- Particulars to accompany application of re-erecting a building: Every person who intends to erect or re-erect or alter a building shall give notice in writing to the Chairperson of his intention in the prescribed Form 1 and such notice shall be accompanied by Plans and Statements in triplicate as required under Bye-law 5, The Plans may be ordinary prints on paper. One set of such Plans shall
be retained in the office of the Chairperson for record after the issue of the permit or a refusal. One copy of such Plan shall be retained in the office of Town Planning Department.
4. “OBPS” Online Building Permission System:
-
All the online applications for buildings located within the Urban local bodies Area shall be submitted through Licence Architects or Firms registered in the name of a Licence Architect who are registered with the respective Urban local bodies
-
The Licensed Technical Persons (LTP) shall submit the Application online to the the Municipal Commissioner/Senior CEO/CEO/Executive Officer of the concerned ULBs along with the Building Plans in .dxf format and documents required as per the Building Bye-law at Chapter II of the Principal Law.
-
On payment of requisite fees etc. the system shall auto generate instant Planning Permit and Building Permit along with approved drawing and forward the same to empanelled LTP and the Applicant with SMS and email alert. The approved drawings, the Planning Permit and Building Permit shall be in a downloadable format by the empanelled LTP and Applicant.
-
In case the proposal is not as per the provisions of the Building Bye-laws and the Master Plan of the concerned towns, the system shall return the same to empanelled LTP with Email/SMS alert to the applicant.
-
Authorities shall carry out post approval inspection of the proposals as and when required to ensure the adherence of the Building Bye-laws and Master Plan. Any discrepancies found during the inspection, shall be treated as unauthorized as per the provisions of this Bye-law, and the Planning Permit/ Building Permit issued shall be withdrawn.
-
The buildings constructed under these clauses shall also obtain instant Occupancy Certificate on submission of all the documents as per provisions given in these bye-laws duly certified by the empanelled LTPs.
5. Plans accompanying Notice:-
The following shall accompany the notice:-
(1) Site plan—The site plans sent with an application, for permit shall be-drawn to a scale of not less than 8 m to 1 cm (or 64 ft to 1inch) 1:100 (1m to 1cm) and shall show:
(a) the boundaries of the Site and of any contiguous land belonging to the owner thereof
(b) the position of the site relating to neighboring streets:
(c) the name of the street in which the building is proposed to be situated;
(d) all existing building standing on the site;
(e) the position of the building and of all other buildings, if any, which the applicant intends to erect upon his contiguous land referred to in (a) in relation to;
(i) the boundaries of the site, and in case where the site has been partitioned the boundaries of the portion owned by the applicant and also of the portion owned by the other owners;
(ii) all adjacent streets, buildings and premises within a distance of 12 m (or 40 ft) of the site and of the contiguous land, if any referred to in (a); and
(iii) if there is no street within a distance of 12 m. (or 40 ft) of the site, the nearest existing street;
(f) the means of access from the street to the building and to all other buildings, if any, which the applicant intends to erect upon his contiguous land referred to in (a);
(g) the position and the number of storeys of all other buildings within 12 m. (or 40 ft) of the site.
(h) the position, forms and dimensions of kitchens, staircases, privies, urinals, drains, cesspools, stable's, cattle sheds, cow-houses, wells and other appurtenances of the buildings;
(i) free passage or way in front of the building;
(j) space to be left about the building to secure a free circulation of air admission of light and access for scavenging purposes;
(k) the width of the street, if any, in front of the building, if any, at the side or rear of the building; and
(l) Such other particulars as may be prescribed by the Road.
(m) north point: and
(n) the width of front, side and rear yard, existing road side trees, lamp and Telephone posts.
(o) Trace map of the proposed site indicating the Dag No. Patta No. and Revenue Village;
(p) Detailed calculation sheet of FLOOR AREA RATIO (FAR).
(q) A certificate of supervision in Form II, Form III and Form IV:
(r) In case of residential layout plans of plots with land area of 1.5 hectare, a minimum of 10% of the plotted area is to be earmarked / reserved for Affordable Housing category.
(s) The owner/developer is given freedom to build these units in a separate block with separate access with option to develop only Economically Weaker Section (EWS) dwelling units in lieu of Lower Income Group (LIG), wherever applicable:
(t) If the houses/flats/apartments are constructed by private developers/builders, and made available for Affordable Housing segment i.e. Economically Weaker Section (EWS)/ Lower Income Group (LIG) the said developers/builders, shall be entitled to an additional FLOOR AREA RATIO (FAR) of 10% to 25% over that applicable FLOOR AREA RATIO (FAR) for the relevant land use depending on the percentage of area allotted to Affordable Housing segment i.e. Economically Weaker Section (EWS) /Lower Income Group (LIG)within these limits. However, there shall be no restrictions for construction of Affordable Housing segment i.e. Economically Weaker Section (EWS) /Lower Income Group (LIG)houses within the permissible FLOOR AREA RATIO (FAR).
6. Building Plans for Multi Storeyed/Special Building: Additional requirements for Multi-storeyed, Lifeline and Special Buildings:
(1) Service plan showing the following details - private water, sewerage disposal system and detail of building services where required by the Authority shall be made available on scale not less than 1:100 and it should also include the following:
(A) For outlet from the soak-pit to municipal drain if provided, an intermediate treatment chamber should be installed, details of which is to be shown in service plan, subject to approval of the Authority:
(a) The space for a STP is mandatory to be proposed in the layout/service plan and constructed as per the approved norms and specifications in case of:
(i) residential layouts, areas measuring 4000 Sq.m. or more:
(ii) group housing/Apartment houses if the built-up area measures above 2000 Sq.m. or if the consumption of water is 20000 liters per day or if it is a multi-storied building with more than 30 apartment houses;
(iii) commercial Complexes/Institutional/Hotel and Lodges/ Industrial Buildings etc. if the built-up area is above 2000 Sq.m. or water consumption is 20,000 liters per day.
(iv) hospitals/Nursing Homes with 40 or more beds.
The STP is required to be certified by independent expert accredited by State Pollution Control Board/Department of Environment and Forest, Govt. of Manipur before the project is commenced for operation or by State Pollution Control Board.
(b) STP provision for building/commercial project, new development project and township ≥ 20,000 sq.m. and < 1,50,000 sq.m. of buildup space will be governed by environmental clearance required as per SO 1533 14th September 2006 notified by Ministry of Forest, Govt. of India.
(c) For all other projects requiring prior environmental clearance the requirement will be as per the clearance.
(B) Garbage bin, location of which should be within the plot and such that it can be easily accessed by collecting staff of municipal authority without any difficulty.
(C) Detail of building services, which include,
(a) air conditioning system, if any:
(b) detail of exits including provisions of ramps, etc. for hospital and special risk building:
(c) Location of generator, if any, transformer and switchgear and main electric panel duly certified by MSPDCL.
(d) smoke exhauster system and fire alarm, if any;
(e) location of centralized control of all fire alarm systems, if any.
(f) location and dimension of static water storage and pump house,
(g) location of fire protection installation, sprinklers, wet risers, etc, if any. N.B.-These should generally be as per specifications of National Building Code, 2016.
(h) location and details of fixed fire protection installation and first-aid and fire-fighting equipments / installations:
7. Fees:
- No notice as referred to above in bye-law 3 shall be deemed valid unless and until the person giving notice has paid the fees given below to the Corporation/Council and an attested copy of the receipt of such payment is attached with the notice:
| For R.C.C., masonry & brickworks: | For R.C.C., masonry & brickworks: | For R.C.C., masonry & brickworks: |
| 1 | Cost of the application Form (Form I-VI) | Rs 100/- per set |
| 2 | Buildings ofplinth area upto 200 square metre | Rs 100/- per square metre |
| 3 | Buildings ofplinth area from 200 square metre and above | Rs 120/- per square metre |
| 4 | For additional storey above Ground+1 | Rs 100/- per square metre |
| 5 | Application Fees for Cinema, Commercial Complex, Theatre, Multiplex, Hotels with Conference Halls in addition to the normal fees | Rs 10,000/- in addition to normal fees at Sl. 1 to 3. |
| Loadbearing buildings | Loadbearing buildings | Loadbearing buildings |
| 1 | The plinth area upto 200 square metre | Rs 50/- per square metre |
| 2 | The plinth area from 200 square metre and above | Rs 100/- per square metre |
| Revalidation of already approved Building Plans | Revalidation of already approved Building Plans | Revalidation of already approved Building Plans |
| 1 | Revalidation of Plans | Rs 1,000/- Per Annum |
| Installation of Communication Towers | Installation of Communication Towers | Installation of Communication Towers |
| 1 | Fee for installation of Towers | Rs 1,00,000/- per unit |
| 2 | For every Service Provider in case of sharing in addition to fee for installation of Towers. | Rs50,000/- per unit |
| 3 | Renewal fee for every service provider | Rs 50,000/- per unit |
| Opening of ATM booths | Opening of ATM booths | Opening of ATM booths |
| 1 | Application fee for one booth | Rs 10,000/- |
| Application for a Filling Station | Application for a Filling Station | Application for a Filling Station |
| 1 | Application fee for a filling station | Rs 40,000/- |
- The owner shall be allowed to re-submit the revised proposal after complying with all the objections raised by the Corporation/Council within a period of one year from the date of rejection after which fresh shall have to be paid. In the event of a building permit not issued, 50% of the fees so paid shall be returned to the owner.
8. Time limit for disposal of applications
i) If within 30 days of the receipt of the notice under Bye-law 3 of these bye-laws, the Corporation/Council fails to intimate in writing to the person. who has given the notice of its refusal or sanction, the notice with its plans and statements shall be deemed to have been sanctioned provided nothing shall be construed to authorize any person to do anything in contravention of or against the terms of lease or titles of the land or against any other bye-laws regulation or ordinance, operating on the site of the work.
ii) The approval/NOC/refusal shall be issued by the outside agency within 15 days or within the time stipulated, failing which the approval/NOC of the outside agency such as Fire Services Department, Airports Authority of India, Manipur Pollution Control Board, Department of Forest, etc on the building plan shall be deemed to be issued. The sanctioning authority shall process the application for building permit accordingly.
iii) Once the plan has been scrutinized and objections have been pointed out, the owner giving notice shall modify the plan to comply with the objections raised and re-submit it, The Corporation/Council shall scrutinize the re-submitted plan and, if there be no further objections, the plan shall not be rejected.
iv) Notwithstanding anything contained therein the structure contravenes any bye-law or is adjudged structurally unsound, the person shall be deemed liable under these bye-laws.
-
Occupancy certificate: No building hereafter erected, re-erected or altered materially shall be occupied in whole or in part until the issue of an occupancy certificate in the form prescribed in Appendix-A by the authorized officer of the Corporation/Council, affirming that such building conforms in all respects to the requirements of these bye-laws and is fit for occupation.
-
Unsafe Building:- All buildings or structures which are structurally unsafe, insanitary or - not provided with adequate means or egress or which in relation to existing use constitute to hazard to safety or health for any reason of in-adequate maintenance, dilapidation or abandonment are, for the purpose of this bye-law, unsafe buildings. All such buildings shall be considered to constitute danger to public safety which shall be abated by repairs or demolition or as otherwise directly by the Corporation/Council.
-
Examination of Unsafe Buildings:-The authorized Officer of the Corporation/Council shall examine every building reported to be unsafe or damaged, and shall make a written record of such examination
-
Notice to owner and occupier:- Whenever the Corporation/Council, from the report of the authorized officer, find any building or structure, or portion thereof, to be unsafe as defined under Bye-law 10, it shall give to the owner and the occupier of such building or structure a written notice stating the defects thereof: This notice shall require the owner or the occupier within 30