Chapter 5Additional Provisions for Regional Plan Areas
5.0 General
In addition to the provisions mentioned in these Regulations, following additional provisions shall be applicable for the areas of the Regional Plans / Authorities mentioned herein under. These provisions shall prevail over the provisions, if any, mentioned in this Development Control and Promotion Regulations to that extent.
5.1For All Regional Plan Areas
5.1.1 Development Permissible Adjacent to Gaothan.
For the villages in the area of Regional Plans (excluding the area of Local Bodies and SPA where Development Plan or planning proposal is sanctioned) where no specific residential zone is shown, for such villages, development permissible in residential zone, may be permitted :-
i) within a belt of 2.00 km. from the boundaries of Municipal Corporation, 1.00 km. from the boundaries of Municipal Council and 0.50 km. from the boundaries of Nagar Panchayat, where zone plans are ( ) prepared or not prepared in the Regional Plan for such area;
(1) However the proposed development within such belt shall be guided by the road network of published / sanctioned zone plans or elsewhere proper road network plan prepared and approved by the Director of Town Planning within 6 months or within such time limit as extended by Government.
ii) within a belt of 500 meters from the gaothan limits of settlements having a population of less than or equal to 5000 as per the latest Census and;
iii) within a belt of 1500meters from the gaothan limits of settlements having a population of more than 5000 as per the latest Census;
iv) in the case of settlements of both the categories mentioned (1) in (ii) and (iii) above, falling in the planning areas / Zone Plans of Regional Plans, such distance from the gaothan limits shall be 500 meters only;
v) in the case of village settlements in the Western Ghat hilly area (eco sensitive zone) in Regional Plan of Satara, Pune, (1) Ahmednagar, Dhule, Kolhapur, Nashik, Nandurbar, Sangli, Sindhudurg, Thane, Palghar and Raigad District or as notified by Govt. from time to time such distance shall be 200 m. only
vi) in the case of villages in Regional Plan of Mumbai Metropolitan Region and Raigad, such distance shall be 500m. only.
Provided that such development shall be permitted only on payment of premium of the total area of land. Such premium shall be calculated considering 15%rate of the said land as prescribed in the Annual Statement of Rates of the year granting such developments. This rate of premium shall be subject to orders of the Government from time to time;
Provided further that, for the areas which are converted into Municipal Councils / Nagar Panchayats within the Regional Plan (under the provision of Maharashtra Municipal Councils, Nagarpanchayats and Industrial Townships Act, 1965), such premium shall be calculated considering 5% rate of the said land as prescribed in the Annual Statement of Rate for the year while granting such residential development (without considering the guidelines therein).
Provided further that, no such premium shall be applicable for development of an individual house of an owner or farm house on owner's land.
Provided further that no such premium shall be applicable for revised permission on the land where development/ Layout permission is granted prior to sanction of the respective Regional Plan, more specifically mentioned in Regulation No. 5.1.3.
Provided further that where more than 50 percent of area of the Survey Number/ Gut Number is covered within the above peripheral distance, the remaining whole of such Survey Number/ Gut Number within same ownership shall be considered for development on payment of premium as above.
Provided further that the criteria of ―distance from gaothan‖ shall also be applicable to the lands from the nearest gaothan of any village.
Provided further that this provision shall not bar development permission for the uses, otherwise permissible, in agricultural zone as per UDCPR within specified distance from gaothan mentioned in this regulation.
Provided also that this regulation shall also be applicable to all declared / Notified Gaothan under MLRC whether shown on Regional Plan or not.
Provided further that in respect of Ratnagiri-Sindhudurg Regional Plan, this provision shall be subject to provisions mentioned in Regulation No. 5.3.
5.1.2 Regulations for Development of Tourist Resorts / Holiday Homes / Township in Hill Stations Type Areas under Hill Station Policy.
The developments under the Hill Station Policy shall be governed by the Special Regulations as sanctioned by Government vide notification No.TPS-1893/1231/C.R.123/96/UD-13, dated 26/11/1996and its amendments by the Government from time to time.
5.1.3 Committed Development
i) Any development permission granted or any development proposal for which tentative or final approval has been recommended by the concerned Town Planning Office and is pending with the concerned Revenue Authority for demarcation or for final N.A. permission before publication of draft RP (date of resolution of the RP Board for publication) shall be continued to be valid for that respective purpose/use irrespective of approved Floor Space Index. Provided that, it shall be permissible for the owner either continue with the permission in toto as per such earlier approval or apply for grant of revised permissions under these regulations. However, in such cases of revision, the premium, if any, shall not be applicable, for approved permissions (including tentative). This provision shall not cover the cases mentioned in 5.1.3 (iii) below.
ii) The layout already approved/ development permission already granted for residential purpose and which are valid as per the provisions of UDCPR shall be entitled for development subject to use of earlier permission. This shall also be applicable to cases where sale permission for N.A. use has been granted prior to the date of sanction of these Regulations, for the same use as the one for which sale permission was granted.
iii) The layout already approved/ development permission already granted for the uses permissible in agricultural or such restrictive zone and which are valid as per the provisions of UDCPR shall be entitled for development subject to use and FSI of respective use granted in earlier permission.
5.1.4 Rectification of draftsman's error.
i) Draftsman's errors, which are required to be corrected as per actual situation on site/ or as per Survey Records, sanctioned layout etc. shall be corrected by the concerned District Collector, after due verification and prior approval of concerned Divisional joint Director of Town Planning.
ii) Drafting errors, if any, regarding Private Lands shown by mistake in the restrictive zone such as defence zone, forest zone, command area etc. shall be corrected after due verifications of records and situation on ground by the concerned Authority with prior approval of Divisional Joint Director of Town Planning. In such case Private Lands will be included in the adjacent zone.
iii) The boundaries of the designated or Notified Eco-Sensitive Zone in respect of Bird Sanctuary, Wildlife Sanctuary and other project shown on Regional Plan shall be as per the final notification issued under Environment (Protection) Act, 1986. All conditions regarding development including Buffer Zone in pursuance of the provisions of the said Act shall be applicable.
5.1.5 Highways notified by State/ Central Government.
If any highway/ ring road/ express way and any other classified road is notified by State/ Central Government Highway Authority under the provisions of relevant act, then the alignment of such notified road shall be deemed to be the part of Regional Plan and for this, procedure under section 20 of MRTP Act, 1966 shall not be necessary.
5.1.6 Station Area Development.
The development (1) in agriculture zone around (1) any functional railway station upto a distance of 500 m. shall be permitted by charging premium at 30% rate of the said land as mentioned in the ASR on total area of land under development, subject to following.
i) Within a 100 m. distance from periphery of the station, the users related to railway station and other users (excluding Residential) shall be permitted.
ii) In remaining distance within 500 m., all users permissible in Residential Zone shall be permitted.
iii) The rate of premium shall be subject to Government's order from time to time.
5.1.7 Modification proposals already sanctioned.
All the modification proposals from Regional Plan already sanctioned by the State Government under section 20(4) of Maharashtra Regional and Town Planning Act, 1966 but not shown in respective zone in Regional Plan shall be treated as included in respective Zone as per the modification sanctioned by the State Government.
5.1.8 Provision of Amenity Space.
In any layout or sub-division of land for residential purpose admeasuring more than 0.4 Ha. (excluding the area of R.P. roads, road widening and designations) amenity space shall have to be provided for the areas and specified percentages mentioned in the table below.
ii) For calculating the area for Amenity Space, area covered under the development proposal submitted to the Authority shall only be considered.
iii) The owner shall be entitled to develop the Amenity Spaces as per the uses permissible in the Amenity Space.
iv) If owner agrees to handover and the Authority agrees to take over the amenity space, then such Amenity Space shall be deemed to be reservation in the plan and floor space index (FSI) in lieu thereof ( )subject to maximum receiving potential prescribed in these regulations may be made available in-situ on remaining land. The calculation of this in-situ FSI shall be shown on the layout/ building plan. In the areas where TDR regulations are applicable and if the owner desires to have TDR against it, instead of in-situ FSI, then he may be awarded TDR. The in-situ FSI or TDR shall be granted only after transfer of the Amenity Space to the Authority. The generation of TDR or in-situ FSI shall be equivalent to the quantum mentioned in Regulation of TDR.
v) (1) Proviso of Regulation No. 3.5.1, (1) (--) shall be applicable to this regulation.
5.1.9 Residential Zone with payment of Premium
Wherever such zone is proposed in sanctioned Regional Plan, provisions related to such zone will continue to that extent.
5.2For Thane – Raigad-palghar Regional Plan
() Development around Tarapur Atomic Power Station in Tarapur-Boisar Area
5.2.1 The development within the area of 5 km. to 16 km. radius of Tarapur Atomic Power Station shall be governed by following regulations.
5 2 1 1 P i i ti d i R l ti N 6 23 h ll b li bl ith f ll i h . . . rov s ons men one n egu a on o. . s a e app ca e w o ow ng c anges.
94
Side and Rear Marginal Distances for building of Height more than mentioned in Table No.6D/6E of Regulation No. 6.2.1 and 6.2.2:- The marginal distances on all sides, except the front side, of building shall be minimum 6.0 m. or H/5, whichever is more. (Where H = Height of building above ground level) Provisions mentioned in Regulation No.6.2.4 shall be applicable
5.2.1.2 Provisions mentioned in Regulation No. 6.10 shall be applicable with following changes :- Distance between Two Buildings :- The distance between two buildings shall be 6.00 mt. or H/5 of the taller building between the two adjoining buildings, whichever is more. (Where H-Height of building above ground level)
5.2.1.3 Provisions mentioned in Regulation No. 6.10 shall be applicable with following changes :- Height of Building:- The maximum permissible height of building, including parking floor. shall be 24 mt.
5.2.1.4 Permissible FSI - a) Provisions mentioned in Regulation No. 6.1 and 6.3 shall be applicable with following changes :- The permissible Basic Floor Space Index shall be 1.10. In to basic permissible FSI, 0.30 FSI shall be permissible on payment of premium.
(***) If the land is affected by proposed road or road widening and if the owner hand over the land under such proposed road or road widening of very said plot, free of cost and free from all encumbrances, to the Authority, such FSI can be used instead of FSI on payment of the premium to the maximum extent of 0.30 or 0.30 FSI over and abovel.1. Basic FSI, may be allowed to be utilized partly from road widening FSI of very said plot and partly from premium FSI.
Provided that, above provision of FSI shall also be permissible for earlier sanctioned proposals within the limits of maximum permissible FSI of 0.75 or 1.00, as the case may be, subject to the marginal distances and Distance between Two building as prescribed above.
b) Provisions mentioned in Regulation No.7.7.2 shall be applicable with following changes:- Development of Housing for EWS/LIG - proposed in Agriculture Zone as per Regulation No.7.7.2-FSI permissible shall be 1.0.
c) Provisions mentioned in Regulation No. 4.11 shall be applicable with following changes:- FSI for users permissible in Agriculture Zone shall not exceed the FSI as prescribed in Regulation No. 4.11.
However, if FSI on payment of premium is permissible over and above the FSI allowed without payment of premium to certain user in Regulation No. 4.11, then the maximum FSI on payment of premium for such user shall be permissible to the extent of such permissible FSI on payment of premium or 0.40, whichever is minimum,
d) Provisions mentioned in Regulation No. 6.4 shall be applicable with following changes:- The permissible basic Floor Space Index shall be 1.00. In addition to the basic permissible FSI, 0.40 FSI shall be permissible on payment of premium.
e) Provisions mentioned in Regulation No. 6.1 and 6.4 shall be applicable with following changes :- Notwithstanding anything mentioned in various provisions of Unified Development Control and Promotion Regulation, Ancillary FSI shall not be permissible in this area..
5.2.1.5 Excepting the Regulation mentioned above, all other Regulations in Unified Development Control and Promotion Regulation shall be applicable for the area.