7.5.1 Approach Road / Means of Access
1 Minimum Road width on which any development shall be allowed is 12 m. In case the proposed use or plot size in case of industrial use, demands a certain road width (Table No. 7.12) then it shall be considered in place of 12 m.
2 The designated roads widths in the Outline Development Plan are indicated in Table No 7.9.
Table No. 7.9: Road Widths in Outline Development Plan
| No | Width of Roads (m) |
|---|---|
| 1 | 12.00 |
| 2 | 15.00 |
| 3 | 18.00 |
| 4 | 25.00 |
| 5 | 30.00 |
| 6 | 45.00 |
3 For building units along overbridge or underbridge, the total width of the road including the these shall be considered for regulating permissible uses, margin, and height for proposed buildings.
4 In case the building unit abuts an existing road and not an Outline Development Plan Road / Town Planning Scheme Road, the right of way / plot boundary shall be considered as minimum 6 m from the centre line of such an existing road or more as decided by the Competent Authority. Roadside margin shall be considered from this imaginary plot boundary thus established. This additional land to be left is defined as ‘setback’. TDR for the land under setback may be given on the balance plot or can be used in zones indicated in Table No. 7.5 of Rule No. 7.3.1. For the sake of avoidance of doubts, it is hereby made clear that any non-notified road shall be presumed to have a minimum ROW of 12 m or existing ROW whichever is higher. (Refer Figure No. 7.2) 5 No new road shall be proposed, except for internal roads, which are less than 12 m in width.

Figure No. 7.2: Building Unit Abuts the Existing Road
Page No 76
Page No 77
7.5.2 Land Locked Building Unit and Required Road Width
1 In case of land locked plots (plots which do not have access from an ODP road or an existing road), the Competent Authority will prepare town planning schemes to provide appropriate access road to the plot.
Where a Town Planning Scheme is not prepared, the Competent Authority shall, for proper access, circulation, and mobility, prepare a road network plan. This shall be in sync with any, existing or Outline Development Plan roads.