9.1 The Authority shall levy the following fees:
9.1.1 Every application for permission for building operation or development shall be accompanied by a building fee as specified in these bye laws.
9.1.2 Fees for retention of structures for temporary period shall be as decided by the Authority from time to time.
9.1.3 Fees for change of occupancy as decided by the Authority from time to time.
9.1.4 Fees for change of land use as decided by the Authority with permission to State Government from time to time.
9.1.5 Any other fee decided by the authority with the approval of the Urban Development and Housing Department or concern Department.
9.1.6 The concern department may change the fees prescribed in these bye laws through a notification from time to time.
9.2 Development permit fee.- The scale of fees for development permit shall be as per Table 2.
| Sl. | Area of Plot | Nagar Panchayat (Rs) | Municipal Council (Rs) | Municipal Corporation/RRDA/MADA/IADA (Rs) |
|---|---|---|---|---|
| (i) | (ii) | (iii) | (iv) | (v) |
| 1 | upto 1.0 hectare | 6000 | 8000 | 10000 |
| 2 | above 1.0 hectare & up to 2.5 hectare | 12000 | 15000 | 20000 |
| 3 | above 2.5 hectare & up to 5.0 hectare | 16000 | 20000 | 30000 |
9.2.1 For development permit above 5 hectare for every addition of 1 hectare or part there will be an additional fee of Rs.2000 per hectare.
9.2.2 In the case of development permit for non residential use the above fees shall be doubled for different sizes of land