76. Installation of Communication Towers:
- Definition: Communication tower shall include antennae fixtures, fabricated antenna, tower to install the telephone lines and transmission towers. This will not include the antennas installed for domestic purpose, namely television antennas or dish antennas.
2) Application for permission:
I. Location: The telecommunication Infrastructure shall be either placed on the building roof tops or the ground or open space within the premises.
II. Installation of base station antenna shall be allowed only on:
a. The building which abuts on minimum 9.00-metre-wide road in order to reduce the risk caused by an earthquake or wind related disaster.
b. The existing sites of the Cell Towers abutting on roads having ROW less than 9.00 metre could only be regularised after specific clearance from the Fire Department regarding the width of the road.
c. The base station antennas should at least be at least 3 metres away from the nearby building and antennas should not directly face the building. Further, the lower end of the antenna should be at least 3 metre above the ground or roof.
d. Sign Boards/Warning signs are to be provided at Base Station Antenna sites which should be clearly visible and identifiable. A warning sign should be placed at the entrance of each zone.
e. “Warning Sign” should discourage longer stay in the zone, even for the maintenance person. The sign board may contain the following text:
-
Danger! RF Radiations, Do not enter.
-
Restricted Area
f. The Operator shall display on board (minimum size 24”x48”) at conspicuous space of the building at Ground Floor the following details:
-
Operators Name & Address
-
Contact Persons Name, Address & Tel No.
-
Address of Complaint Redressing Authorities with Tel No.
-
Police Control Room: 000
-
Fire Control Room: 000
-
Ambulance: 000
-
Details of Insurance Policy.
g. The operators, who have erected Cell Towers without permission, shall apply to the Corporation/Council for regularisation within 30 days.
h. No towers shall be permitted to be erected within 100m radius of schools, colleges, hospitals, nursing homes, religious institutions, lifeline buildings and the like. Antenna should not face hospitals nursing homes, religious institutions, lifeline buildings and the like and should be placed at a minimum of 3mts above the base.
III. Type of structure:
a) Steel fabricated tower or antennas on M.S. pole
b) Pre-fabricated shelters of fibre glass or P.V.C. on the building roof top/terrace for equipment.
c) Masonry Structure/Shelter on the ground for equipment.
IV. Requirement: Every applicant has to furnish the following:
a) Obtain/procure the necessary permission from the “Standing Advisory Committee on Radio Frequency Allocation” (SACFA) issued by Ministry of Telecommunications.
b) Site plan in the scale of 1:200.
c) Before erection of cell tower, application shall be filed by the owner(s) and the mobile service provider. Copy of the agreement between the service provider and the owner shall also be submitted along with the application.
d) Drawing of tower with complete details including specifications of foundations and design parameters.
e) Height of the tower along with its elevation.
f) In case the tower is in the vicinity or adjoining to high- or low-tension line then the distance from the same shall be clearly indicated in the drawings. NOC from the Me SEB has to be furnished accordingly.
g) Erection of Tower shall only be permitted only on regularized buildings.
h) Produce the structural stability certificate from any one of the 6 (six) institutions are required to be obtained by the Cellular and Basic Cellular Operators:
Manipur Institute of Technology, Imphal
National Institute of Technology, Imphal
National Institute of Technology, Silchar
Indian Institute of Technology, Guwahati
Central Building Research Institute, Roorkee
Rail India Technical & Economic Services Ltd. (RITES), Delhi.
i) In case it is a roof top tower, the applicant has to produce/submit approved buildings plans along with the structural safety certificate from the registered structural engineer that the building can take the additional load of the tower. The certificate is to be vetted by any one of the following institutions:
Manipur Institute of Technology, Imphal
National Institute of Technology, Imphal
National Institute of Technology, Silchar
Indian Institute of Technology, Guwahati
Central Building Research Institute, Roorkee
j) For Ground Base Towers, a soil test report has to be submitted.
k) Submission of undertaking from the Operator that the installation of cell Tower does not cause any adverse effect to the health of human being of the area.
l) Indemnity bond to take care of any loss or injury due to accident caused by the tower (including a declaration to the effect that the application shall take special precaution for fire safety and lightning and he shall be solely responsible for paying all kinds of compensation and damages and would be responsible for any civil or criminal case arising there from).
3) Projections:
I. No Pager and/or Telephone Tower shall project beyond the existing building envelop of the building on which it is erected in any direction.
II. The distance of the tower from the electric line or pole or tower thereof shall not be less than the height of tower plus requisite distance from respective high- or low-tension line.
4) Inspection of tower:
The Executive Officer of the Corporation/Council or his authorised representative shall inspect the wireless telecommunication towers to:
I. Conduct inspections of the telecommunication tower and other facility once in every 6 (six) months to ensure its structural safety and continuing compliance with these bye-law.
II. Conduct inspections to check abandonment or discontinuation of use and issue notice of discontinuation/ notice for removal of the structures within 30 days from the date of notification.
5) Penalties for violation of Bye-law:
Whoever erects, materially alters or commences to erect, materially alters any transmission tower without the previous sanction of the Corporation/Council or violates the Tower permission sanction issued by the Corporation/Council or contravenes with the provisions of this bye-laws or who interferes or obstruct any authorised personnel in the discharge of his duties shall be guilty of an offence. The Corporation/Council shall:
-
Punish the person as per the provisions of the Manipur Municipalities act, 1994.
-
Take suitable action which may include demolition of un-authorized works, sealing of premises, prosecution and criminal proceeding against the offender, in pursuance of relevant laws in force, as decided by the Corporation/Council.
-
Take suitable action against licensed technical personnel and license may be withdrawn in case of an offence as decided by the Corporation/Council.
Impose a fine of not exceeding Rs 5,000/- (Rupees five thousand) only payable within one month from the date of final notification and to a further fine not exceeding two hundred rupees for every day during which the operator continues to violate this Bye-law. Final notification shall be issued only after the operator is given a reasonable opportunity of being heard for showing cause within a period of 30 days.
6) Renewal of No objection Certificate (NOC):
-
NOC issued by the Corporation/Council is valid for 5 (five) years only. The NOC shall be got renewed on payment of requisite fee as prescribed in section 7(1).
-
The Towers existing for more than 5 (five) years are also required to be renewed within 3 (three) months from the date of notification of this bye-law in the gazette on payment of requisite fee.
-
The Corporation/Council reserves its right to withdraw permission/NOC at any time without assigning any reason.
7) Sharing of tower/Co-location of Tower:
The telecom operators may share the towers for fixing their respective antennas. The same are required to adhere to the prescribed technical requirements, so as to curtail multiplicity of towers as well as to optimize the use of the existing ones.
77. In-Building Solutions for Common Telecommunication Infrastructure
For installation of In-Building Solution (IBS) / Smart Connectivity infrastructure, the procedure laid down in Annexure-C shall be followed.
78. Gasoline (Motor Fuel) Filling Stations and Gasoline Filling cum Service Stations:
1) Definitions:
a) The term “Filling station” is a piece of retail business engaged in supplying and dispensing of Gasoline (Motor Fuel) and motor oil essential for the normal operation of automobiles.
b) The term “Filling cum Service Station” is a place of retail business engaged in supplying goods and services essential for the normal operation of automobiles. These include dispensing Gasoline and Motor oil the sales and services of tyres, batteries and other automobiles accessories and replacement item and washing and lubrication. They do not include the body of tender work, painting or other major motors repairs and over hauling.
2) Information accompanying Notice:
i. Clearance of installation of the Petrol Pump under provisions of the Petroleum Act, 1934 read with Petroleum rule, 1973 rules 155 of the Petroleum Rule 1937 sanctioned by the District Magistrate.
ii. N.O.C. obtained from Public Works Department for all proposals whether in the National Highway, State Highway etc. While N.O.C. is issued, due consideration is to be given on factors like congestion of the locality, movement of vehicles traffic in the particular road etc.
iii. Layout plans for installation of the facilities at the retail outlet such as underground tank, pipeline, dispensing pump, sale room/office drainage, toilets, electrical layout approved by the Explosive Department, Government of India.
iv. Photocopy of receipt of the application fee issued by the Corporation/Council.
3) Layout Plans
i. The distance to be kept from the dispensing pump of the three side i.e., side and rear should not be less than 15 meters distance from a residential house. The frontage should conform as per the Indian Road Congress 13–1967 (IRC– 13-1967). For installation of Petrol Pump the recommended practice for location and layout of roadside, motor filling and motor fuel filling-cum service station should conform as per the Indian road congress 12-1983 and 13-1967 (IRC-12-1983), (IRC-13-1967).
ii. The following shall be applicable for locating the petrol pump cum service stations:
A) Minimum distance from the road intersections.
(a) For minor roads having less than 30 m R/W: 50 m
(b) For major roads having R/W 30 m or more: 100 m
B) The minimum distance of the property line of pump from the center line of the Road should not be less than 15 meters on roads having less than 30 m R/W. In case of roads having 30 m or more R/W the R/W or the road should be protected.
C) Plot Size
(a) Only filling stations 30 m x 17 m and small size 18 m x 15 m (for two and three wheelers)
(b) Filling-cum-service station minimum size 36 mt. x 30 mt. and maximum 45 m x 33 m
(c) Frontage of the plot should not be less than 30 m
79. Automated Teller Machine (ATM):
-
Definition: ATM stands for Automated Teller Machine and basically used to perform bank transactions like withdrawal of money and to view bank statements.
-
Requirement: Every applicant has to furnish the following:
-
Site plan in the scale of 1:200 prepared by a licensed architect.
-
A photocopy of the receipt of the Application Fee issued by the Corporation/Council.
-
Before opening, application shall be filed by the owner(s) and the Bank. Copy of the agreement between the Bank and the owner shall also be submitted along with the application.
-
NOC from Transport Department, Traffic Police and PWD. While N.O.C. is issued, due consideration is to be given on factors like congestion of the locality, movement of vehicles traffic in the particular road, recommendations of the Master Plan for the respective town etc.
-
Any other information / data required by the Corporation/Council.
80. Sanction/Approval for construction/installation:
All Building Plan Sanctions, Revalidation, Installations of Towers, Issue of permission for erection of filling stations and opening of ATM booths shall be examined under this Bye-law and issue NOC or Refusal for sanction within 30 days of the receipt of notice as envisaged under Section 8(1) after obtaining Planning permission under Section 17(2) of this Bye-law.