parking.
(i) Multilevel car parking with car lifts would be permitted with adequate fire safety.
- FAR, Setbacks, Ground Coverage and Heights of Commercial Buildings
| Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas | Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas | Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas | Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas | Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas | Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas | Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas | Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas | Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas | Proposed Setbacks and Heights of Commercial Buildings other than CBD and TOD Areas |
| No. | Plot Area (sq.mt) | Maximum Ground Coverage | FAR | Maximum Height Permissible (in meters) | Maximum Height Permissible (in meters) | Minimum Setbacks proposed (in meters) | Minimum Setbacks proposed (in meters) | Minimum Setbacks proposed (in meters) | Minimum Setbacks proposed (in meters) |
| No. | Plot Area (sq.mt) | Maximum Ground Coverage | FAR | Maximum Height Permissible (in meters) | Maximum Height Permissible (in meters) | Front | Rear | Side 1 | Side 2 |
| 1 | 90-150 | NIL | 150 | 11 | G+2 | 1.50 | 0.90 | 0.90 |