(A) Non-Compoundable Items:
Any deviations except those set in para "AA" hereunder, from the maximum, minimum prescribed limits regarding:
(1) Coverage,
(2) F.A.R.
(3) Setbacks,
(4) Open spaces,
(5) Total height of the building
(6) No. of floors,
(7) No. of DUs and density
(8) Parking norms,
(9) Light and Ventilation provisions,
(10) Use
(11) All other provisions of these bye-laws except item given in para 'B' below shall not be compounded/ regularized and shall have to rectified by altering/ demolition at the risk and cost of owner. Besides this any other action as per terms and conditions of lease and provisions of Act shall proceed.
(A.A) Compounding Excess Coverage/FAR
(i) Deviations in the coverage / F.A.R. to the extent of 10% of the permissible coverage / FAR in building(s) use premises, other than building(s) use premises where 100% ground coverage and fixed height is allowed as per Architectural control forming part of comprehensive schemes like District Centre, Community Centres, Cluster Court Housing etc. may be compounded after levying penalty at the following Rates:
Rates of excess coverage/floor area:
Up to 10% of excess coverage / F.A.R. a one time compounding fee equivalent to the land rated in the concerned locality applicable at the time of the application for compounding.
PART-I
307
(ii) For excess coverage / F.A.R. for above 10%
Any excess coverage / F.A.R. above 10% would be liable to demolish to that extent.
(iii) Compounding at set back Infringements
The infringements of the set backs maximum to the extent of 30 cm. (1 ft.) may be compounded by way of levying compounding fee at the following rates:
| Infringements | Residential Buildings | Non-Residential Buildings |
|---|---|---|
| Upto 15 cm. (6 inch) | ₹1000 per sq. m. of area infringing the set back | ₹2500 per sq.m. of area infringing the set back |
| Above 15 cm.(6 inch) | ₹2000 per sq. m. of area infringing the set back | ₹5000 of area of the infringing the set back |
(B) Compoundable Items :
If a building or part thereof has been constructed unauthorizedly, i.e. without obtaining the requisite building permit from the concerned Authority as required under the building bye-laws, the same shall be compounded at the following rates provided the building or part thereof so constructed other wise conforms to the provisions contained in the Building Bye-laws and Master / Zonal Plan regulations. For this party shall have to submit the request for building permit in the prescribed procedure.
Rates:
(a) ₹ 50 per sq m. of the covered area constructed unauthorizedly in residential building up to 500 sq m. Plot size.
(b) ₹ 100 per sq m. of the covered area constructed unauthorizedly in the building categorized below:
- All Government Public and Semi-Public and Utility Buildings.
- Religious, Institutional and Educational Buildings.
(c) ₹ 250 per sq m. of the covered area constructed unauthorisedly
- Residential Building above 500 sq m. plot size, Group Housing and Guest Houses.
● Industrial Buildings:
● Storage buildings (underground or above ground)
(d) ₹ 1000 per sq m. of covered area constructed unauthorisedly.
- Cinema and Theatre Building.
- Petrol Pumps (Filing/Service Station)
- Hazardous Buildings.
• Commercial/Business Buildings
(1) The building not covered specifically under the above categories shall be compounded as decided by the Authority, considering the merit of each Individual case.
(2) Items which are exempted from the calculations of the coverage and F.A.R. e.g. cupboards, canopy, basement, and mezzanine, loft, watchman cabins, etc. but constructed unauthorisedly without obtaining prior permission from the Authority, but within the permissible limits shall also be compounded / regularized at the rate prescribed above.
(ii) Deviations of the building bye-laws other than specified in (A) (Non-compoundable) Deviation up to the maximum extent of 10% from the maximum / minimum prescribed limit (as prescribed by the building bye-laws) shall be compounded at the following rates:
[ PART-I
(a) In case of deviations of areas of various components of the building, the rate of penalty will be @ ₹ 50 per 1% deviation.
(b) For deviations in terms of height the penalty shall be @ ₹ 50 per 1% of deviation for every 10 sq m. or part thereof of the affected area.
(c) Deviations from the prescribed limit of width, length, penalty shall be @ ₹ 50 per 1% of the deviation for every 10 sq m. or part thereof of the affected area.
Notes:
(1) Notwithstanding the provisions above, no penalty shall be levied for the first 3% of deviation but in case the deviation limit exceed 3% penalty shall be levied at above rates for the total deviation up to 10%.
(2) The penalties of the above rates as given in (ii) (a), (b), and (c) shall be charged for each deviation and for every component of the building separately.
(a) In case of increase in size of canopy in front open space form the prescribed limits of bye-laws the same shall be charged @ ₹ 100 per sq m.
(b) End walls up to 0.9 m. in width in a terrace type construction constructed purely as an architectural feature ₹ 50 each.
(c) Enclosing of front balcony with jail wall which is being used as a part of staircase ₹ 500 sq m.
(d) (i) An open Urinal Wall up to 1.7 m. height ---- No Penalty.
(ii) Water storage Tank over open urinal with walls up to 1.70 m. in height ---- No
Penalty, if sanctioned. If not sanctioned, ₹ 500 each.
(e) All roof projections beyond permissible limit of Bye-laws as specified shall be counted towards F.A.R. calculations if other wise the same do not infringe up to any other Bye-laws.
(f) Plinth steps in setback portion ---- ₹ 100 each.
(g) Extra slab in mumty constructed without sanction shall be compounded at the rate given in (B) (compoundable item) provided it does not infringe upon the provision of any other Bye-laws.
(h) Partition wall provided without sanction at any floor if the same are not infringing upon the provision of any other bye-laws ---- ₹ 50 per sq m. of the surface area of the wall (i.e. length X height).
(i) Projections / sunshade / (not more than 0.45 m. in width on public streets / roads over window opening above first floor shall be objected. However, at Ground Floor these shall be not permitted.
Note:
The Authority if satisfied that there are other deviations of general nature, which are not described above, may fix rates for compounding such deviations. However, there shall be no further relaxation in F.A.R. and coverage over that permitted above.
PART-I]
309
FORM I(A) (See clause-4 in Chapter II)
Form for first application to erect, re-erect, demolish or to make material alteration in a building To:
The Member-Secretary,
---- Planning Authority,
-
Sir,
I hereby give application that I intend to erect / re-erect / demolish or to make material alteration in the building on Plot No ----in R.S No----, T.S.No----, Ward----, Block----, in ----Revenue Village, ----Municipality / Commune ,----in accordance with the Puducherry Building Bye-laws and Zoning Regulations and I enclose herewith the documents as per checklist 1-A / 1-B / 1-C annexed to this application. I request that the construction may be approved and permission accorded to me to execute the work.
Signature of the applicant
Name of applicant (in Block letters)
Address of the applicant :
Dated :