Parking provisions in the TOD Zone shall be at 50% of those as mentioned in UDCPR.
Note : No on-street parking shall be permissible, unless specifically allowed in the integrated mobility plan report.
14.2.1.6.1 Incentive for providing Public Parking in the area falling within the radius of 200 mt. from the Metro/MRTS Station.
If the owner / developer of the plot falling within the radius of 200 mt. from the Metro Station is willing to provide Public Parking space over and above the parking spaces required as per regulation No.14.2.1.6 of this regulation, the same shall be allowed without charging premium for such additional area and in that case the overall premium shall be discounted on 50 % of such parking area while calculating premium for additional FSI allowed over and above the base FSI, subject to following conditions :-
a) Such parking area shall be in the built-up form and shall be handed over to Planning Authority free of cost before granting the Occupation Certificate to the project. The Planning Authority should enter into an agreement with owner / developer for such parking space at the time of granting Commencement Certificate to the project. Such Public Parking area shall be clearly shown on the proposed building plan / layout and a condition to above effect shall be incorporated in the Commencement Certificate.
b) The parking area shall have independent access from major road adjacent to the plot and with proper entry and exits.
c) The parking area to be made available at individual site shall be at minimum 100 sq.mt. at one place either at Ground floor / Stilt floor or first floor.
d) The maximum parking area that can be provided shall be decided by the Authority, as the case may be, on considering the location of such site and the parking requirement.
e) A board showing the location of such public parking space should he displayed at suitable places by the Planning Authority.
(1) Inserted vide Notification u/s 37 (1AA)(C) & 20(4) No.CR 158/19, dt. 10th October, 2022
(1)f) Area covered under such parking shall not be counted towards FSI consumption.
285
g) Concerned land owner / developer / society / public company shall not be allowed to operate the public parking.
h) The proposed development shall be further subject to such conditions as may be decided by the Authority.
14.2.1.7 In case of development or redevelopment, proposed by the Authority / individual applicant / any other Planning Authority, from the edge of the Metro Rail, within 20 mt. distance on its either side, the concerned Planning Authority before granting such permission for development / redevelopment shall seek prior NOC from the concerned Metro Railway Authority as required under the Metro Railways (Construction of Works) Act, 1978 from the point of view of safety of the Metro Railway and such other related matters.
14.2.1.8 For the matters not provided in this regulation, the relevant provisions of Principal DCPR shall apply. However, in case of any conflict between this Regulation and any other Regulation/s of the Principal DCPR, this Regulation shall prevail for the TOD zone.
14.2.1.9 No Compound wall / fencing shall be permissible on the boundary of plot facing the road and 50% front marginal distance (subject to minimum of 3.0 mt.) shall be kept accessible to the pedestrians to be used as foot paths. However, it shall be permissible for the applicant to construct / erect fencing, on the receded boundary, after leaving the space for pedestrians as specified above.
14.2.1.10 Large wholesale stores having built-up area of more than 500 sq.mt., car dealer showrooms, warehouses / storages, auto service centres, Garages etc. shall not be permissible in TOD zone.
14.2.1.11 Provision of Inclusive housing shall not be applicable in TOD zone.
14.2.1.12 For Gunthewari development regularized under the provisions of Maharashtra Gunthewari Development Act, 2001 and falling in TOD zone, seeking permission for development / redevelopment, these regulations shall apply.
14.2.1.13 In case of independent unit / Bungalow for self-use, such Development / Redevelopment may be allowed within base FSI subject to Principal DCPR.
Notwithstanding anything contained in this regulation, if any development on plot in TOD zone is proposed within base permissible FSI (without TDR or Premium FSI) as per provisions of Principal DCPR, all other provisions of Principal DCPR shall be applicable.
14.2.1.14 The layout of building / group housing layout or standalone building on a plot / plots situated in TOD zone / Circle, over which any development permission granted or any development proposal for which any action is taken and for which occupancy certificate is not granted, may be revised and balance potential, as per this regulation, if any, may be allowed subject to structural stability criteria and provisions in Regulation 1.5 of Principle DCPR and subject to following.
a) Parking - For the ongoing buildings, the requirement of parking as per this regulation shall be applicable for the balance building potential.
b) Tenement size - For the ongoing buildings, the requirement of tenement size as per this regulation shall be applicable for the balance building potential.
(1) Inserted vide Notification u/s 37 (1AA)(C) & 20(4) No.CR 158/19, dt. 10th October, 2022
| 14.2.1.15 | (<sup>1</sup>) The Amount received as scrutiny fee, hardship premium, and premium for additional |
|---|---|
| 14.2.1.16 | FSI etc. in TOD zone / circle shall be kept in separate head at Authority level and shall be utilizedfor development of metro project as per directives issued by Government from time to time. These TOD provisions will also be made applicable to other MRTS projects such as BRTS. The scale of FSI availability will be notified later by the Government for such other projects. |
| 14.2.2 | Pune Metropolitan Region Development Authority area. For this areas, the regulations specified in Regulation No. 14.2.1 are applicable mutatis - mutandis |
| 14.2.3 | For Nagpur Municipal Corporation and Nagpur Metropolitan Region Development Authority. Following Regulations are applicable for Development / Redevelopment of building falling within Nagpur Metro Rail Corridor (NMRC) |