5.1 Obtaining a Development Permission
5.1.1 Application
Application for Development Permission shall be made by the Owner of the Building units/land on which the building is proposed in the format prescribed in:
Form No. 5 for Buildings, and for Sub‐division and Amalgamation and Form No. 5A for Brick Kiln, Mining and Quarrying.
5.1.2 Scrutiny Fees
Scrutiny Fees and other charges for obtaining a Development Permission shall be determined by the Competent Authority and are listed in Schedule 13.
5.1.3 Drawings, Specifications and Documents
Drawings, specifications and documents to be submitted along with Application for Obtaining a Development Permission shall be determined by the Competent Authority and are listed in: Schedule 3a for Building, Schedule 3b for Sub‐division and Amalgamation and Schedule 3c for Brick Kiln, Mining and Quarrying. The format for submission of drawings, specifications and documents is specified in Schedule 4.
5.1.4 Scrutiny of Application
On receipt of the application for Development Permission, the Competent Authority shall undertake scrutiny of the Application for Development Permission and communicate to the applicant.
Lack of compliance with Development Regulations and/or queries pertaining to the Building‐unit shall be communicated.
Acceptance or rejection of compliant modifications in the design and specifications of the proposed building and responses to queries shall be communicated. Acceptance or rejection of further compliant modifications in the application and responses to queries shall also be communicated.
5.1.5 Grant or Refusal of a Development Permission
Development Permission shall be granted to the applicant when the Competent Authority is satisfied that the design and specification of the proposed building comply with the Development Regulations. On receipt of the application for Development Permission, the Competent Authority may grant or refuse permission to the applicant as per the provisions of the Act within ninety days from the date of payment of the Scrutiny fees. The permission may be granted with or without conditions or subject to any general or special orders made by the State Government in this behalf.
The Development Permission shall be in the format of Form No.7 and it shall be issued by an officer authorised by the Competent Authority in this behalf. Reasons for rejection of application shall be communicated to the applicant.
In cases where the building design requirements are as per regulations but the co owner of the property or Chairman/Secretary of the Cooperative Society are not giving consent at the time of development permission, the Competent Authority may issue permission after giving opportunity of hearing to the co owner of the property or Chairman/Secretary of the Cooperative Society considering the merits and demerits of individual case.
5.1.6 Penalties
Penalties for not complying with Regulation No. 5.1 are stipulated in Schedule 13.
5.2 Revising a Development Permission
5.2.1 Application
Application for Revising a Development Permission shall be made by the Owner or Developer of the Building‐unit, in the format prescribed in Form No.8.
5.2.2 Fees
Development Permission Fees and other charges for revising a Development Permission shall be determined by the Competent Authority and are listed in Schedule 13.
5.2.3 Drawings, Specifications and Documents
Drawings, specifications and documents to be submitted along with Application for Revising a Development Permission shall be determined by the Competent Authority and are listed in Schedule 3a, 3b and 3c for the respective uses. The format for submission of drawings, specifications and documents is specified in Schedule 4.
5.2.4 Scrutiny of Application
The Competent Authority shall undertake scrutiny of the Application for Revising a Development Permission.
Lack of compliance with Development Regulations and/or queries pertaining to the Building‐unit shall be communicated. Acceptance or rejection of compliant modifications in the application, modifications made in the design and specifications of the proposed building and responses to queries shall be communicated. Acceptance or rejection of further compliant modifications in the application and responses to queries shall also be communicated.
5.2.5 Grant or Refusal of a Revised Development Permission
A Revised Development Permission in the format prescribed in Form No. 7 shall be issued to the applicant when the Competent Authority is satisfied that the design and specification of the proposed Building‐unit comply with Development Regulations. Reasons for r ej e c t i o n of application shall be communicated to the applicant.
5.2.6 Penalties
Penalties for not complying with Regulation No. 5.2 are stipulated in Schedule 5.
5.3 Revalidating a Development Permission
5.3.1 Application
Application for Revalidating a Development Permission shall be made by the Owner or Developer of the building, before the expiry of the Development Permission. The revalidated period shall in no case exceed three years in the aggregate that is for a total period of four years.
Lapsed Development Permission may be revalidated after the expiry of the original Development Permission, within a period of six months, with payment of penalty charges.
Revalidation of a Lapsed Development Permission after one and half year from the issue of the original Development Permission shall not be permitted. New application for Development Permission shall have to be made.
5.3.2 Fees
Development Permission Revalidation Fees for revalidating a Development Permission shall be determined by the Competent Authority and are listed in Schedule 13.
For revalidating a lapsed Development Permission, penalty charges shall be applicable and are listed in Schedule 13.
5.3.3 Documents
Documents to be submitted along with Application for Revalidating a Development Permission shall be determined by the Competent Authority and are listed in Schedule 7. The format for submission of documents is specified in Schedule 4.
5.3.4 Scrutiny of Application
The Competent Authority shall undertake scrutiny of the Application for Revalidating a Development Permission, in context of proposals of Draft Development Plan‐2035, and communicate queries pertaining to the application.
Acceptance or rejection of responses to queries shall be communicated to the applicant.
5.3.5 Grant or Refusal of a Revalidated Development Permission
A Revalidated Development Permission in the format prescribed in Form No. 7 shall be issued to the applicant when the Competent Authority is satisfied that the design and specification of the proposed development comply with the Development Regulations. Reasons for grant or refusal of Revalidating a Development Permission shall be communicated to the applicant.
In case of any change to the Building‐unit which affects the approved layout or building blocks, Development Permission may not be revalidated. New application for Development Permission shall have to be made.
5.3.6 Penalties
Penalties for not complying with Regulation No. 5.3 are stipulated in Schedule 13.
5.4 Common Protocol
For Facilitation to investor under Investment Facilitation Portal (IFP) following procedure must be adopted by competent authority where ever procedure is narrated in this document.
-
Competent Authority must made all procedure, protocols and checklist available online.
-
Application received online by competent authority and Investor Facilitation Portal.
-
Compliance at any time shall be available online on competent authority website and Investor Facilitation Portal.
-
Competent Authority must display the grant of permission or rejection or suspension online in public domain on Competent authority website and Investor Facilitation Portal at time new permission ,renewal and revalidation of application.
-
Inspected report of each time must be online on respective website and Investor Facilitation Portal by competent authority within 48 hrs.
-
Competent authority allocates the inspector randomly and it must be on computerize.
-
Integrate the payment gateway online.
-
For any development permission, if site inspection is required for different purposes, all the officers or the inspectors required, to carry out inspections shall visit jointly on a prescribed date. The competent authority shall ensure that such date of joint inspection is communicated to applicant at least three days in advance and also ensure that the inspectors carry out the inspection on specified .
GDCR 2016