9.0 Procedure During Construction
9.1. Responsibilities of the Applicant : - Applicant shall obtain, where applicable, from the Authority, permission relating to building, zoning, occupancy, advertisements signs, street, highways, signage, grades, sewers, water mains, plumbing, gas pipeline, electricity, flying control surfaces, blasting and all other permissions required in connection with the carrying out of development
ER , - , , 3 -,R/ -, 3
Neither the grant of permission nor approval of the drawing, nor inspection by the Authority during erection of the building shall in any way relieve the applicant for development of such building from full responsibility for carrying out work in accordance with these provisions and safety norms as prescribed by the Bureau of Indian Standards.
9.2 The Applicant shall : -
a. At any reasonable time for the purpose of enforcing these provisions, permit authorized officers of the Special Planning Authority to enter the land for which the Commencement Certificate has been granted for carrying out development ;
b. In case of building operations, on completion up to plinth level and fifteen (15) working days before the commencement of further work, give notice to the Authority ;
c. Give written notice to the Authority regarding completion of the development duly signed by the Technical Person ;
d. Obtain Occupancy Certificate from the Authority prior to any occupancy or use of development so completed ;
e. To ensure conformity with the requirements of these provisions, keep available for inspection during the carrying out of development and for such period thereafter, as required by the Authority, the records of the tests which are made on any material;
f. Keep a copy of the Commencement Certificate pasted in a conspicuous place on the property in respect of which the permission to develop is granted ;
g. During carrying out of development, keep a copy of the approved plans on the premises where the development has been permitted; and
h. The owner shall submit a digital copy (soft copy) of all the as-built plans in a format as may be required by the Authority before issue of the Occupancy Certificate.
i. In case of Industrial plants which have been closed down and seeking to change the use, the applicant has to submit a clearance certificate from the Labour Commissioner to the effect that the industry has paid all the dues to the employees.
9.3. Checking of plinth, columns up to plinth level- To enable and ensure that the work conforms to the sanctioned plans, the applicant, on completion of work up to plinth level, shall give notice in the prescribed form to the Authority through his licensed surveyor, engineer, structural engineer or supervisor or his architect, as the case may be. Within fifteen (15) working days from the receipt of such notice, the Authority may inspect the
3C ER T, - a u, T , 3 3-9, R0/ R-, 993
work jointly with the licensed technical person or architect and either grant or refuse permission for further construction in the prescribed form. If within this period, the permission is not refused it shall be deemed to have been granted, provided the work is carried out according to the sanctioned plans.
9.4. Deviations during construction: - If during construction of a building any departure of a substantial nature from the sanctioned plans is intended by way of internal or external additions which compromise general building requirements, structural stability or fire safety requirements, sanction of the Authority shall be necessary. A revised plan showing the deviations shall be submitted and the procedure laid down for the original plans shall apply to all such amended plans. Any work done in contravention of the sanctioned plans, without prior approval of the Authority shall be deemed unauthorised.
9.5. Completion Certificate:- The applicant, through his licensed surveyor / engineer / structural engineer / supervisor or his architect, as the case may be, who has supervised the construction, shall furnish a building completion certificate to the Authority in the prescribed form with a request for occupying the completed development. This certificate shall be accompanied by three sets of plans of the completed development.
9.6 Occupancy Certificate: - The Authority, after inspection of the work and after satisfying itself that there is no deviation from the sanctioned plans, issue an occupancy certificate in the prescribed form or refuse to sanction the occupancy certificate in the prescribed form within 21 days from the date of receipt of the said completion certificate, failing which the work shall be deemed to have been approved for occupation, provided the construction conforms to the sanctioned plans. One set of plans, certified by the Authority, shall be returned to the owner along with an occupancy certificate. Where the occupancy certificate is refused or rejected, the reasons for refusal or rejection shall be given in intimation of the rejection or the refusal.
9.7 Part Occupancy Certificate:- When requested by the holder of the development permission, the Authority may issue a Part Occupancy Certificate for a building or part thereof, before completion of the entire work, as per development permission, provided sufficient precautionary measures are taken by the holder to ensure public safety and health safety.
Provided further that the part of the building for which Occupancy Certificate is applied for shall be functionally complete and conform to all requirements of these Provisions. This certificate may be granted by the Authority subject to the condition that the Owner indemnifies the Authority, on stamp paper of such value as decided by the Authority for Stamps as per the prescribed proforma.