10.1.4 No piece of land shall be used as site for the construction of building,
(a) If the land is within a prohibited distance (currently of seventy five meters) from the crest of the outer parapet of the Armament Research and Development Establishment (ARDE), Range Pashan, Pune;
(b) If the land is within a prohibited distance of approximately 457.2 m. (500 yards) from the crest of the outer parapet of the High Energy Materials Research Laboratory (HEMRL), Sutarwadi, Pune as shown on Development Plan;
10.2Thane Municipal Corporation Area.
($)10.2.1 Development along Ram Maruti Road and Gokhale Road.
Front set-backs for development on above roads shall be as below :-
In the case of plots fronting on Ram Maruti Road, only ground floor of the structure shall be set back by 3.05 m. from the road line and rest of the floors shall be set back at a distance of 4.5 m. (1) The front terrace so formed shall be allowed to be accessible.
ii) In case of any plot fronting on Gokhale Road, from the portion between Ashok Talkies and its junction with M.G. Road, the ground floor of the building shall be set back by 2.3 m. from the road line and the upper floors shall be set back at a distance of 4.5 m. subject to condition that the owner of the plot shall pave the front open space. (1) The front terrace so formed shall be allowed to be accessible.
10.2.2 Setbacks from Eastern Express Highway and Roads more than 52.5 m. in width.
No construction of building shall be undertaken within 7.5 m. from the boundary of the Eastern Express Highway and other roads having prescribed width more than 52.5 m.
186
10.2.4Development around Hazardous Industries (Chemical Zone Areas).
a) Green Belt -
i) There shall be green belt of 100 m. around the boundary of the Hazardous Chemical Industries as shown on plan attached with the report of authority.
ii) The creation of the green belt, its development and maintenance as per report of authority will be the responsibility of Municipal Corporation.
iii) The cost of acquisition of land for the green belt, around the Hazardous Chemical Industries will be borne by the Industry / Industry Association. The private land owner will be given Transfer of Development Rights based on FSI for the present land usage. The cost of acquisition to be borne by industry will be exclusive of the value of TDR.
The existing authorised structures should be tolerated. However, only repairs to such existing structures should be allowed in future and no reconstruction or new construction should be allowed in the Green Belt.
v) Unauthorised structures should be removed or relocated by the Thane Municipal Corporation as per the existing Public Policy.
b) Creation of Low Density Zone
i) Beyond the Green Belt, another belt of 150 m. should be created as "Low Density Zone" as shown on plan, attached with the report of the Authority.
ii) The FSI in the Low Density Zone shall be 0.5 and only Ground plus two storey structures should be allowed.
iii) The existing buildings if already authorised with the higher FSI and plan of the proposed building already approved by the Thane Municipal Corporation and Commencement Certificate have been given to such structure should be allowed to continue, be completed and occupied by the issuing Occupation Certificate. Where the plans have been approved by the Thane Municipal Corporation but commencement certificates have not been issued, they should be reviewed and the permission should be revised in accordance with the Low Density Zone Regulation, now be prescribed.
iv) The development proposals in Low Density Zone shall be scrutinised and permission shall be granted as per these UDCPR.
c) Development between 250 and 1000 Meters.
The Development proposals beyond the area of 250 m. shall be scrutinised and permissions shall be granted as per these UDCPR.
Other Stipulations -
i) The original land under Chemical Industry, which has been certified by the Director of Industries/ Director of Industrial Safety and Health/ Competent Authority as permanently closed or having shifted elsewhere shall be allowed to be developed as per the relevant provisions in the prevailing Development Control Regulations.
Upon certification by the Director of Industries/ Director of Industrial Safety and Health/ Competent Authority that the Chemical Industry has been permanently closed or has shifted elsewhere, the 100 m. Green belt and the further 150 m. low density belt around the plot boundary of such Chemical Industry shall suo-moto cease to exist.
10.2.3a) Development of Multi Storey Public Parking Lot (PPL) near Metro Stations.
For development of Multi-storied PPL on any plot abutting a road of minimum width of 18 m., additional FSI ( hereinafter referred to as ―Incentive FSI‖ ) as specified below on built up parking area, created and handed over to the Thane Municipal Corporation (TMC) free of cost with amenities required for parking area as prescribed by the Commissioner such PPL shall be allowed, on the land belonging to a private owner/Lease hold plots of Govt. and TMC with prior consent, which is not reserved for any public purpose, subject to the conditions contained herein below:
I. The minimum area of plot shall be 1000 Sq.m. in sector - 1, 2, 3 and 2000 Sq.m. in remaining sectors. The minimum number of Motor Vehicle public parking spaces provided shall not be less than 50. The location of parking spaces can be in 2 level basement, ground floor or upper 2 floors maximum, with access through ramp/lift or combination of both subject to clearance from CFO with special emphasis on fire hazard.
II. A Committee under the Chairmanship of Municipal Commissioner, TMC shall earmark/ select the plots for public parking, on the basis of their suitability. The Committee shall comprise the following or their representatives (i) Metropolitan Commissioner, MMRDA. (ii) Dy. Commissioner of Police (Traffic), (iii) Joint Director of Town Planning, Konkan Division (iv) Assistant Director of Town Planning, TMC (Member Secretary).
III. The incentive FSI given on this account will be over and above the base FSI permissible under any other provisions of UDCPR. This incentive FSI shall be allowed to be used on the same plot in conformity with UDCPR/ DP, within the overall cap/ limit of total maximum permissible FSI as given at (vii) below.
IV. The proposed development shall be subject to any other conditions prescribed by the Municipal Commissioner.
V. Concerned land owner/ developer/ society/ company shall not be allowed to operate the public parking lot.
VI. Area covered under parking shall not be counted towards FSI consumption.
VII. The incentive FSI permissible under this Regulation against BUA of the PPL shall be 50% of the BUA of the PPL, such that the total permissible FSI including the incentive FSI under this Regulation does not exceed the limit as per Regulation 6.3.
VIII. The maximum cap on BUA per parking shall be 50 Sq.m. for LMVs, 65 Sq.m. for LCVs and 120 Sq.m. for HMVs/Buses. Incentive FSI shall be calculated as per BUA of the PPL, based on these norms or the actual BUA of the PPL, whichever is less.
IX. The developer of the PPL shall pay ‗premium‘, worked out as per the following formula:-
Premium = 60% of [ Value of the additional BUA corresponding to the incentive FSI admissible under this Regulation, as per A.S.R. – (Cost of construction of PPL + cost of any extra amenities/facilities provided + cost of construction of BUA corresponding to the incentive F.S.I. admissible under this Regulation) ]
For the purpose of calculating premium as above, the cost of construction of PPL including amenities/ facilities and the cost of construction of BUA corresponding to the Incentive FSI admissible under this Regulation shall be 75% and 125% respectively of the rate of RCC construction as per ASR.
X. The Premium shall be paid before the issuance of building permission for the incentive FSI admissible under this Regulation.
Upon Payment of 100% premium as aforesaid, building permission shall be issued in respect of 50% of incentive FSI. In no case, Incentive FSI be released without handing over of the PPL, complete in all respects, to TMC.
The year in which premium is paid before the issuance of building permission for the PPL shall be taken as the year for determination of construction cost as well as ASR for calculation of the premium. Out of the total premium payable, 50% shall be paid to the GoM and the remaining 50% to TMC.
Provision of this Regulation may also be applicable to lease hold plots of Govt. and TMC with prior approval from Government/ Municipal Corporation.
XI. The land owner/ developer/ Society/ company shall hand over PPL with separate entrance and exit for the dedicated use of TMC by way of registered conveyance deed. Such PPL will not be part of proposed society/ apartment/ owners association.
XII. The PPL shall not be permissible in combination with other regulations.
XIII. Public Parking shall be developed in independent building as far as possible, but it may permissible in composite buildings subject to compliance of these regulations.
XIV. The Commissioner may hand over such PPL to any agency to transparent bidding procedures for its operations and maintenance upon such terms and conditions as deem fit and proper. However in any condition such PPL shall not be allotted to concerned land owners/ housing society/ association of apartment owners of occupiers in the plot of PPL.
XV. No public parking lots shall generally be more than 500 vehicles. However in exceptional cases Commissioner may permit PPL for 1000 vehicles for the reasons to be recorded in writing.
XVI. PPL connectivity to nearest station of Local/ Mono/ Metro/ BRTS etc. may also be insisted if propose PPL is within 250 m. by skywalk and underground connectivity within 100 m. These area shall also be counted for giving incentive FSI and shall not be included for calculating limits of vehicles.
XVII. For every sectors Commissioner shall endeavour to evaluate total need of PPL and shall cause it to be declared in local newspaper within three months of promulgation of these regulation for every 5 years. Total PPL sanctioned in any sector shall not increase beyond that for next 5 years. PPL shall be allowed only after studying traffic impact analysis of area with the periphery of 250 m. of PPL.
10.2.5Development around Air Force Stations.
i) As per Government of India, MoD SRO No. 4, dated 13 January, 2010 which was published in Part-II Section 4 of Gazette Notification dated 23 January, 2010. Air Force Station Thane falls within the 100 m. restriction zone. As per notification, no construction should be permitted within the restricted zone of 100 m. from the outer parapet of the Air Force boundary. Similarly, live hedges, tree/rows or clumps of trees or orchards shall not be maintained, planted, added to or altered within the 100 m. restricted zone. The restriction is equally applicable for construction of underground structure, wherein no digging and/ or change in the level of ground is permitted within the notified zone.
ii) Beyond the notified zone of 100 m., no restriction is required to be imposed as per the Works of Defence Act 1903 and no NOC from Air Force Station, Thane is necessary. (1) (--)
(2)10.2.6 Development around Defence Establishment.
Following restrictions are imposed in and around the land in the vicinity of the said unit as per the plan enclosed with Notification No.TPS-1203/1254/C.R.193/05/UD-12, Dt.30/12/2006.
Village : Kolshet/Kavesar/Waghbil (within the limit of Thane Corporation)
Circle / Taluka : Thane, District : Thane, State: Maharashtra
Height Restrictions:-
(a) The height restrictions to any of the future constructions on North, North-West, West and South-West sides will be as follows:-
Sr. No.
Height Limiting zones from unit boundary (Zones indicated by colours)
(2)(b) The height restrictions to any of the future constructions on North East, East and South-East sides will be as follows :-
Sr. No.
Height Limiting zones from unit boundary (Zones indicated by colours)
Permissible height in meters
Remarks.
A
Red
Nil
Unit Area
B
Brown
Nil
Buffer Zone (No Dev. Zone)
C
Orange
15
--
D
Pink
20
--
E
Yellow
35
--
F
Violet
40
--
G
Sky Blue
45
--
Other Restrictions :- In addition to the above restrictions, following general restrictions are also enforced :-
a) No high tension power line up to 22 KV is to be setup within 1500 meters from unit boundary.
b) Open wires, overhead lines, including telephone cables are to be outside 500 meters from unit boundary. However, UG cables. (below 5 meters) are permissible.
c) No rail line with electric traction is permitted within two kilometers from the unit.
d) Area within one kilometer radius from unit boundary is to be clear of all metallic structures including bridges.
e) Ground water level is to remain constant. No efforts are to be made to change the electrical conductivity of the designated zone.
f) No industry/equipment, which generates any kind of RG noise, are permitted to operate within 1 km. Radius from unit boundary.
10.2.7Regulations for G-1 Zone (Yeur village Section-VII only)
Following uses shall be permitted in G-1 Zone.
The residential Building on the lands which are actually under cultivation and the holiday homes for weekend stay and the Rest Houses subject to following conditions :-
The plot to be permitted for such development shall be not less than 4000 Sq.m. with the maximum FSI of 0.025.
Each building to be not more than ground plus one storey with height not exceeding 9.75 m. including the height of stilt portion if any, subject to maximum built up area 100 Sq.m. excluding stilt.
To permit Club House, open play Grounds and other recreational purposes as normally permissible under green zone with permissible FSI as per these Regulations.
To insist plantation at the rate of two fast growing trees per 100 Sq.m. of land under development.
10.2.8 Regulations for G-3 Zone for Forest Area.
No development of any sort shall be allowed in this zone except the project of the Forest Department. In case of pockets of private lands in G-3 zone, development shall be permitted as per the provisions of Green Zone / as per the provisions of G-1/G-2 Zone subject to concurrence of Forest Department.
10.2.9 (1) For the sake of Regulations No.1.3.74, No. 1.3.93 (xiv)(i) and No.6.2.3(b) High Rise Building / Special Building means any multi-storied Residential Building, which is under redevelopment, and which is more than 25 m. in height above average surrounding ground level.
10.2.10(2) Redevelopment of Old Dilapidated / Dangerous Buildings
Reconstruction / Redevelopment in whole or in part of any building which has ceased to exist in consequence of accidental fire / natural collapse or demolition for the reasons of the same having been declared dangerous or dilapidated or unsafe by or under a lawful order of the Authority or building having age of more than 30 years, shall be allowed subject to following conditions.
Redevelopment of multi-dwelling buildings of society/ Co-Operative Housing Societies / Apartments -
i) The FSI allowed for redevelopment of such building shall be FSI permissible under Regulation No.6.1 or 6.3 including FSI on payment of premium and maximum permissible TDR loading as per Table 6-A or 6-G, or the FSI consumed by the existing authorized building including TDR, premium FSI etc., whichever is more. (Such TDR, Premium FSI etc. utilised in existing building shall be treated as a basic FSI for redevelopment.) In addition to this, incentive FSI to the extent of 50% of the existing authorised built up area or 15 Sq.m. per tenement, whichever is more, shall be allowed. Provided that in cases where carpet area occupied by residential tenement in the existing building is less than the carpet area of 27.87 Sq.m. then such tenement shall be entitled for minimum carpet area of 27.87 Sq.m. and difference of these areas shall be allowed as additional FSI without any premium. In case of non-residential occupier the area to be given in the reconstructed building shall be equivalent to the area occupied in the old building. Such incentive FSI shall not be applicable for redevelopment of existing bunglow.
ii) This regulation shall be applicable only when existing members of the societies are proposed to be re-accommodated.
iii) If tenanted building/s and building/s of co-operative housing society/non-tenanted building/s coexist on the plot under development, then proportionate land component as per existing authorized built up area of existing tenanted building on the plot shall be developed as per Regulation No.7.6.2. and remainder notional plot shall be developed as per this regulation.
191
iv) Notes below Regulation No.7.6 shall be applicable to this regulation.
(1) Inserted Vide Corrigendum / Addendum No.CR 79/2021, dt. 02nd December 2021.
(2) Inserted Vide Order No.CR 236/18 (Part 3), dt. 02nd December 2021.
10.2.11(1) Height of Building Permissible for Re-development Proposals / SRA Proposals
For all re-development proposals and slum-rehabilitation schemes in Municipal Corporation area, the building height upto 70.0 m. shall be permissible on roads having width between 9.0 to 12.0 m. subject to minimum front margin as per these regulations or minimum 6.0 m., whichever is less and subject to condition that such road shall be widened to 12.0 m. under the provisions of the Municipal Corporation Act, by prescribing line of street before granting occupation certificate to such buildings of re-development or slum-rehabilitation schemes. This shall be subject to Fire prevention, protection and life safety requirements and Fire NOC from Chief Fire Officer.
10.4.2Special Regulations for the Improvement Schemes :
The improvement schemes by Public participation which are sanctioned by the Government under the provisions of the Nagpur Improvement Act 1936 and which comes under the jurisdiction of the NMA area shall be valid and continue to be valid for the said purpose under the said Act. The Special Development Control Regulations for these schemes shall be as mentioned below :-
Any changes/ Modifications/ Amendments in the details layout or in the master plan shall be carried out by the Metropolitan Commissioner at his own level. However the Public Amenity/ Public Utility Areas and their percentage as per original sanction shall not be changed while making Modifications/ Amendments in the Schemes.
i) Improvement Scheme - The scheme is prepared under the NIT Act 1936 for the notified area and is duly approved by the State Government and which is now included in NMRDA area.
ii) Original Plot - A plot consisting of nearby khasras calculated as a single record in a village which is under same ownership and has the same tenure status as defined in the respective 7 / 12 documents of the khasras.
iii) Final Plot - The plot which is reconstituted or reshaped from the Original Plot within a draft/ sanctioned Improvement Scheme in a manner appropriate for development and given access from the public right of way. The Final Plots is reconstituted as per the relevant regulations/ Act as Final plots for Authorities share and owners share.
iv) Owner - An owner is a person who has legal title for land or building. The definition also includes :-
a) An agent or trustee who receives the rent on behalf of the owner;
b) An agent or trustee who receives the rent of a or is entrusted with or is concerned with any building devoted to religious or charitable purposes;
c) A receiver, executor or administrator or a manager appointed by any court of competent jurisdiction to have the charge of, or to exercise the rights of the owner; and
d) A mortgage in possession.
v) Permissible FSI For Final Plot –
i) The Metropolitan Commissioner may allow the owner to develop the final plot in possession of the owner subject to handing over to the Planning Authorities share as independent plot free of cost as per norms prescribed by Metropolitan Commissioner.
ii) The owner shall thereafter be entitled to develop his final plot for the uses permissible in adjoining zone as per the this DCPR with full permissible FSI of the entire Plot alongwith Additional FSI/TDR potential permissible for his Final plot share as per Chapter No. 6 of this DCPR .
10.2.12(1) Podium
Podium for parking alongwith ramp may be permitted with side and rear marginal distance of 1.5 m. from plot boundary, subject to following conditions :-
a) Top of the Podium shall be accessible for Fire Engine by 7.5 m. Ramp with gradient 1:10.
b) Structural Stability Certificate regarding such Podium and Ramp shall be submitted with respect to stand Fire Engine over it & sustain load of Fire Engine.
c) Minimum 6 m. marginal distances with required turning circle over the Podium shall be provided for manoeuvring of Fire Engine.
Provided that, if the podium is not accessible for Fire Engine then 6.0 m. marginal open space shall be provided all around the building excluding front margin. Turning circle shall not be less than 9.0 m. The refuge area in such cases shall be facing front road and shall be connected to Fire Tower as per Clause 2.24 of Part 4 of NBC 2016.
d) Provisions mentioned in Regulation No.9.13 shall be applicable except (ii).
10.2.13
(1) Front Marginal Distances / Set-back / Road side margin/s in congested area minimum front marginal distance for buildings under re-development proposal shall be 1.5 m. for roads having width 6 m. or more.
10.2.14
(1) Off street parking requirement - For Redevelopment Projects in Thane Municipal Corporation area, multiplying factor for off street parking requirement as per regulation no.8.2.2 shall be 0.8.
10.2.15
(a) For Redevelopment of smaller plots having area upto 1500 Sq.m. with multistoried building upto 24.0 m. height plus height of parking upto 6.0 m., side / rear margin of 6.0 m. shall be relaxed upto 3.0 m. subject to Fire NOC, in case of bonafide hardship and such building shall not be considered as special building.
(b) Other provisions mentioned in Regulation No.6.2.3 shall be applicable.
(1) Inserted Vide Corrigendum / Addendum No.CR 79/2021, dt. 02nd December 2021
10.3
NAGPUR MUNICIPAL CORPORATION The following regulations shall be applicable
10.3.1
Buildings in Commercial Zone : (a) In non-congested area : FSI for buildings outside congested area in commercial zone - the basic FSI permissible shall be 2.00 for commercial cum residential use or purely residential use and 2.50 for purely commercial use. (b) In congested area : The permissible FSI for commercial use shall be 1.50 for the plots fronting on the road having width less than 9 m. and 2.00 for the plots fronting on the road having width 9 m. or more.
10.5.2Development of Cycle Track Along River and Nallah
A cycle track shall be developed in green belt areas earmarked on Development Plan along the rivers. Also, cycle track proposal is shown on canal land in the Development Plan.
A distance of 6 m. from the edge of minor water course (nallah) is to be left as marginal distance for construction of any building. A 3 m. strip of land from the edge of such water course out of this 6 m. distance to be left shall be available for use as cycle track for general public. The compound wall shall be constructed excluding this distance of 3 m. strip for cycle track. The owner shall be entitled for FSI of this strip of land for cycle track, in-situ. This 3 m. wide strip shall be handed over to Municipal Corporation for which, owner shall be entitled for TDR or insitu FSI equivalent to 35% of the area of 3 m. wide strip. This regulation shall be applicable for development of land along Nallahs specified in Plan-A annexed with this UDCPR. Where development is already taken place and it is not possible to make provision for such 3 m. wide cycle track, then Municipal Commissioner shall be empowered to decide not to apply this regulation for particular stretch of nallah. In such cases, normal marginal distances under these regulations shall apply.
10.5.3Set back and marginal distances for 36 m. wide D.P. road passing through village Gangapur and Ambad.
Notwithstanding anything contained in Regulation No. 6.2.1, following set back and marginal distance shall be applicable for road mentioned below.
Description of the road
Min Plot Size in Sq.m.
Min width of plot in meters
Min set back from road side in meters
Min. side margins in meters
Min. rear margins in meters
Remarks
36 m. wide D.P. road from Gangapur S.No. 12 to AmbadS.No.199
300
12
3.00(for commercial use also)
2.00
2.00
Margins for buildings G+2 or stilt + 3 structure. Higher height permissible subject to marginal distances in Regulation No.6.2.3.
Vasai Virar City Municipal Corporation
Following regulations shall be applicable for the low intensity development areas in the Vasai Virar City Municipal Corporation.
The basic and total permissible FSI with DR/TDR on the plot shall be as under :-
Table No. 10 A
Sr. No.
Land use Zone
Base FSI
Additional FSI on payment of premium
Admissible TDR including Road widening FSI if any
Maximum permissibl e FSI
1
Low Density Residential Zone
0.3
0.2
--
0.5
(1)(--)
(1) Deleted vide Notificatio27n No.CR 121/21, dt. 27/10/2021.
10.7
MIRA BHAYANDAR MUNICIPAL CORPORATION -
10.7.1
Uses permissible in Agriculture Zone. The lands along 45m., 30 m. wide roads upto a depth of 30 m. may be developed for residential purpose on condition that the owner should provide infrastructural facilities such as septic tank, drainage, water supply etc. at his own cost.
10.10Navi Mumbai Municipal Corporation
10.10.1 Basic FSI Permissible for Certain Categories of Plots.
Business or Mercantile use wholly or in combination with the residential use in any other zone mentioned in Regulation, other than Regional Park Zone and No Development Zone, shall be as below.
Provided that, in case of combination, Business or mercantile use shall not be less than 10% of the admissible FSI. Provided further that the area of all such plots taken together in the zone from Node shall not exceed 15% of the area of the relevant zone from the Node.
a. For plots of area below 1000 Sq.m. Basic FSI = 1.00
b. For plots of area 1000 Sq.m. and above & fronting on minimum 15 m. wide road Basic FSI = 1.50
(2) Substituted / Inserted Vide Corrigendum / Addendum No.CR 79/2021, dt. 02nd December 2021.
Note :
The benefit of the regulation mentioned at (a) above may be extended to plots of land leased out or agreed to be leased out by CIDCO earlier with different (lower) FSI, in Zones other than predominantly Commercial Zone, provided further that all other UDCPR provisions including parking are fully complied with.
All plots leased by CIDCO with FSI 1.50 and fronting on roads less than 15 m. if any, prior to the sanction of this UDCPR shall be exempted from the 15 m. road with criteria.
If the intended development is within the scheme for allotment of land to the project affected land holders in the defined area contiguous to the villages or within the scheme of allotment of 12.5% / 22.5% land to the project affected land holders, 15% of such FSI may be utilized for commercial area and FSI permissible shall be 1.50. ( ) In such case, the clear marginal open spaces within the plot required to be provided for the purposes of deriving light and ventilation, shall be as follows :-
Category
Area of plot fronting road (in m.)
Max permissible height of buildings
Min. Marginal Open Spaces (in m.)
Front
Side
Side-2
Rear
10.10.2Reconstruction / Redevelopment of Building in CIDCO / NMMC Areas
Regulation for reconstruction / redevelopment schemes undertaken by CIDCO/Owner‘s Association / Co-operative Housing Society (CHS) in respect of the authorized buildings previously constructed by CIDCO but subsequently destroyed by natural calamities or accidental fires or which have collapsed by aging or are demolished or being demolished under a lawful order of the Municipal Commissioner etc.:-
Reconstruction / Redevelopment, in whole or in part of a building, previously constructed by CIDCO (not being a building wholly occupied by warehousing / Industrial user and also not being an individually owned structures, which has ceased to exist for the reasons mentioned above) or a building constructed by CIDCO which has been declared dilapidated by the
Commissioner NMMC or a buildings constructed by CIDCO which is above 30 years of age, irrespective of its status of dilapidation, (hereinafter collectively referred to as ―dangerous / dilapidated building‖) shall be permissible in accordance with the following Regulations.
Regulation for Reconstruction / Redevelopment :-
For redevelopment of building or buildings in the housing schemes of CIDCO, containing houses or tenements for (i) EWS / LIG and / or (ii) MIG and/or (iii) HIG, the total permissible FSI shall as specified in Table below or Rehab + Incentive FSI as per clause 2(A) & (B), whichever is more and shall be based on gross plot area:-
Table No -10 C
Sr. No.
Category
Permissible FSI
i)
Plot area of 1000 sq.mt. or more and having access road of minimum 15 m width.
3.00
ii)
Plots area of 1000 sq.mt. or more and having access road of minimum 9m. width
2.00
iii)
iii) The Metropolitan Commissioner shall develop the Final Plot in his possession (Authorities Share) for the purpose for which the scheme is sanctioned. This plot shall be entitled to be developed as per potential permissible for Authorities Final plot share as per Chapter No. 6 of this UDCPR.
10.4.4
vi) Net Plot area for Computation of FSI - For the purpose of computing FSI/Built - up area, the net area of the plot shall be as defined in these regulations.
vii) Special Regulations For Inclusive Housing - The provision regarding inclusive housing in development proposal shall be not made applicable in Improvement scheme if the Final Plot in the possession of Authority is to be designed and develop for the purpose of any affordable housing scheme.
viii) Height of Building - The maximum height of building for all users shall be as per Chapter No. 6 of this UDCPR.
195
ix) Amenities Space - If the Amenity space has already provided in the scheme at the time of approval of scheme/ layout, in such cases the amenity space as required under this UDCPR shall not be insisted.
x) Land Use Permissible - All land uses mentioned in this UDCPR shall be permissible in the Improvement Schemes.
xi) Development Charges - The Development charges shall be recovered as mentioned in these regulations.
xii) Power to Authority - For the smooth implementation of the schemes, the Metropolitan Commissioner with the Approval of the Authority, makes / amends the rule in consistent to the relevant Act and Regulations assigned to it with prior approval of by the Government.
xiii) UDCPR - All regulations of UDCPR shall apply except above special regulations.
(#) 10.4.3 The following regulation shall be applicable only for the reference of Regulation No. 25.6 (xxxx) mentioned in the notification of sanctioning the Development Plan of Nagpur Metropolitan Region Development Authority.
In Agriculture zone, Residential use shall be allowed subject to following conditions.
a) Minimum area of land shall be 15.0 hect.
b) Land shall front on minimum 12 m. wide existing road.
c) Permissible FSI/ TDR shall be as that of Residential zone.
d) The offsite infrastructure like road, water supply, sewerage treatment plant having zero discharge shall be developed by land owner at his own cost, unless this infrastructure is provided by Authority.
e) 10% of the entire holding area shall be handed over to the Authority free of cost, without any FSI/ TDR and free of all encumbrances for sale by Authority for residential, commercial or industrial use depending upon the nature of development. This 10% area shall be over and above recreational open space and amenity space to be provided as per regulation. This 10% area shall front on minimum 12 m. wide road.
f) Premium on gross area at the rate of 5% of land rate in Annual Statement of Rates of the said land without considering the guidelines therein shall be paid to the Authority.
(1)The following regulation shall be applicable only for the reference of Regulation No. 25.6 (xxxxiii) mentioned in the notification of sanctioning the Development Plan of Nagpur Metropolitan Region Development Authority.
(#) Clarification issued vide letter No. CR 67/2022, dt. 6th September, 2022.
(1) Development permission around the periphery of Gaothan boundary -
Development permission around the periphery of Gaothan boundary shall be allowed as per the Regulation mentioned as below. This regulation shall be applicable only for the Rural centre and rural area (excluding nine urban centre area). Regulation for residential zone and other regulation shall be applicable.
The peripheral residential area shown along the Gaothan village is deleted and land thereunder included in Agriculture Zone. The development along the periphery of the Gaothan shall be allowed subject to following:
a) In the villages in Rural area / Rural Centre excluding the area under nine urban centres, Residential Development or development allowed in Residential Zone, may be permitted within the periphery of Gaothan boundary as per the criteria given below. The regulations in respect of residential zone specified in these UDCPR shall be applicable.
Sr. No.
Category of Village (Populations as per latest census)
Development allowed from Gaothan boundary
1
Up to 5000
750 M
2
Above 5000
1000 M
Such development may be permitted on payment of premium of the total area of land. Such premium shall be calculated considering 15 % rate of the said land as prescribed in the Annual Statement of Rates of the year granting such developments. Such premium shall be deposited in the concerned Authority.
Provided that, where more than 50% of area of the Survey Number/ Gat Number is covered within the above peripheral distance then the remaining whole of such Survey number/Gat number within one ownership shall be considered for development on payment of premium as above.
Provided further that, the premium charges shall be recovered at the time of tentative approval of the Development permission. Where tentative development permission is already granted before publication of this Development Plan and final approval is yet to be granted, then in such cases premium charges shall not be recovered at the time of final approval.
Provided further that, such payment of premium shall not be applicable in cases where development permission is already granted or layout is already approved by the authority before publication of Development Plan. Such premium shall also be not applicable for revision of such already approved permissions.
However, such development should not be permitted on lands which deserve preservation or protection from Environmental considerations viz. Hills and Hill tops and within the required Buffer Zone / prohibited Zone from river, lakes and reservoirs of minor and major project of water resource department.
10.5
NASHIK MUNICIPAL CORPORATION
10.5.1
Applicability of Regulations for some areas.i) The special Regulations framed by the Arbitrator for some final plots in TP Scheme No.1 (First Varied) shall remain in force.(2) (--)
(1) Inserted Vide Addendum No.CR 236/18 (Part-1), dt. 23<sup>th</sup> June, 2021.(2) Sr. No (ii) deleted vide Corrigendum / Addendum No. CR 121/21, dt. 02<sup>nd</sup> December, 2021.
10.3.2
Buildings in Industrial Zone a) In congested area, the permissible FSI for industrial use shall be 1.00. b) In non-congested area, the permissible FSI for industrial use shall be 2.5.
10.3.3
I to R provisions - Allowing Residential/ Commercial uses in Industrial Zone. The Regulation No. 4.8.1 in these regulations shall be applicable to Nagpur Municipal Corporation area with following modifications. i) Any open land or lands of closed Industrial unit/ units in the Industrial Zone (Excluding the leased out plots by NIT/ NMC) may be permitted to be utilized for all the users permissible in the Residential zone with permissible FSI in Residential Zone, subject to payment of premium to be paid equal to 15% of the rate of developed land as given in the Annual Statement of Rates published by IGR every year. However, for the Industrial Plots leased out by Planning Authority, (NIT / NMC) while granting I to R permission on these plots, FSI of 2.5 for purely commercial use and 2.00 for Mix use shall be permissible subject to payment of premium at the rate of 15% for Residential and 20% for Commercial use. Premium charges shall be as per rate of developed lands as given in the Annual Statement of Rates published by IGR every year. ii) Provisions of Regulation No. 4.8.1 (b) (iv) shall not be applicable where the Industrial layout has already been approved, and where in amenity space has already been provided in the approved layout.
10.3.4
For Plots admeasuring 1000 Sq.m. and above (including amalgamated plots) in Residential Zone, basic FSI shall be 1.25, in congested and non-congested area, irrespective of road width. In cases covered in Regulation No. 10.3.1 and 10.3.4 maximum building potential on plot including in-situ FSI shall remain the same, as mentioned in Table No. 6 A and 6 G. However, the owner shall be at liberty to avail, the difference of potential if any, out of column 4 or/ and 5.
10.4
NAGPUR METROPOLITAN REGION DEVELOPMENT AUTHORITY
10.4.1
(#) Development along Ring Road: 250 m. Residential Zone/ Residential Belt proposed along the 60 m. wide Outer Ring Road as a corridor development is sanctioned, subject to payment of premium. The development in this 250 m. corridor is permitted on payment of premium as decided by the Government on the total area of land under development or building permission. Such premium shall be deposited with the concerned Authority. (#)Clarification issued vide Order No. CR 236/18 (Part 2), dt., 23<sup>rd</sup>December, 2021
10.7.2
Manori-Gorai-Uttan Notified Area Special Development Control Regulations sanctioned for the Manori-Gorai-Uttan Notified Area as amended from time to time shall be applicable for the development/ redevelopment in the said notified area being a special Tourism Development Plan sanctioned for this notified area.
10.8
ULHASNAGAR CITY MUNICIPAL CORPORATION Regulations of unauthorised development in Ulhasnagar City Municipal Corporation shall be governed by the Regularisation of Unauthorised Developments in the City of Ulhasnagar Act, 2006.
10.910.9.1
KOLHAPUR MUNICIPAL CORPORATION Open spaces, area, FSI and height limitations for characteristic specified areas in Kolhapur. For characteristic specified areas in Kolhapur, listed herein below, shall have the open spaces and regulations for FSI and height limitations as given in table No. 10 B. below :-
TABLE NO - 10 B.
TABLE NO - 10 B.
TABLE NO - 10 B.
TABLE NO - 10 B.
TABLE NO - 10 B.
TABLE NO - 10 B.
TABLE NO - 10 B.
Sr. No.
Particulars of Areas
Minimum size of plot
Marginal distance to be observed
Marginal distance to be observed
Marginal distance to be observed
Permissible Max. built-up area
Sr. No.
Particulars of Areas
Minimum size of plot
Front
Rear
Side
Permissible Max. built-up area
1
2
3
4
5
6
7
1
Rajarampuri almost all plots are of 40 x 78 except corner plots of 80 x 78
40 x 78 = 3120 Sq.ft. (12.16 m. x 23.77 m.) 294 Sq.m.
10.0(3.05 m.)
2.0(0.60 m.)
2.6(0.76 m.)
-
2
Shahupuri Commercial lane 30 x 75 (9.12 m. x 22.86 m.) or 40 x 75 (12.16 m. x 22.86 m.) Part of old cantonment (new Shahupuri) Shown as ABCDE on Development Plan.
30 x75 = 2250 Sq.ft. ( 9.12 m. x 22.86 m.)
1.0(0.305m)
1.0(0.305m)
1.06
-
Shahu Road
40 x 75 = 3000 Sq.ft. (12.216m. x 22.86 m)
1.0(0.305m)
1.0(0.305m)
2.6
-
Other lanes (12.16 m. x 24.30 m.)
40 x80 = 3200 Sq.ft. ( 0.305 m.)
1.0(0.305m)
1.0(0.305m)
2.6
-
3
Laxmipuri
80 x160 = 12800 Sq.ft. ( 24.3m x48.64m)
20.0(6.00m)
5.0(1.52 m)
5.0(1.52 m)
-
50 x100 = 5000 Sq.ft.( 15.2 m x 30.48m)
10.0(3.05m)
2.6(0.76 m)
2.6(0.76 m)
-
40 x80 = 3200 Sq.ft. (12.16m x 24.3m)
5.0(1.52m)
2.6(0.76 m)
2.6(0.76 m)
4
Subhash road (South side Uma Talkies
40 x100 = 4000 Sq.ft. ( 12.16 m x 30.4 m)
10.0(3.05m)
3.0(0.91 m)
5.0(1.52 m)
-
Gokhale College
Upto 3000 Sq.ft.
10.0(3.05m)
3.0(0.91m)
5.0(1.52m)
-
5
Balbag Vashant
80 x 120 = 9600 Sq.ft. ( 24.32 m x 36.48m)
15.0(4.56 m )
10.8(3.04 m)
5.0(1.52 m)
-
6
Muskuti Talao
40 x 80 = 3200 Sq.ft. ( 12.16 m x 24.32 m )
5.0(1.52m)
2.6(0.76 m)
2.6(0.76 m)
-
7
Old cantonment (New Shahupuri) Remaining part area excluding in Sr. No. 2
80 x 120 = 9600 Sq.ft. ( 24.32 m x 36.48m)
2.6(0.76m)
2.6 (0.76m)
2.6(0.76 m)
-
40 x 80 = 3200 Sq.ft. ( 12.16 m x 24.32 m )
2.6(0.76m)
2.6(0.76m)
2.6(0.76m)
8
Patankar Colony
80 x 120 = 9600 Sq.ft. ( 24.32 m x 36.48m)
-
-
-
-
Main Road
10.0(3.05m)
3.0(0.91m)
5.0(1.52m)
-
Other Roads
5.0(1.52m)
2.6(0.76 m)
2.6(0.76 m)
-
9
Rajarampur New vasahat East side of Tararani vidyapeeth
40 x 80 = 3200 Sq.ft. ( 12.16 m x 24.32 m )
10.0(3.05m)
3.0(0.91m)
5.0(1.52m)
-
10
Petala New Mahadwar Road
40 x100 = 4000 Sq.ft. ( 12.16 m x 30.4 m) Other plots interior roads.
5.0( 1.52m)
3.0( 0.91m)
5.0( 1.52m)
-
11
Tarabai Park
5000 Sq.ft. and above ( 460 Sq.m.)
15.0(4.56 m )
10.0(3.05)
10.0(3.05m)
-
3000 Sq.ft. to 5000 Sq.ft. ( 278.5 Sq.m. to 460 Sq.m.)
15.0(4.56 m )
10.0(3.05)
7.6(2.25 m)
-
12
Shahaji Nagar
5000 Sq.ft. ( 460 Sq.m.)
15.0(4.56 m )
10.0(3.05)
10.0(3.05m)
-
13
Sykes Extension
80 x 120 = 9600 Sq.ft. ( 24.32 m x 36.40m)
15.0(4.56 m )
10.0(3.05)
10.0(3.05m)
-
CTS no. 1143, E
60 x 70 = 3200 Sq.ft. ( 18.29 m x 21.33 m )
10.0(3.05m)
5.0(1.52m)
5.0(1.52m)
-
CTS no. 1141, E
40 x 80 = 3200 Sq.ft. ( 12.16 m x 24.32 m )
5.0(1.52m)
2.6(0.76 m)
2.6(0.76 m)
-
14
Old Gavat Mandai opposite Jijamata Girls High School
40 x 80 = 3200 Sq.ft. ( 12.16 m x 24.32 m ) and other Plots.
10.0( 3.04m)
2.6( 0.76 m)
2.6( 0.76 m)
-
15
Subhash Nagar
40 x60 = 2400 Sq.ft. (12.16 m x 10.24m)
5.0( 1.52m)
2.6( 0.76 m)
2.6( 0.76 m)
-
16
Jawahar Nagar
40 x60 =2400 Sq.ft. (12.16 m x 10.24m)
10.0( 3.05m)
5.0( 1.52m)
5.0( 1.52m)
-
17
Line Bazar near Masjid
40 x90= 3600 Sq.ft. (12.16 m x 27.42m))
10.0( 3.05m)
2.6( 0.60 m)
2.6( 0.76 m)
-
18
Shivaji Udyam Nagar (Industrial use only permitted except to residential use already in use)
80 x 120 = 9600 Sq.ft. ( 24.32 m x 36.48m)
20.0(6.10 m)
3.6(1.064m)
2.6(0.76m)
-
40 x 80 = 3200 Sq.ft. ( 12.16 m x 24.32 m )
5.0(1.52m)
2.6( 0.76 m)
2.6( 0.76 m)
-
On Rajaram Road 80 x80 = 6400 Sq.ft. ( 24.32 m x 24.32m)
5.0( 1.52m)
3.6(1.064m)
5.0( 1.52m)
-
40 x 80 = 3200 Sq.ft. ( 12.16 m x 24.32 m )
5.0( 1.52 m)
3.6( .064m)
5.0( 1.52m)
-
CTS No. 1325
40 x 80 = 3200 Sq.ft. ( 12.16 m x 24.32 m )
5.0(1.52m)
2.6( 0.76 m)
2.6( 0.76 m)
-
CTS No. 1243/2 to 1243/4 for foundry use. Power Nagar, Udyam nagar extension
20.0(6.10 m)
5.0( 1.52m)
5.0( 1.52m)
-
19
Dhor Vasahant
80x 160 = 12800 Sq.ft. ( 24.32 m x 48.64m)
15.0( 4.56 m)
10.0( 3.05 m)
5.0( 1.52 m)
-
20
Town Planning Scheme
Kolhapur No. 1 Special
-
-
-
-
For final Plots
Upto 2 Gunthas ( less than 2 area)
5.0( 1.52 m)
5.0( 1.52 m)
2.06(0.76m)
50%
For final Plot
2 Gunthas to 5 gunthas ( 2 Ares to 5 areas)
10.0( 3.05m)
5.0( 1.52m)
5.0( 1.52m)
50%
For final Plots
5 gunthas (5 Ares)
15.0( 4.5 m )
15.0(4.56 m )
10.0( 3.05 m)
33%
21
Town Planning Scheme Kolhapur No. II Special Regulations.
Town Planning Scheme Kolhapur No. II Special Regulations.
Town Planning Scheme Kolhapur No. II Special Regulations.
Town Planning Scheme Kolhapur No. II Special Regulations.
Town Planning Scheme Kolhapur No. II Special Regulations.
Town Planning Scheme Kolhapur No. II Special Regulations.
B)
Excepting above further final plots
15.0(4.56 m)
15.0(4.56 m)
5.0( 1.52m)
33%
22
Two planning Scheme Kolhapur No. III Special Regulations.
Sakoli Vasahat to the South West of Rankala S.T. Stand
As per gaothan regulation
1.0(0.305m)
1.6(0.457m)
-
28
Timber Market
100x150 - 15000 Sq.ft. ( 30.48 m x 45.72m)
15.0(4.56 m)
15.0(4.56 m)
15.0 (4.56m)
-
29
Golibar Vasahat K Bavada
40 x 40 = 1600 Sq.ft. ( 12.16 m x 12.16m )
2.6( 0.76 m)
2.6( 0.76 m)
2.6( 0.76 m)
-
30
Patharvat Vasahat Near Daulat Nagar
30 x 50 = 1500 Sq.ft. ( 9.14 m x 15.24 m )
5.0( 1.52m)
2.6( 0.76 m)
2.6( 0.76 m)
-
31a) b)
Old Vasahats Dombar Wada Takala portion on Koti-tirth
Gaothan Regulation would be applicable
-
-
-
-
32
Sotewala Vasahat
5.0( 1.52m)
2.0( 0.60 m)
2.6( 0.76 m)
-
33
Nagala Area of Tarbai Park
5000 Sq.ft. and above ( 460 Sq.m.& above)
15.0(4.56 m)
10.0( 3.05 m)
10.0( 3.05 m)
33%
3000 Sq.ft. to 5000 Sq.ft. (278.5 Sq.m. to 460 Sq.m.)
15.0(4.56 m)
10.0( 3.05 m)
7.6(2.25 m)
33%
34
Hind co-Operative Housing Society (Ruikar Colony)
65 x 80 = 52000 Sq.ft. ( 19.81 m x 24.36 m )
10.0(3.05 m)
-
7.0(2.135m)
-
60 x 90 = 5400 Sq.ft. ( 18.91m x 27.42m )
15.0(4.56 m)
5.0(1.52 m)
7.0(2.135m)
-
35
Dinanath Mangeshkar Nagar - site No. 272 & 273
i) 1500 to below 2000 Sq.ft. (139.35 Sq.m. to 185.80 Sq.m.)
10.0 (3.05 m)
5.0(1.52 m)
5.0(1.52 m)
1/2
ii) 2000 to below 3000 Sq.ft. (185.0 Sq.m. to 278.7 Sq.ft.)
10.0( 3.05 m)
10.0( 1.52 m)
5.0( 1.52 m)
1/2
iii) 3000 to below 5000 Sq.ft. ( 278.7 Sq.m. to 464.5 Sq.m.)
15.0(4.56 m)
10.0( 3.05 m)
7.6(2.25 m)
1/2
36
Sagarmal ( S.No. 1330) E Ward, site No. 338)
do
do
do
do
do
37
R.S. No. 690 site No. 365
400 Sq.ft.( 37016 Sq.m.) 400 to 784 Sq.ft. ( 37016 to 67.03 Sq.m.)
Gaothan Regulatio n shall be applied5.0(1.52m)
-2.0(0.60m)
-2.6(0.76m)
-
38
Site No. 87 ( Housing the Dishoused)
AS mentioned in sr.no.l35
AS mentione d in sr.no.l35
-
-
-
39
R.S. No 711 K, Karveer
500 to 1000 Sq.ft. ( 46.45 to 92.90 sq.mt.)
5.0( 1.52m)
-
3.0( 0.9 m ) on one side2.6(Common distance ( 0.76m)
-
40
Remanmala Zopadpatti
1800 to 2000 Sq.ft. ( 1167.22 to 185.8 Sq.m.)
5.0(1.52 m)
2.6( 0.76 m)
2.6( 0.76 m)
1/2
41
Site No. 60
50 x 30 = 1500 Sq.ft. (15.24 m x 9.14 m)
5.0(1.52 m)
2.6(0.76 m)
2.6( 0.76 m)
1/2
42
Daulat Nagar
1500 Sq.ft. ( 139.35m)
5.0(1.52 m)
2.6(0.76 m)
2.6( 0.76 m)
1/2
Note 1 – Maximum permissible Basic FSI for Sr. No. 1 to 3 and 26, 27 and 31 shall be 1.5 for residential use and 2.0 for residential cum-Commercial use and for remaining areas, it shall be 1.1 and mix non-residential use to be allowed without any restriction of percentage.
Note 2 – The properties fronting on ― Mahadwar to Mahadwar Chowk Road ― shall be given building permission with a front set back of only 0.5 m.
Note 3 – The Maximum permissible Basic FSI, permissible TDR loading and additional FSI on payment of premium shall be as allowed as per these regulations.
Note 4 – Height of building
i) Height of building to be constructed on Kiranotsav Marg of Mahalaxmi Temple shall be determined by the Municipal Commissioner.
For Sr. No. 1, 2 & 3 – upto 21 m. height with marginal distances as per column No. 4, 5 & 6 of table above. Above 21 m. height - it shall be as per Regulation No. (1) 6.1.1(iii), (vi) or Regulation No.6.2.3, as the case may be.
iii) For Sr. No. 4 to 42 upto 15 m. as per column No 4, 5 & 6 of table above.
For height above 15 m., 1.0 m. set-back for every 3 m. height on all sides except front for open plot. For the existing structures and ongoing projects only front and rear set-back to be kept in addition to the marginal open spaces as per column No. 4, 5 & 6 of table above. This may be allowed in form of step margin. Side margin as mentioned in column No. 6 of table above, may be continued upto 21 m. height.
Above 21 m. height - it shall be as per Regulation No. (1) 6.1.1(iii), (vi) or Regulation No.6.2.3, as the case may be.
Note - 5 Other provisions excluding above, shall be as per UDCPR.
Note - 6 For parking spaces in basement and upper floor at least one vehicular ramp of 3.00m. width in side and rear margin for 4 wheeler ( )and for 2 wheeler or one vehicular ramp of 2 m. width for 2 wheeler shall be provided for plot area upto 1000 Sq.m. (2)or the owner may provide minimum 2 Car lifts instead of Ramp.
10.9.2 Height of building on Kiranotsav Marg other than specified area.
204
The height of building to be constructed along Kiranotsav Marg of Mahalaxmi Temple shall be determined by the Municipal Commissioner.
Row houses with or without common walls
a
40 m2 to less than 150 m2
13 m
1.5
0.0
0.0
2.2.5
b
150 m2 to less than 150 m2
13 m
3.0
0.0
0.0
3.0
Semi-detached building
a
150 m2 to less than 150 m2
13 m
1.5
2.25
0.0
2.25
b
150 m2 to less than 300 m2
13 m
3.0
1.5
0.0
3.0
c
More than 300 m2 to less than 450 m2
13 m
3.0
3.0
0.0
3.0
Detached building
a
450 m2 to less than 1000 m2
13 m
3.0
3.0
3.0
3.0
b
1000 m2 and above
As per regulation No. 6.2 and 6.3 of these regulation.
(#)3) In case of plot where basic FSI is 1.5 the maximum building potential of plot including insitu FSI as mentioned in table 6 G may be allowed to be exceeded by further 0.5.
All other plots having access road below 9m width.
1.80 or Authorisedly consumed FSI + 50% Incentive whichever is less
If the entitlement of FSI as above is less than maximum building potential mentioned in column 6 or 9 of Table 6-G of Regulation No.6.3, then difference of FSI entitlement shall be availed by payment of premium. Moreover, the maximum building potential mentioned in Table No.6-G shall be allowed considering the road width one step below subject to road width of minimum 12 m.
e.g. for the roads as mentioned at Sr.No.3 in Table No.6-G, the maximum building potential shall be considered as given at Sr.No.4.
Identification of dangerous / dilapidated buildings shall be done by a Committee Under the Chairmanship of the Municipal Commissioner, NMMC, comprising Superintendent Engineer, Public Works Department, Thane; Joint Director, Town Planning, Konkan Division; City Engineer, NMMC; Chief Engineer, CIDCO; Chief Planner, CIDCO and such other members as may be appointed by the Municipal Commissioner, NMMC, having regard to their academic qualifications, technical competence and previous experience in the field of Structural Engineering.
Where redevelopment of any dangerous / dilapidated buildings(s) in a Housing Scheme of CIDCO constructed building is undertaken by the Co-op Housing Society or the occupiers of such building(s) or by the lessees of CIDCO, the Rehabilitation area Entitlement, Incentive FSI and sharing of balance FSI shall be as follows:-
A) Rehabilitation Area Entitlement :
i) Under redevelopment of any dangerous / dilapidated building(s) in a Housing Scheme of CIDCO, the entitlement of rehabilitation are for an existing residential tenement shall be equal to sum total of-
(a) a basic entitlement equivalent to the carpet area of the existing tenement plus 35% thereof, subject to a minimum carpet area of 300 Sq.ft. and
(b) an additional entitlement, governed by the size of the plot under redevelopment, in accordance with the Table below :-
Table No - 10 D
Area of the Plot under
Additional Entitlement (As % of the
Redevelopment
Carpet Area of the Existing Tenement)
Upto 4000 Sq.m.
Nil
Above 4000 Sq.m. to 2 hect
10%
Above 2 hect to 5 hect
15%
Above 5 hect to 10 hect
20%
Explanation: The plot under redevelopment means the total area of the land on which redevelopment of dangerous / dilapidated building (s) is to be undertaken.
Provided that the maximum entitlement of rehabilitation area shall in no case exceed the maximum limit of carpet area prescribed for MIG category by the Govt., as applicable on the date of approval of the redevelopment project.
Provided further that the entitlement of rehabilitation area, as admissible under this regulation, shall be exclusive of the area of balcony.
ii) Under redevelopment of any dangerous / dilapidated building(s) in a Housing Scheme of CIDCO, the entitlement of rehabilitation area of any existing authorized commercial unit / amenity unit in the Residential Housing Scheme shall be equal to the carpet area of the existing unit plus 20% thereof.
B) Incentive FSI : Incentive FSI admissible against the FSI required for rehabilitation, as calculated above, shall be based on the ratio (hereinafter referred to as Basic Ratio) of Land Rate )LR) in Rs/Sq.m. of the plot under redevelopment as per the Annual Schedule of Rates (ASR) and Rate of Construction (RC)* in Rs/Sq.m. applicable to the area as per the ASR and shall be as given in the Table below :-
Table No - 10 E
Basic Ration (LR/RC)
Incentive (As % of Admissible Rehabilitation Area)
Above 3.00
70%
Above 2.00 and upto 3.00
80%
Above 1.00 and upto 2.00
90%
Upto 1.00
100%
Explanation :- *RC is the rate of construction in respect of R.C.C. Construction, as published by the Chief Controlling Revenue Authority & Inspector General of Registration, Maharashtra State in the Annual Schedule of Rates.
Provided that the above incentive will be subject to the availability of the FSI on the Plot under redevelopment and its distribution by NMMC, with prior approval of CIDCO.
Provided further that in case there are more than one land rate applicable to different parts of the plot under redevelopment, a weighted average of all the applicable rates shall be taken for calculating the Average Land Rates and the Basic Ratio.
Provided further that the Land Rate (LR) and the Rate of Construction (RC) for calculation of the Basic Ration shall be taken for the year in which the redevelopment project is approved by the authority.
C) Sharing of the Balance FSI :
The FSI remaining in balance after providing for the rehabilitation and the incentive components, calculated as per (A) and (B) above respectively, shall be shared between the existing or proposed Co-operative Housing Society / Apartment Ownership Association and CIDCO, in the form of built-up area, as given in Table below and the share of CIDCO shall be handed over to CIDCO free of cost.
Table No - 10 F
Basic Ratio (LR/RC)
Sharing of Balance FSI
Society / Association Share
CIDCO Share
Above 3.00
30%
70%
Above 2.00 and upto 3.00
40%
60%
Above 1.00 and upto 2.00
50%
50%
Upto 1.00
60%
40%
Provided that building or buildings under redevelopment in the NMMC area, upto 20% of the CIDCO‘s share in the form of tenement shall be handed over free of cost to the NMMC. NMMC require the same for rehabilitation of the project affected persons.
2.1 Where redevelopment of dangerous / dilapidated building(s) in a Housing Scheme of CIDCO is undertaken by CIDCO directly or jointly by CIDCO along with the Co-operative Housing Society / Association or the occupiers of such building(s) or by the lessees of CIDCO, the Rehabilitation Area Entitlement, incentive FSI and sharing of balance FSI shall be as follows:
A) Rehabilitation Area Entitlement :
The Rehabilitation Area Entitlement shall be increased by 15% of the existing carpet area, over and above the Rehabilitation Area Entitlement calculated in (A) of Clause 2 above, subject to the maximum of the size of MIG, prescribed by the Government in the Housing Department.
B) Incentive FSI : Incentive FSI shall be the same as in (B) of Clause 2.
C) Sharing of the balance FSI : There shall be no sharing of the balance FSI, which shall be entirely available to CIDCO for implementing Affordable Housing Project.
3. Other requirement / Criteria :
For the purpose of calculating the FSI, the entire area of the layout including widening of existing roads and internal roads but excluding the land earmarked for public amenities shall be considered. Sub-division as well as amalgamation of plots shall be permissible. Amalgamation of more than one Apartment Owners‘ Association / Co. op. Hsg. Society (CHS) / Residents‘ Association shall be permissible and after such amalgamation, the amalgamated plot should be in the name of the applicant CHS with legal ownership title, without considering the provision made in the Regulation of the DCR. However consent of at least 70% leaseholders / occupants who intend to amalgamate such condominium shall be necessary.
ii. In a condominium/plot area, widening of existing roads as per the regular line of street prescribed by the Commissioner, NMMC or widening of road providing vehicular access to the condominium plot to bring it to the minimum right of way as prescribed in Table No. 10 C, shall be permissible for reconstruction / redevelopment, after handing over required stretch of land under road to NMMC, free of cost, duly developed with
storm water drains and footpath, if any, to the satisfaction of the Municipal Commissioner.
iii. In case where there are a number of dangerous / dilapidated buildings on a plot, in such cases, equivalent Land component of such buildings shall be worked out and incentive F.S.I. shall be based on such land component.
iv. The normal permissible tenement density per net hectare may be allowed to be exceeded in multiple of F.S.I. permissible.
v. The existing residential premises (other than R+C premises) shall be permitted to be redeveloped for residential user only. No change of use from Residential to Residential cum Commercial shall be permitted. However, in such premises, if area of such plot is more than 1000 Sq.m. and the same is fronting on a road having width of 20 mtr and above then it shall be permissible to construct convenience shopping to the extent of 5% of the plot area and if the plot area is more than1000 sq.mr and the plot is fronting on a road having width of 30 mtrs and above then this limit for convenience shopping will be upto 10%.
vi. In a condominium/plot area, It shall be mandatory to keep minimum 10% or 15%, as the case may be, compulsory recreational open space on ground clearly open to sky over and above podium garden, in the proposed redevelopment project in respect of land area between 2500 sq.mt. to 4000 sq.mt. or more than 4000 sq.mt., respectively.
vii. 5% of the Plot area under reconstruction / redevelopment project shall be surrendered to the Municipal Corporation, free of cost, towards essential amenity area, in case the plot area is more than 2500 sq.mt. The FSI of such amenity area shall be permissible on the balance plot area and the entire area of such amenity space will be considered for computation of FSI, without deducting this area from the gross plot area. However, 1.0 FSI out of amenity space FSI will be deducted from the total permissible FSI. Alternatively carpet area equivalent to 5% of the area of the plot Under redevelopment can be constructed within the Scheme, providing Separate access, and handed over to NMMC free of cost as Social amenity.
viii. The Layout of entire condominium / residential / Residential cum commercial premises, duly signed by the Apartment owners‘ Association/CHS shall be submitted at the time of Commencement Certificate to ascertain the feasibility of the entire condominium for redevelopment, so that in future, proper redevelopment of other buildings in the condominium/residential premises is smoothly feasible. However, such redevelopment can be undertaken in a phased manner in respect of one or two buildings likewise as per the approved layout of the entire condominium/residential premises. In case of such partial redevelopment, the infrastructure charges shall also be deposited in proportion to the area under such partial redevelopment.
ix. For the purpose of deciding the authenticity of the age of the structure, if the approval plans of such existing structure are not available, the Municipal Commissioner shall consider other evidence such as Assessment Record, or city survey record or sanad.
x. In any Redevelopment project where the existing or proposed Co-operative Housing Society/Apartment Owners‘ Association/Developer appointed by the concerned Society/Association has obtained No Objection Certificate from the CIDCO, thereby securing additional balance FSI with the consent of 70% of its members and where such NOC holder has made provision for alternative accommodation in the proposed building (including transit accommodation), then it shall be obligatory for all the occupiers / members to participate in the Redevelopment Scheme and vacate the
existing tenements for the purpose of redevelopment. However, in case of Apartment owners‘ Association, the Consent as per the concerned Act will be required.
xi. For redevelopment of any dangerous / dilapidated buildings in any Housing Scheme of CIDCO under clause 2.1 hereinabove, by CIDCO, the consent of the Cooperative Housing Society in the form of a valid Resolution as per the Co-operative Societies Act, 1960 will be sufficient. Similarly in case of Apartment Owners‘ Association, the consent as per the concerned Act will be required.
xii. For providing the requisite infrastructure for the increased population, an infrastructure charge at the rate of 10% of the Land Rate as per the ASR of the year of approval of the redevelopment project shall be levied and charged by the NMMC for the extra FSI granted for the redevelopment project, over and above the Basic Zonal FSI.
xiii. A corpus fund, as may be decided by Municipal Commissioner, shall be created by the Developer which shall remain with the concerned Co-operative Housing Society / Apartment Owners‘ Association for the maintenance of the new buildings under the Rehabilitation Component.
xiv. For the purpose of this Regulation, the carpet areas for EWS, LIG or MIG tenements shall be as determined by the Government in the Housing Department from time to time.
XV. Any redevelopment proposal where NMMC has already issued Commencement Certificate (C.C.) prior to the date of coming into force of this Modification (hereinafter referred to as ―the appointed date‖) and which is valid as on the appointed date, shall be allowed to convert to redevelopment projects under this Regulation, provided it satisfies all the requirements specified in this Regulation.
10.10.3 Road width of 11 m.
The road width of 11 m. in Navi Mumbai Municipal Corporation area shall be treated at par width of 12 m. for all purposes including permissible uses mentioned in this UDCPR.
10.10.4 Allowance of premium FSI in lieu of TDR
In addition to the quantum of premium FSI mentioned in Table 6A of Regulation No.6.1.1 and Table 6G of Regulation No.6.3, the additional premium FSI to the extent of TDR mentioned in the said table shall be allowed till the generation of TDR in Navi Mumbai Municipal Corporation area (1) and CIDCO as a Planning Authority by virtue of NTDA.
10.10.5 Provision of Amenity Space.
The Regulation No.3.5 shall not be applicable to CIDCO area.
10.10.6 Provision of Recreational Open Space
The recreational open space required to be provided in the lands allotted outside the Action area shall be as per the relevant clause of the Agreement to lease or as per these regulations (UDCPR), whichever is more.
The Action area means area for which the CIDCO intends to prepare a detailed layout plan with special development control regulations.
10.11 National Park and Tungareshwar Eco-sensitive Zone -
10.11.1 Development around National Park and Tungareshwar Eco-sensitive Zone
The restrictions imposed by Ministry of Environment, Forests and Climate Change for the Ecosensitive Zone declared around Sanjay Gandhi National Park and Tungareshwar Eco-sensitive Zone shall be applicable as amended from time to time in addition to these Regulations.
10.12Maharashtra Airport Development Company Notified Area.
10.12.1 In the areas notified for Maharashtra Airport Development Company as Planning Authority / Special Planning Authority, the following additional regulation shall be applicable. The basic FSI permissible for development in Airport and allied activities / services, Special Economic Zone, Mix Use Zone, Public-Semi-Public Zone shall be 1.50.
10.13 BHIWANDI SURROUNDING NOTIFIED AREA
10.13.1 Regulations for Affordable Housing Scheme:
In order to promote construction of affordable housing stock on private lands, the Planning Authority may permit implementation of Affordable Housing Scheme in accordance with the provisions of these Regulations. Affordable Housing Scheme (hereinafter referred to as 'the Scheme') shall be permissible only on the lands situated within the limits of the Bhiwandi Surrounding Notified Area in the Mumbai Metropolitan Region (MMR).
(i) Affordable Housing Scheme shall be permissible in Residential Zone / Affordable Housing Zone shown on the Development Plan only and on plots having access from an existing or proposed Development Plan Road having width equal to or in excess of 18 nit, or an existing road in respect of which Regular Line of Street has been declared under the relevant provisions of Maharashtra Municipal Corporation Act, Maharashtra Municipal Councils, Nagar Panchayats and Industrial Townships Act, 1965 for a width of 18 mt. or more, provided permissible FSI on such plots is 0.95 or more and TDR/additional FSI on payment of premium more than 0.6 is allowable. However in case of a proposed road, the land under the said proposed road shall be acquired before the approval of building plans for the Affordable Housing Scheme. Affordable Housing Scheme shall not be allowed in areas where FSI is less than 0.95 or where use of TDR is not permissible.
(ii) Minimum plot area for the Affordable Housing Scheme shall be 4000 sq.mt. excluding area under D.P. Roads and D.P. Reservations, if any.
(iii) The plot under the Scheme shall be independent, unencumbered and contiguous.
(iv) The Scheme shall not be permissible in congested areas, demarcated as such on the Development Plan.
The Special Planning Authority for Bhiwandi Surrounding Notified Area shall be competent to grant both location clearance and layout approval/building permission for an Affordable Housing Scheme.
(i) Maximum permissible FSI (including the base FSI of 1.00) under the Scheme shall be 3.00 on the gross plot area, including mandatory layout recreational open space and Amenity Space. The FSI to be utilized shall be in the proportion of 1:3 for the Affordable Housing Component and the Free Sale Housing Component on 1/4th and 3/4th part of the land respectively. Thus Affordable Housing and Free Sale Housing shall be proposed on the same plot of land but on two separate independently buildable pockets. For lands in
Affordable Housing Zones, the owner/ developer may be allowed to develop the land as per the Rules of the Affordable Housing Policy with the proviso that free sale to Affordable Housing FSI ratio will be 1.8:1 instead of 1.66 : 1 and the maximum FSI will be 2.5. Or
the owner / developer may be allowed to develop the land as permissible in Residential Zone as per prevailing Development Control Regulation subject to the condition that the area of tenements to be constructed with entire potential of the land, shall be of Affordable Housing Scheme. However if the provisions of inclusive housing stipulated in UDCPR are applicable to this area then, it shall also be made applicable to such land.
(ii) Under Affordable Housing Scheme, upto 15 % of the total built-up area of the Affordable Housing Component may be used for construction of shops / commercial use as per the direction of Special Planning Authority for Bhiwandi Surrounding Notified Area and such commercial built-up area shall be handed over to the Special Planning Authority for Bhiwandi Surrounding Notified Area free of cost.
(i) An Affordable Housing Unit shall be a self-contained dwelling unit of 25 sq.mt, carpet area, However the carpet area of a Housing Unit shall be 160 Sq.ft., where the construction under the Rental Housing Scheme has already commenced.
(ii) The amenity space for Affordable Housing shall be 10 % of the gross plot area under the Scheme and it shall be proportionately provided in the area earmarked for the Affordable Housing Component and the Area kept for Free Sale Housing Component.
Provided that where the Scheme is to be implemented on a plot in Industrial Zone where the Planning Authority has duly permitted Residential user under the relevant provisions of the Development Control Regulations:-
no further area shall be required to be kept as amenity space under Regulation 5 (ii) for the Scheme if the area prescribed to be kept as amenity space while permitting residential user in Industrial zone is equal to or more than 10% of the gross plot area.
only the balance area shall be required to be kept as amenity space under Regulation 5(ii) for the Scheme if the area of amenity space prescribed by the Planning Authority, while permitting residential user in Industrial zone, falls short of 10%.
(iii) Notwithstanding anything contained in the relevant provisions of the Development Control Regulations of Amenity Space in general, and also regarding permitting Residential User in Industrial Zone, it shall be obligatory on the Developer/Owner to develop the amenity space for users (hereinafter referred to as prescribed amenity users) such as School, Play Ground, Garden, Health Care Facilities, Multipurpose Hall, Auditorium, etc. with the approval of Chief Executive Officer of Special Planning Authority, as per the specifications prescribed by the said Authority, subject to the condition that at least 50% of such amenity space shall be kept for open users, before seeking Occupancy Certificate for the Free Sale Housing Component of the Scheme, failing which the land under such amenity space shall be handed over free of cost to the Planning Authority and such land shall be developed by the Chief Executive Officer of Special Planning Authority for the aforesaid prescribed amenity users only.
No compensation in the form of TDR shall be admissible to the Owner/Developer for development of such prescribed amenities under this Regulation.
(iv) Irrespective of whether the Owner / Developer develops the prescribed amenity users as per the provision of Clause (iii) above or fails to do so, the process of handing over the
land under such amenity space, along with the developed prescribed amenities, where such prescribed amenities have been developed, shall be completed within one month from the date of application by the Developer / Owner for seeking Occupancy Certificate for the free sale Housing Component of the Scheme and if such handing over process is not completed within the said period, the occupancy Certificate for the free sale Housing Component of the Scheme shall be withheld by the Chief Executive Officer of Special Planning Authority, till such amenity space, along with developed prescribed amenities, where such prescribed amenities have been developed, is handed over to the Planning Authority.
(v) Under the Affordable Housing Scheme, there shall be a welfare hall and a Balwadi at the rate of 30 sq.mt. for every multiple or part of 200 residential units and an office for Managers/Co-operative Housing Society at the rate of 30 sq.mt. per every multiple or part of 500 residential units which shall be treated as a part of Affordable Housing Component and shall not be counted towards the FSI while computing 3.00 FSI on the site and shall be given along with layout/DP roads and shops, free of cost to the Special Planning Authority for Bhiwandi Surrounding Notified Area. These facilities shall be constructed at locations as suggested by the Special Planning Authority for Bhiwandi Surrounding Notified Area and shall be transferred free of cost to it.
Under the Affordable Housing Scheme, Off-Site Infrastructure Charges at the rate of 5% of the land rate as given in the Annual Statement of Rates (ASR) prepared by the Inspector General of Registration, Maharashtra State, for the year in which Commencement Certificate is issued, subject to a minimum of Rs. 2000 per sq.mt., shall be paid by the Developer for the built up area, over and above the normal permissible FSI. This amount shall be paid to the Special Planning Authority for Bhiwandi Surrounding Notified Area.
7. Release of FSI under the Scheme shall be as follows:-
FSI for Affordable Housing Component and the Free Sale Housing Component under the Scheme shall be released in accordance with the following Table:-
Sr. No.
Stages of Release FSI
Affordable Housing Component*
Free Sale Component*
1
On Grant of Building Permission/ Commencement Certificate up to plinth by 1.1-L-B Special Planning Authority for Bhiwandi Surrounding Notified Area /Planning Authority to the Affordable Housing Project.
3.00
1.00
2
On Completion of 50% BUA of Affordable Component
-
0.75
3
On Completion of 100% BUA of Affordable Component
-
0.75
4
On handing over of 25% land and completed Affordable Housing Component buildings with Occupancy Certificate
-
0.50
Total
3.00*
3.00*
*Explanation- The FSI of 3.00 is to be calculated on the one-fourth of plot area for Affordable Housing Component as well as three-fourth of plot area for Free-Sale Housing Component.
The Affordable Housing Component under the Scheme shall be handed over alongwith the 1/4 part of the total plot of land, free of cost to the Special Planning Authority for Bhiwandi Surrounding Notified Area.
(i) The affordable Housing stock created under the Scheme shall be allotted by the Special Planning Authority for Bhiwandi Surrounding Notified Area as follows:-
Percent age
Allotment to
Category of Stock
Rate of Allotment
25
Special Planning Authority for Bhiwandi Surrounding Notified Area for use as PAP tenements or Staff Quarters or Transit Accommodation,
Ownership
Free of Cost
25
Outright sale to Govt. of Maharashtra and its statutory bodies / Govt. undertakings for use as PAP tenements or staff quarters or Transit Accommodation.
Ownership
As per Construction rate of ASR
50
Outright sale as affordable housing by MHADA subject to the general or specific directions of the Government.
Ownership
Free of Cost to MHADA which shall dispose of the same as per its pricing policy and by draw of lots.
(ii) The Affordable Housing stock shall be disposed of as per the prevailing policy of MHADA regarding pricing and disposal of its housing Stock meant for affordable housing. Each Project approved under the Scheme Shall be brought to the notice of the Government of Maharashtra and its statutory bodies/Government undertakings by means of Press Advertisement and if the Government of Maharashtra or any of its statutory bodies/Government Undertakings doesn't place firm requirement for the housing stock earmarked for them in the Scheme before the Completion Certificate/Occupation Certificate for the said Scheme is issued, the same shall come to the share of MHADA for outright sale as per the Prevailing Policy of the MHADA.
(i) The other aspects of the Development of Affordable Housing Scheme, not specifically dealt with hereinabove, shall be as per the relevant provisions of the Development Control Regulations of the respective Planning Authority.
(ii) It shall also be permissible for the Developer/Owner to utilize the FSI available for Free Sale Housing Component, fully /partly for any other user otherwise permissible as per Development Plan and Development Control Regulations.
(iii) In case owing to genuine hardship and site conditions, relaxation in marginal open spaces is sought by the Developer/Owner, the Chief Executive Officer of Special Planning Authority may consider such request, using his discretionary powers under the Development Control Regulations, subject to the condition that in no case shall the clear marginal open space reduced below 6.m No premium shall be charged for granting such relaxation in marginal open space in respect of Affordable Housing Component of the Scheme.
No project under the Rental Housing Scheme envisaged under the said directives issued by the Government vide orders dated 61h August 2008, 25h August 2009,49' November 2008 and August 2008 shall be permitted after the date on which the Notice No TPS-1212/79/C R 6 0 / 1 2 / 1 1 D 2 1 2 , Dated 30th November 2013 regarding this Regulation Under section 37 (IAA) of the Maharashtra Regional and Town Planning Act, 1066 was published in the official (herein after referred to as 'the cut cat date')
Provided that the Rental Housing Projects in respect of which Location Clearance had been granted by MMRDA, but Commencement Certificate has riot been issued by the concerned planning Authority, shall he allowed to continue, as such in case such project proposals are resubmitted to MMRDA within a period of 31) days from the date of this Notification in the Official Gazette. All such project proposals received by MMRDA within the prescribed time limit shall be scrutinized by MMRDA on merit and submitted for the prior approval of the State Government for their continuance under the Rental Housing Scheme.
Provided further that the Rental Housing Projects already approved may be allowed to be converted into Affordable Housing Projects under the provisions of this Regulation, with prior approval of the State Government.