7.1 Obtaining Building Use Permission
7.1.1 Notice of Completion of Construction and Building Use Permission
The Owner and the Architect on Record for the building shall be responsible for notifying the Competent Authority of completion of construction and for certifying that the construction complies with the sanctioned design and specifications. Notice of Completion of Construction and Compliance Certification shall be made in the format prescribed in Form No. 12, and shall be accompanied by documents and drawings as prescribed by the Competent Authority in Schedule 11. The format for submission of drawings, specifications and documents is specified in Schedule 4.
Subsequent to notifying the Competent Authority about the completion of construction in compliance to the regulations, application for Building Use Permission may be made to the Competent Authority in the format stipulated in Form No. 13.
7.1.2 Fees
Building Use Permission Fees shall be determined by the Competent Authority and are listed in Schedule 13. It shall be the responsibility of the Owner to deposit Building Use Permission Fees with the Competent Authority along with the Application for Obtaining a Building Use Permission.
7.1.3 Final Inspection
Following receipt of the Notice of Completion of Construction and Compliance Certification, the Competent Authority shall undertake final inspection of construction for ensuring compliance to sanctioned design, specifications and other aspects of the building as stated in Schedule 15. The Competent Authority shall inform the applicant within 21 days of receipt of Notice of Completion of Construction.
If, on inspection, the Competent Authority is satisfied that the construction of the building complies with the sanctioned design and specifications, it shall grant a Building Use Permission.
If the construction is found not to comply with sanctioned design and specifications, the Competent Authority shall communicate queries regarding the construction and/or directions to ensure compliance to the Owner and the Architect on Record or Engineer on Record. Failure to comply with directions, as may be issued by the Competent Authority, may result in revocation of the Development Permission. The Architect on Record or Engineer on Record shall respond to queries and notify the Competent Authority of having undertaken compliant modifications.
7.1.4 Grant/ Refusal of Building Use Permission
The final inspection of the work and communication of the decision about the grant of the Building Use Permission shall be made by the concerned Competent Authority within 21 days from the date of receipt of Notice of Completion of Construction and Compliance Certification. If the Competent Authority is satisfied that the construction of the building complies with the sanctioned design and specifications and other requirements as per Schedule 15, it shall grant a
Building Use Permission in the format stipulated in Form No. 14. Reasons for grant/refusal of Building Use Permission shall be communicated to the applicant.
In cases where the building construction is as per regulations but the Owner of the adjoining building or Chairman/Secretary of the Cooperative Society are not giving consent at the time of Building Use permission, the Competent Authority may issue permission after giving opportunity of hearing to the Owner of the adjoining Building or Chairman/Secretary of the Cooperative Society considering the merits and demerits of individual case.
7.1.5PEN Alties
Penalties for not complying with Regulation No. 7.1 are stipulated in Schedule 13.
7.2 Obtaining Permission to Change Sanctioned Use of Building
7.2.1 Application
Application for obtaining Permission to Change Sanctioned Use of Building shall be made by the Owner, for which a change in use is proposed and the Persons on Record, in the format prescribed in Form No. 13.
7.2.2 Drawings, Specifications and Documents
Drawings, specifications and documents to be submitted along with Application for Permission to Change Sanctioned Use of Building are listed in Schedule 11. The format for submission of drawings, specifications and documents is specified in Schedule 4 and Schedule 15.
7.2.3 Fees
Fees and other charges for obtaining Permission to Change Sanctioned Use of Building are listed in Schedule 13.
7.2.4 Scrutiny of Application
The Competent Authority shall undertake scrutiny of the Application to Change Sanctioned Use of Building. Lack of compliance with Development Regulations and/or queries pertaining to the application shall be communicated. Acceptance or rejection of compliant modifications in the application and responses to queries shall be communicated.
7.2.5 Grant / Refusal of Permission to Change Sanctioned Use of Building
A permission to Change Sanctioned Use of Building shall be issued to the applicant when the Competent Authority is satisfied that the proposed change of use of the building complies with these Regulations. Reasons for rejection of application shall be communicated.
7.2.6 Penalties
Penalties for not complying with Regulations No. 7.2 are stipulated in Schedule 13.