FSI for Affordable Housing Component and the Free Sale Housing Component under the Scheme shall be released in accordance with the following (1)Table No. 14 S.
(1) Substituted vide Corrigendum / Addendum No. CR 121/21, dt. 02nd December, 2021.
| Table No. 14 S | |||
| Sr. No. | Stages of Release of FSI | Affordable Housing Component* | Free Sale Compone nt* |
| 1. | On Grant of Building Permission / Commencement Certificate up to plinth by Commissioner to the Affordable Housing Project | 3.00 | 1.00 |
| 2. | On Completion of 50% BUA of Affordable Component | -- | 0.75 |
| 3. | On Completion of 100% BUA of Affordable Component | -- | 0.75 |
| 4. | On handing over of 25% land and completed Affordable Component | -- | 0.50 |
| Total | 3.00* | 3.00* | |
* Explanation - The FSI of 3.00 is to be calculated separately on the one-fourth of plot area for Affordable Housing Component as well as three-fourth of plot area for Free-Sale Housing component.
v) The Affordable Housing Component under the Scheme shall be handed over along with the % t h part of the total plot of land, free of cost to the concerned ULB.
vi)(a) The affordable housing stock created under the scheme shall be allotted by the concerned ULB as follows :-
| Table No. 14 T | |||
| Percentage | Allotment to | Category of stock | Rate of allotment |
| 50 | Respective ULBs for use as PAP ownership free of cost tenements or staff quarters or transit accommodation. | Ownership | Free of cost |
| 25 | Government of Maharashtra and its statutory bodies/Govt. undertaking for use as PAP tenements or staff quarters or transit accommodation | Ownership | Free of cost |
| 25 | As affordable housing by MHADA subject to the general or specific direction of the Government | Ownership | Free of cost to MHADA which shall dispose of the same as per its policy and drawl of lots |
b) The affordable housing stock shall be disposed of as per the prevailing policy of MHADA regarding pricing and disposal of its housing stock meant for affordable housing. Each project approved under the Scheme shall be brought to the notice of the Government of Maharashtra and its statutory bodies/Government undertakings by means of press advertisement and if the Government of Maharashtra or any of its statutory bodies/Government Undertakings doesn‘t place firm requirement for the housing stock earmarked
for them in the Scheme before the completion certificate / occupation certificate for the said scheme is issued, the same shall come to the share of MHADA for outright sale as per the prevailing policy of the MHADA.
a) The other aspects of the development of affordable housing scheme, not specifically dealt with hereinabove, shall be as per the relevant provisions of UDCPR.
It shall also be permissible for the developer / owner to utilise the FSI available for free sale housing component, fully / partly for any other user otherwise permissible as per UDCPR.
c) In case owing to genuine hardship and site conditions, relaxation in marginal open spaces is sought by the developer / owner, the authority may consider such request, using its discretionary powers under the UDCPR, subject to the condition that in no case shall the clear marginal open space be reduced below 6 m. No premium shall be charged for granting such relaxation in marginal open spaces in respect of affordable housing component of the scheme.