85. Streamlining the building approval/sanction procedure (Ease of Doing Business)
Approval of the external bodies like Airport Authority of India (AAI), Fire Services etc. wherever required, the specific requirements of the external bodies are to be added in the Common Application Form (CAF) so that building proponent has to file all information at a single customized online application.
86. Options for reducing the timelines for approvals:
(a) Outsourcing procedures:
The urban Local Bodies may outsource work pertaining to clearances and appoint firms/ companies to undertake the work on behalf of the corporation/Council.
(b) Creating a Cell in all the Urban Local Bodies:
There is a need for creating a specialized cell in all the Urban Local Bodies which is manned by qualified personnel conversant with the procedures and the interpretation of development regulations. The Cell should be headed by a qualified Town Planner who should lead a team of Architects and Engineers to handle online submission and conveying the online approvals as well.
(c) Single Window System: all the Urban Local Bodies
(d) Town Planning Department shall work out the modalities for Single Window Clearance. Town Planning Department shall work out the modalities for Single Window Clearance in consultation with all the stake holders.
(e.g., Existing system of obtaining Planning Permission and Building Permission through Single Window.)
87. Risk based classification of building proposals
There is a need for make provisions for fast tracking building permission procedures for all non-automatic approvals. Therefore, in the spirit of “Ease of Doing Business” the buildings have been classified further on the basis of risk parameter/risk-based classification to clear the building permits on fast-track system.
88. Residential buildings
For approval of residential plotted and group housing buildings, risk-based classification shall be as per Table given below:
Table No 88.1 Risk Matrix for different residential buildings
| Risks | Very Low | Low | Moderate | High | |
|---|---|---|---|---|---|
| Criteria | Parameters | ||||
| Size of the plot | Square meters | Below 105 m² | 105-500 m² | Above 500 m² | All sizes |
| Height of building | Metres | Below 15 m | Below 15 m | Below 15 m | 15m and above |
| Use of the premise | Various categories | Residential plotted | Residential plotted | Residential plotted | Group Housing |
* Group housing area is minimum 2000 sqm.
Suggested Fast tracking tools:
For Very Low Risk Buildings:
In case of standard building plans by the authority for residential plots up to 105 sqm. in size and forming part of the approved layout plan, the owner shall be entitled to sign such standard plans and the required documents for sanction. In such cases, certificate from professionals would not be necessary and the owner shall be bound to follow the approved standard plan in detail.
For Low-Risk Buildings:
A competent professional (qualification and competence as per Appendix-A) shall be empowered to issue the building permit, but only after submitting the plan along with requisite documents and fees to the concerned local body. If the owner/professional desires to get the building plan sanctioned by the local body, building plans prepared by a qualified architect/engineer will have to be submitted to the concerned local body along with the fees and other requisite documents and the local body shall grant the building permit within 10 days.
For Moderate Risk buildings:
Building plans and the building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
For high-Risk Buildings:
Clearance from Fire Department and other necessary clearances from AAI, NMA and other Agencies have to be obtained. Building Plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
89. Storage/Warehouses Buildings
For approval of the buildings meant for use as storage buildings/warehouses/godowns/risk-based classification shall be as per Table
| Very Low | Low | Moderate | High | |
|---|---|---|---|---|
| Area on all floors/Built up area | Upto 250 m² | Above 250 m² and upto 2000 m² | Upto 2000 m² | Above 2000 m² |
| Height of building | Below 15 m | Below 15m | Below 15m | Below 15m |
| Abutting Road | Min 12 m | Min 12 m | Min 12 m | Min 12 m |
| Type of Material storage | Category A | Category A | Category B (Stacking height-medium) | Category B (Stacking height-High) |
Note:
The level of Risk is classified according to the material stored in the warehouse/storehouse.
Suggested modes of fast tracking:
For Very Low Risk Buildings:
A competent professional (qualification and competence as per APPENDIX-A) shall be empowered to issue the building permit but only after submitting the plan along with requisite documents to issue the building permit, but only after submitting the plan along with requisite documents and fees to the concerned local body, he shall apply online to the local body and the local body shall grant the building permit within 10 days.
For Low-Risk Buildings:
Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
For Moderate Risk Buildings:
Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
For High-Risk Buildings:
Building Plans will have to be prepared by a qualified architect and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 30 days.
Industrial Buildings:
For approval of the building meant for use as storage buildings/warehouses/godowns, risk-based classifications shall be as per Table below
| Risks | Low | Moderate | High | |
|---|---|---|---|---|
| Criteria | Parameters | |||
| Size of the plot | Square meters | Upto 350 m² | About 350 m² | All sizes |
| Height of the building | Meters | Less than 15 meters | Less than 15 meters | 15 m and above |
| Abutting Road width | Meters | Min.12 m | Min.12 m | Min.12 m |
The level of risk is classified according to the size and height of the industrial building proposed.
Suggested mode of Fast tracking;
For Low-Risk Buildings:
-
Deemed Approval with Self- Certification
-
Plans to be submitted along with Structural drawings which does not require sanction.
For Moderate Risk Buildings:
-
Plans to be submitted to the empanelled professional.
-
Fire/Structural safety certification by Fire Services/ Structural Engineers.
-
Approval to be granted within 10 working days by the empanelled professional.
-
Approved plan to be submitted to ULB/DA.
For High-Risk Buildings:
-
Online Application
-
Immediate acknowledgement by software.
-
Fire/Structural safety Certification by Fire Services/ Structural Engineers.
-
Approval by ULB/DA within 20 working days.