(1) Effective measures shall be taken within the premises for conservation of rainwater. Workable rooftop Rain Water Harvesting arrangements shall be provided as an integral part of all new building constructions for the following occupancies, namely, residential, offices, public buildings and commercial buildings such as malls, shopping centers and cinema halls, educational and health institutions and industry with terrace area as mentioned in the table below:
TABLE
| Occupancy | Terrace area / Plot area |
|---|---|
| Residential | Terrace area of 100 Sq.m. or more /Plot area of 200 Sq.m. or more |
| Offices and Public buildings, Commercial buildings,Educational and Health Institutions and Industrial buildings | Terrace area 200 Sq.m. or more / Plotarea 300 Sq.m. or more |
(2) The details of the Rain Water Harvesting (R.W.H.) System shall be shown in the site plan enclosed along with the application in Form I seeking approval for construction and permission to execute the work. Building permission by the Planning Authorities shall not be issued unless adequate R.W.H. systems are provided in the building plan submitted. The Occupancy Certificate for new buildings shall be issued by the Planning Authorities only on implementation of the R.W.H. system by the applicant. The Authorities concerned shall not extend power, water supply and sewer connections to the buildings unless the owner of the building obtains the occupancy certificate from the concerned Planning Authority.
(3) Exemption in respect of implementing the Rain Water Harvesting system may be granted in respect of cases where water logging is common or in areas with impermeable sub-soil conditions to considerable depth. The assessment of the conditions of the sub-soil may be made by the Planning Authority in consultation with the State Ground Water unit of the Agriculture department, Puducherry.
(4) The roof top Rain Water Harvesting arrangements shall have the following components, namely: Roof's catchment area;
Flat roofs sloped towards edges with rainwater outlet pipes and roof gutters for sloping roofs;
Down pipe for transporting rainwater from roofs to the ground level;
First flush pipe arrangement for diverting debris, dirt and dust on the roofs; and
A filter unit comprising a container or chamber filled with filter media at the ground level.
(5) The other components on how the rain water is to be utilized, that is, for ground water recharging or for direct use, shall be as follows:
[ PART-I
A. For storing and reuse of the rainwater:
A storage tank that has provision for drawing water and for spillover of excess water is to be provided; and
For charging the ground water aquifers, the water from the filter unit shall be diverted to suitable structures like dug wells, bore wells, recharge trenches or recharge pits for charging the groundwater aquifers.
B. For ground water recharging:
Through direct channeling of surface water to abandoned wells or hand-pumps, recharge pits or recharge trenches, or to through recharge shafts.
Directing of harvested rain water to pumping wells.
Note: Additional arrangements for carrying the spillover water from storage tank to recharge well or percolation pit shall be provided.
(6) The owner(s) / occupier (s) shall maintain the rooftop rainwater harvesting arrangements and artificial ground water recharge arrangements in good working conditions.
(7) The Planning Authorities and Local Bodies of the Union territory of Puducherry shall enforce workable artificial ground water recharging arrangements as an integral part of all new building constructions through collection of roof top rainwater.
B. Regulations for Re-use of Waste Water:
(1) Effective measures shall be taken within the premises of various categories of buildings as mentioned in the table below for reuse of waste water:
TABLE
| Occupancy | No. of dwelling units / Plot area |
|---|---|
| Apartments or group housing complexes | 20 dwelling units or more |
| Offices and Public buildings, Commercial buildings, Educational & Health Institutions and Industrial buildings | Plot area of 2000 Sq.m. or more / Minimum sullage discharge of 10,000 litres and above per day. |
(2) The details of the water reuse infrastructure facilities such as plumbing plans, waste water treatment and disposable arrangements shall be shown in the site plan enclosed along with the application in Form-I seeking approval for construction and permission to execute the work. Building permission by the Planning Authorities shall not be issued unless adequate water reuse arrangements are provided in the building plan submitted. The Occupancy certificate for new buildings shall be issued by the Planning Authorities only after water reuse arrangements are completely implemented. The Authorities concerned shall not extend power, water supply and Sewer connections to the buildings unless the owner of the building obtains the occupancy certificate from the concerned Planning Authority.
(3) The recycling of waste water arrangements shall have the following components:
Separate conveyance system for sewage and sullage to facilitate reuse of sullage water for treatment and for reuse;
Suitable storage and treatment facilities for collection of sullage water. The waste water treatment facilities shall fulfill the standards specified by the Puducherry Pollution Control Committee, Puducherry; and separate over head tank and pumping facilities for fresh water and reuse water.
(4) The use of recycled water for flushing, washing and for watering gardens shall be after primary, secondary and tertiary treatments as advised by the Puducherry Pollution Control Committee. The Planning Authorities and Local Bodies of the Union territory of Puducherry shall enforce workable recycling of waste water arrangements as an integral part of all new building constructions through collection of sullage water".