The building unit intended to be developed shall be in conformity with Regulation on requirement of site. Generally all development work for which permission is required shall be subject to inspection by the Competent Authority as deemed fit.
The applicant shall keep a board at site of development mentioning the Re-survey No, Town survey No, Block No, Ward No, Plot No., name of the lay out if any, concerned Revenue Village name, concerned Municipality / Commune Panchayat, Region etc. name of owner and name of the Registered Architect / Registered Engineer / Registered Structural Engineer.
10.1 Record of Construction Progress:
(a) Stages for recording progress certificate and checking:
(i) Plinth, in case of basement before the casting of basement slab.
(ii) First storey
PART-I
255
(iii) Middle storey in case of High-rise building.
(iv) Last Storey.
(b) At each of the above stages, the owner / developer / Builder shall submit to the Planning Authority a progress certificate in the given formats (Form No.13 -16) This progress certificate shall be signed by the Registered Engineer.
(c) The progress certificate shall not be necessary in the following cases:
(i) Alteration in Building not involving the structural part of the building.
(ii) Extension of existing residential building on the ground floor up to maximum 15 sq.m. in area.
(d) Completion Report:
(i) It shall be incumbent on every applicant whose plans have been approved, to submit a completion report in Form No.17.
(ii) It shall also be incumbent on every person / agency who is engaged under this Regulations to supervise the erection or re-erection of the building, to submit the completion report in Form No.18, 19 and 20 prescribed under these Regulations.
(iii) No completion report shall be accepted unless completion plan is approved by the Planning Authority.
(e) The final inspection of the work shall be made by the concerned Planning Authority within 21 days from the date of receipt of notice of completion report.
10.2 Issue of Occupancy Certificate:
The Planning Authority before issuing occupancy certificate shall ensure that following are complied from consideration of safety against natural hazard.
(i) Certificate of Lift Inspector has been procured & submitted by the owner, regarding satisfactory erection of lift.
(ii) The Certificate of Competent Authority and or Fire Department for completion and or fire requirements as provided in these regulations has been procured and submitted by the owner.
(iii) If any project consists of more than one detached or semi detached building / buildings in a building unit and any building / buildings there of is completed as per provisions of the Bye-laws and Zoning Regulations (such as parking, common plots, internal roads, height of the building, infrastructure facilities, lift and fire safety measures), the Planning Authority may issue Completion Certificate for such one detached or semi detached building / buildings in a building unit.
The Occupancy Certificate shall not be issued unless the information is supplied by the owner and the Registered Architect / Registered Engineer concerned in the schedule as prescribed by the Planning Authority from time to time.
11. MAINTENANCE OF BUILDINGS :
In case of building older than fifty years, it shall be the duty of the owner of a building, to get his building inspected by a Registered Structural Engineer (RSE) within a year from the date of coming into force of these regulations. The Structural Inspection Report (Form No.22) shall be produced by the Owner to the Planning Authority. If any action, for ensuring the structural safety and stability of the building is to be taken, as recommended by RSE, it shall be completed within five years. For other buildings, the owner shall get his building inspected after the age of building has crossed forty years. The procedure shall be following as per above regulation.
12. PROTECTIVE MEASURES IN NATURAL HAZARD PRONE AREAS :
In natural hazard prone areas identified under the land use zoning regulations, structures buildings and installations which cannot be avoided, protective measures for such construction / development should be properly safeguarded based on the suggestions given in Appendix-A.
[ PART-I]
- REPEAL AND SAVINGS :
(a) The Puducherry Building Bye-laws and Zoning Regulations, 1972 are hereby repealed.
(b) Notwithstanding such repeal anything done or any action taken under the said Bye-laws and Regulations shall be deemed to have been done under the corresponding provisions of these Bye-laws and Regulations respectively.