15 Power of the competent authority to sanction or refuse erection or reerection.- (1) The competent authority shall refuse to sanction the erection or re-erection of any building, if it is in contravention of any of the provisions of these rules.
(2) The competent authority may sanction the erection or re-erection of any building either absolutely or subject to such modification in accordance with these rules as it may deem fit and one copy of the sanctioned plans shall be sent to the applicant.
(3) The intimation of sanction or rejection of the building plans shall be given in Form 'D'.
Presumption of sanction.- If the competent authority fails to convey approval or rejection within a period of sixty days of the receipt from any person of a valid application, complete in all respect to erect or re-erect a building, the plans shall without prejudice to the provisions of these rules and the restrictions specified for erection or re-erection of buildings, be deemed to have been sanctioned and the applicant may proceed with the erection or re-erection of building or carryout any development work as described in the application and in any accompanying documents, but not so as to contravene any of the provisions of the Act and rules made thereunder and the restriction specified for erection or re-erection of buildings.
Pre-approved building applications.- Where building applications which have been already approved by the competent authority before coming into force of these rules and where construction is in progress and has not been completed within the specified period of such approval, the said approval or permission shall be deemed to be sanctioned under these rules and shall only be eligible to re-validation under these rules, but where the construction on site has not yet been started, the owner or applicant may get his building plans revised after paying the requisite charges.
Validity period of sanction.– Every sanction for the erection or re-erection of any building or carrying out any development work shall remain in force, unless it is modified or cancelled by the competent authority by due process of law.
19 Submission of revised building plans in case of major alterations.- (1) If during the construction of a building, any major deviation from the sanctioned plan is intended to be made, approval of the competent authority for the same
Section 108(2)
Section 108 (2)
Section 108 (2)
Section 108 (2)
2392
may be obtained before the change is made. The revised plan showing the deviations shall be submitted and the procedure laid down for the sanction of building plan as specified in these rules shall be followed for all revised plans, along with the balance scrutiny fee, if any.
(2) The building approval is not necessary for compoundable alterations or violations, which do not otherwise violate any provisions regarding general building requirements, structural stability and fire safety requirements of these rules.
20 Revocation of sanction.–The sanction granted under these rules can be revoked by the competent authority, if it is found that such sanction has been obtained by the owner by misrepresentation of material facts or fraudulent document submitted along with the building plan application or otherwise or the majority of construction is not being done in accordance with the sanction granted.
21 Maintenance of e-register for sanction or Registration of Building Plans.– An online e-register shall be maintained for all building applications received, permissions given or deemed to have been given or refused or returned under these rules. The said register shall be available online to the public for inspection on Departmental website.
22 Damp proof course certificate.– The owner shall submit a certification from an Architect or Civil Engineer or by himself, in case of self-certification to the effect that the construction of building upto damp proof course level is as per sanctioned plan. The competent authority shall verify the certification and shall issue consent or comments within fifteen days of receiving the certification. The damp proof course certificate shall be deemed to be accepted, if it is in conformity with these rules, and no consent or comments have been passed by Competent Authority within a specified time.
Occupation certificate.– (1) The applicant shall apply for obtaining occupation certificate of the building to the competent authority for which completion certificate has already been issued as specified in Form- “I”. No owner or applicant shall occupy or allow any other person to occupy building or part of a building or any portion whatsoever, until such building or part thereof has been issued Occupation Certificate by the competent authority after checking and found fit to occupy the building.
(2) After receipt of application, the competent authority shall communicate in writing within thirty days, his decision for grant or refusal of such permission for occupation of the building in Form- ‘J’. The E-register shall be maintained as specified in these rules for maintaining record in
respect of Occupation Certificate. If no communication is received from the competent authority within thirty days of submitting the application for “Occupation Certificate”, the owner is permitted to occupy the building, considering deemed issuance of “Occupation certificate” and the application Form-D shall act as “Occupation Certificate”. However, the competent authority may check the violations made by the owner and take suitable action.
(3) Revocation of occupation certificate.- In case, after the issuance of occupation certificate, if found at any stage that the building is used for some other purpose against the permission or make any addition or alteration in the building without approval, then, after affording personal hearing to the owner, the competent authority may pass orders for revocation of occupation permission and the same shall be restored only after removal of violations.
Section 108 (2)
Section 108 (2)