3.1 Responsibilities of Owner / Developer
3.1.1 Owner / Developer to Apply for a Development Permission
Application for the Development Permission can be made by Owner or Developer of the plot on which development / building is proposed.
3.1.2 Responsibilities of Owner or Developer
The Owner or Developer shall:
1 Be responsible for ensuring that the development / building complies with these Rules.
2 Appoint an Architect on Record / Civil Engineer on Record to ensure compliance with all procedural requirements and to certify that the architectural design and specifications of the proposed development / building comply with the Outline Development Plan and these Rules.
3 Appoint a Structural Engineer on Record to certify that the structural design and specifications of the proposed development / building comply with these Rules.
4 Appoint a Clerk of Works on Record irrespective of type of building / construction in all building units having proposed built‐up area more than 1000 sq m for overall constant supervision of construction work on site and such person appointed shall not be allowed to supervise more than ten such sites at a time.
5 Appoint a Supervisor on Record irrespective of type of building / construction in all buildingunits having proposed built‐up area more than 300 sq m or irrespective of built-up area in case of Apartments (DW3), Mercantile, mixed use (mercantile + residential) for overall constant supervision of construction work on site and such person appointed shall not be allowed to supervise more than two such site at a time.
6 Certify along with the Clerk of Works on Record that the construction of the building has been undertaken as per detailed design and specifications stipulated by the Architect on Record or Civil Engineer on Record and the Structural Engineer on Record.
7 Certify along with the Supervisor on Record that the construction of the building has been undertaken as per detailed design and specifications stipulated by the Architect on Record or Engineer on Record and the Structural Engineer on Record and instruction given by Clerk of Works from time to time.
8 Obtain a development permission from the Competent Authority prior to commencement of building.
9 Submit construction progress reports and certificates as required to the Competent Authority.
10 Obtain an Occupancy Certificate prior to making use or occupying the building.
11 Not cause or allow any deviations from the sanctioned drawings in course of execution of the project against the instruction of Architect / Civil Engineer / Structural Designer / Clerk of Works and shall bear all responsibility for any irregularity committed in the use and function of the building or its parts for which the approval has been obtained.
12 Ensure that no construction is undertaken during the period that the Development Permission has lapsed, is suspended or cancelled.
13 Provide adequate safety measures for structural stability and protection against fire hazards likely from installation of services like electrical installation, plumbing, drainage, sanitation, water supply or any other requirements under the rules.
14 Ensure that only names of persons on record are displayed on site and no additional names are mentioned.
15 Be required to produce the construction documents and its intended use as per sanctioned plan to any prospective buyer.
16 Approval of drawings and acceptance of any statement, documents, structural report, structural drawings, progress certificate, or building completion certificate shall not discharge owner, engineer, architect, clerk of work and structural designer, supervisor, developer from their responsibilities imposed under the act or from the development regulations or from any other law for the time being in force.
Page No 32
17 Be held responsible if any unauthorized construction, addition, and alteration is done without prior permission of Competent Authority.
18 Take adequate measures to ensure that in the course of work, no damage is caused to the work under construction and the adjoining properties, no undue inconvenience is caused to the people in neighbourhood and no nuisance is caused to traffic & neighbouring people by way of noise, dust, smell, vibration etc.