Part IIIProcedure of Submission Ofapplications for Building Plan, Completion Certificate and Occupation Certificate
9 Erection or re-erection without permission. - Subject to the provisions of the Act and other provisions of these rules, no person shall commence the erection or re-erection of any building on any site without previous sanction of the competent authority.
10 Design and supervision. - Except where standard design has been supplied by the competent authority, the architectural design of every building shall be prepared and signed by an Architect or Civil Engineer and every building operation shall be supervised by an Architect or an Engineer.
11Section Application to erect or re-erect buildings (without self-certification).- (1) 108 (2) Every person who intends to erect or re-erect a building shall make an application in Form ‘A’ (Annexure 1) to the competent authority along with the following documents and fee as determined by the competent authority, namely:-
(i) ownership documents-lease deed or sale deed or possession letter in the name of owner issued by the allotment authority or permission to use the land issued by the competent authority;
(ii) Site plan as detailed in sub- rule (3);
(iii) Hard copy of Building plan and other plans along with an un-editable Compact Disc or DVD or any other electronic medium permissible by the competent authority from time to time containing the drawings in “dwg” format as detailed in sub- rule (4);
(iv) Details of specifications of the work to be executed in Form- ‘C’ (Annexure 3);
(v) Structural safety drawings (for record) as per Form- ‘B’ (Annexure 2);
(vi) Fire safety design as required under Part IV, Fire and Life Safety of the National Building Code of India, 2016, as amended from time to time, if applicable;
(vii) Heating, Ventilation, Air-Conditioning (H.V.A.C.) service plan wherever required;
(viii) Certificate of conformity to regulation and structural safety for the relevant buildings (depending upon type and height) in the relevant Form ‘B’(Annexure 2);
(ix) Public health services plan in un-editable compact Disc or DVD or any other electronic medium, containing drawings in “.dwg” format;
(x) Scrutiny fees (non–refundable) shall be deposited in favour of the competent authority through any specified payment mode, at the rate as described below:
(a) The applicant shall submit all kind of plans in electronic format on the online portal of the competent authority along with hard copies of the plans. The competent authority shall convey objections or observations or sanction or refusal through online portal or as specified mode.
(b) Every person applying under this rule shall appoint an Architect or Engineer for drawing up of building plans or structural drawings and for the supervision of erection or re-erection of the building. The supervision of erection or re-erection of residential or commercial building up to 15 metres height (G+3 floors including stilt) may be undertaken by the Architect or the Engineer. However, in case of buildings of 15 meters or above height (including stilt), the supervision shall be undertaken by both the Architect and the Engineer. During construction, if appointed Architect or Engineer notices that violations (except compoundable) are going on, he shall intimate the owner and advise him to stop further construction and remove the violation and shall also intimate the concerned authority.
(c) The applicant, the Architect and the Engineer shall sign the application, plans, structural drawings, specifications and the certificates as required in the relevant forms and documents, before making submission to the competent authority.
(d) In case of row type or semi-detached building, at the time of re-erection of building, the owner shall provide an indemnity bond as per Annexure 21 that in case of any damage caused to the adjoining property during construction, the owner shall be bound to get the damages repaired to the satisfaction of the neighbour.
(2) Size of drawing sheets and colouring of plans. – The size of drawing sheets shall be any of those specified below, namely:-
Scrutiny fees for building plan approval
Type of Building
Rate in Rupees Per Square meter of the Total Covered Area of the Proposed Building
Residential
30
Commercial buildings and other Public
60
Buildings Construction of boundary wall of plots having area more than 1000 sq.mt.
@Rs. 10 per running meter of the boundary wall.
No scrutiny fees for building plan approval of care centre or school for disabled persons, care centre or school for mentally challenged persons, orphanage and old age home shall be chargeable.
In case of revised or superseded plans, the fee chargeable shall be half of the rates charged for fresh plans for such category of plots as mentioned above.
Notes:-
(a) The decision of the competent authority, in case of any dispute, shall be final and binding on all concerned.
(b) At any stage during construction, if an Architect or Civil Engineer notices that violations (except compoundable ones) are taking place, he shall intimate to the concerned authority of such violations and stop further supervision. He shall also intimate the allottee about the violations and advise him to stop further construction. Complete details along with photographs shall be
Section 108(2)
submitted to the concerned authority. The competent authority shall immediately issue a notice to the owner on the basis of the Architect’s or Civil Engineer's certificate to suspend further work and rectify violations. In such cases, the owner shall be held responsible for further additions in violations. Such a situation shall automatically annul the process of self-certification and the owner may, after removal of violations, engage an Architect or Civil Engineer for preparing the revised drawings. In such case, completion shall be given only after scrutiny of revised drawings and inspection of site.
(c) The compoundable changes shall be allowed to be done, provided that at the completion stage all changes are incorporated by the Architect or Civil Engineer in the completion drawings to be submitted by the owner to the competent authority. While seeking completion certificate, the Architect or Civil Engineer shall give a certificate that all changes done are in accordance with these rules and policies of the Government as amended from time to time.
(d) After submission of application or during the construction of building, if the Owner or Architect or Civil Engineer or Structural Engineer are changed, the applicant shall intimate the competent authority by email or online building plan approval system that he is no longer responsible for the project from the date of actual dispatch of the letter. The information must be sent within seven days of occurrence of the change to the competent authority by the respective owner or Architect or Engineer. The construction work shall have to be suspended until the new owner or Architect or Civil Engineer or Structural Engineer, as case may be, undertakes the full responsibility of the project vide forms and documents submitted at the time of applying for erection or reerection of the building within seven days of his taking over. The owner’s intimation regarding change of name of professionals shall be considered to be final by the competent authority or any other person authorized by him.
13 Preparation of building plans of the Departments of the Government.- The Department of the Government intending to erect or re-erect building shall get their building plans prepared from the Department of Architecture of the State Government or Central Government, as the case may be, conforming to these building rules and shall issue a certificate specifying that the provisions of these building rules have been followed in all respects. Such plans shall be
Section 108 (2)
submitted to the competent authority for information and record before commencement of erection or re-erection of the building.
However, if the building plans are prepared by the private Architect or Civil Engineer, the same shall be submitted to the competent authority for approval.
14 Completion certificate. – (1) The applicant shall submit a notice of completion of the building to the competent authority regarding completion of the work as per approved plans. The notice of completion shall be submitted by the owner through the Architect and Engineer as engaged for building plan design who fulfills the specified qualifications mentioned in Annexure 13, or as the case may be, who has supervised the construction, in the Performa given in Form-‘F’ and ‘G’ respectively (Annexure 6 and Annexure 7), accompanied by three copies of completion plan and the following documents along with the specified fee, namely:-
(i) copy of all inspection reports of the Authority e.g. Fire Safety, Structural Safety, Green Building (if applicable) etc;
(ii) detail of compoundable violations from the approved building plans, if any, in the building, jointly signed by the owner, Architect and Engineer along with demand draft of the due payment for compounding charges of such violations at the rates specified by the competent authority shall be submitted;
(iii) complete completion drawings or as-built drawings - certified by the Architect and Engineer;
(iv) photographs of front, side, rear setbacks, front and rear elevation of the building shall be submitted along with photographs of essential areas like cut outs and shafts from the roof top. An un-editable compact disc or DVD or any other electronic media containing all photographs shall also be submitted;
(v) structural stability certificate duly signed by the Structural Engineer;
(vi) certificate of fitness of the lift from concerned Department wherever required;
(vii) certificate from the Punjab Energy Development Agency (PEDA) for installation of Rooftop Solar Photo Voltaic Power Plant in accordance to orders or policies issued by the Renewable Energy Department from time to time;
(viii) completion certificate or final Certificate or no objection certificate from the rating agencies (GRIHA/LEED/IGBC) for green building or Bureau of Energy Efficiency (BEE), Certified Energy Auditor for Green Building or constructing building in accordance to the provision of the Punjab Energy Conservation and Building Code, wherever applicable;
(ix) no objection certificate (NOC) of fire safety of building from concerned Fire Officer or an officer authorized for the purpose; and
(x) any other information or document that the Authority may deem fit.
(2) The ‘completion certificate’ or ‘partial completion certificate’ shall be issued on the basis of the following parameters, namely: -
(i) the applicant shall remove or demolish any temporary building which might have been erected and the debris from the site and adjoining roads or vacant site before the completion certificate is issued;
(ii) the partial completion certificate may be granted for partially constructed building with at least one habitable room, one water closet and one kitchen as per the sanctioned plan and duly functional in case of a residential house;
(iii) the partial completion certificate may be granted for partially constructed non-residential buildings subject to the minimum completion of 25 percent construction of the availed total floor area along with all the required public utilities and public safety measures;
(iv) the partial completion certificate to shop-cum-offices or shops may be granted subject to the condition that construction of ground floor is completed along with public safety measure;
(v) in case of large campus or complex, completion of individual block or building shall be issued by the competent authority in accordance with the construction work completed phase wise;
(vi) in case of high rise buildings, partial completion certificate shall be issued if the superstructure of the building has been constructed as per approved plans along with all the required parking, public utilities, public safety etc. measures of the proportionate area completed on site; and
(vii) the minimum permissible covered area as mentioned below shall have to be constructed to obtain partial completion certificate for industrial buildings:
Minimum permissible ground coverage to obtain partial completion certificate for industrial buildings
Serial Number
Area of site
Percentage of permissible ground coverage
I.
Upto 2 acre
25 percent
II.
Above 2 acre upto 5
acres 20 percent
III.
Above 5 acres
15 percent
(3) The competent authority on receipt of the notice of completion shall inspect the work and communicate the approval or refusal, or objection thereto, in the Performa given in Form- ‘H’ within thirty days from the receipt of notice of completion. However, the competent authority may also seek compounding charges of compoundable violations which are compoundable before issuance of completion certificate. If nothing is communicated within this period, it shall be deemed to have been approved for completion provided that the fact is immediately brought to the notice of the competent authority in writing by the person, who had given the notice and has not received any intimation from the competent authority within the specified period. Where the completion certificate is refused, the reasons shall be intimated for rejecting in the first instance itself.
(4) If the Architect or Engineer engaged by the owner or applicant submits a wrong report while making application under these rules or if any additional construction or violation is reported to exist at site or has concealed any fact or misrepresented regarding completion of construction of building along with its eligibility for seeking completion certificate or before the completion of such report, he shall be jointly and severally held responsible for such omission and complaint against the Architect or Engineer for suspension of his registration and the owner shall be liable to pay fo the penalty as may be decided by the competent authority after giving an opportunity of hearing. Further, if it is emerged that the information is concealed by the Architect or Engineer, necessary penal proceedings shall be initiated along with debarring such Engineer or Architect from practicing in the State of Punjab.
Section 108 (2)
Section 108 (2)
2391
16
Section 108 (2)
Section 108 (2)
17
Section 108 (2)
18
Size of drawing sheets
Serial Number
Sheet name
Sheet size (in mm)
I.
A0
841 X1189
II.
A1
594 X 841
III.
A2
420X594
IV.
A3
297 X 420
Note:
(a) All dimensions in plan can be indicated in metric or feet-inches units.
(b) Various elements of plans (site and building), elevation, section and details shall be shown in different colours and thickness or type of line, etc., and shall be preferably prepared in layers and as per Bureau of Indian Standard (BIS) Code.
(c) The prints of drawings shall be on one side of paper only.
(3) Site plan.- Site plan fully dimensioned shall be drawn to a scale of not less than 1: 500 for a site up to one hectare and not less than 1: 1000 for a site more than one hectare and shall show:-
(i) boundaries of the site and any contiguous features;
(ii) direction of the north point relative to the site of the building;
(iii) streets or roads adjoining the site with their width clearly dimensioned and names, if any, giving also all existing roads, trees, lamp posts or any other feature or structure likely to affect the approach to the building;
(iv) outlines of the proposed building;
(v) immediate neighbours on all sides identified, whether buildings or vacant plots;
(vi) levels of the site and the plinths of the building in relation to those of the neighbouring roads and also the level of courtyard and open space;
(vii) area calculations such as ground coverage, Floor Area Ratio and Non Floor Area Ratio, parking calculations, any other relevant calculations as required;
(viii) all existing buildings or structures on or over or under the site or projecting beyond it;
(ix) proposed access points on site boundary for the proposed construction;
(x) methods of disposal of waste water, sewerage and storm water;
(xi) surroundings up to a distance of fifteen metres on all sides from the boundaries of the site;
(xii) prominent trees in the area of the drawing and any important urban service points above or under ground (like sewer or water pipes, gas pipeline, transformers, electric poles or lines, phone distribution boxes, etc.);
(xiii) such other particulars as may be specified by the competent authority; and
(xiv) plot number or revenue particulars of the property on which the building is intended to be erected.
(4) Building plans, sections and elevations.- The building plans, sections and elevations shall be drawn to a scale of 1:100. The building plans and details so drawn shall show -
(i) the plans of all the floors including basements and all external elevations and cross sections illustrating distinctly all the different levels and minimum one section through staircase, water closet, bath, kitchen and garage;
(ii) the plinth level of the building with reference to the level of the mean level of street from where approach to the site is taken;
(iii) the schedule indicating the size of the doors, windows, openings and other methods of ventilation of each room or area;
(iv) the use or occupancy of all parts of the buildings;
(v) the means of access to the buildings and to its various floors as well as the means of escape in case of fire, if required under the specific law or code; along with ramps and steps with respect to the building;
(vi) in case of proposed additions and alterations in the existing building, all new works shall be shown on the drawings in distinctive colours along with index;
(vii) exact location of essential services, for example, water closet, sink, bath and the like;
(viii) the method of disposal of waste water, sewage, storm water and water supply in detail;
(ix) provision of rain water harvesting system in accordance with rule 40 (wherever applicable);
(x) provision for photovoltaic solar power plant in accordance with these rules (wherever applicable);
(xi) provision for barrier free build environment for persons with disability and elderly persons in accordance with these rules (wherever applicable);
(xii) indications of the north point relative to the plan.
Note: The requirement of 1:100 is permitted to be flexible for specific details needed for further illustration; and also for drawings for these in electronic form. In case any detail in building plan is not readable, the same can be shown in enlarged form with clouding of that area.
(5) Standard design and architectural controls.- Where the applicant intends to construct a building in accordance with a standard design, approved by the competent authority concerned, he shall obtain a copy of the same before starting the construction and notify the competent authority accordingly of the site and design. In such cases, he shall not be required to submit any building plan. However, the site plan showing access, building footprint and all other aspects in accordance with sub-rule (3) should be submitted. Only the design plans can be indicated referring to standard design names or numbers:
Provided that if the owner proposes certain permitted modifications in the standard design or the architectural controls, then he shall submit the same to the competent authority for approval.
Note: For any urban area within the State of Punjab, notified in the Master Plan as a “Special Area” of planning for any special purpose by virtue of historical, functional, natural features or any other significance, for which a Form Based Codes (FBC) or Regulating Plan has been prepared and notified by the concerned Local Authorities, provisions under sub-rules (3), (4) and (5) shall be in accordance with such Form Based Codes (FBC) or Regulating Plan superseding any other general development norms and standards stipulated in these Building Rules.
12 Procedure for submitting application through self-certification.- (1) TheSection 108 (2) self-certification is applicable on the following category of buildings, namely:-
(i) Residential plot having size upto 1000 sq.yd (836 sq.m);
(ii) Industrial plots having size upto 1000 sq.yd (836 sq.m); and
(iii) Commercial plots such as shop-cum-office (SCO), shop-cum-flat (SCF), Shops and Booths within approved layout for which standard design has been approved by the competent authority.
(2) Procedure.- (i) Any person intending to erect or re-erect building shall apply through an architect in Form ‘A’ along with documents specified in rule 11 to the competent authority for approval of building plans duly signed with stamp of “sanctioned”, under self-certification by giving thirty days notice to the competent authority for record of building plans intimating the date of start of construction. The construction of proposed building can be started after thirty days, in case any objection is not conveyed to the applicant.
(ii) The plan submitted shall conform to the provisions of these rules as amended from time to time and approved zoning plan. In this regard, a certificate shall be given on the plan as under, namely:-
“Certified that the above building plan is as per the zoning plan Drg. No. ........ dated..... and as per the Punjab Urban Planning and Development Building Rules, 2021 as amended from time to time.”
Architect/Civil Engineer
Seal with signature
(iii) Certificate of conformity to regulation and structural safety for the relevant buildings (depending upon type and height) in the relevant Form.
(iv) After receiving the above documents, the competent authority issues an autogeneration receipt mentioning that documents have been received and are being kept in the office for record with this understanding that these plans have been prepared as per the provisions of approved zoning plan and these rules. The competent authority shall also convey within thirty days to the applicant regarding discrepancies in the building plans and the applicant shall be bound to rectify the discrepancies in building plans and shall submit the same before start of the construction otherwise submitted plan shall be taken as deemed approved.
(v) The competent authority or any other person authorized by him reserves the right to check the building plans and construction at any stage and violations (except compoundable ones), if found, shall have to be rectified by the owner or applicant. In case the owner or applicant fails to rectify the violations, the competent authority may take necessary steps to remove the violations and the action shall also be taken against the defaulting Architect or Civil Engineer by referring his case to the Council of Architecture or Institute of Engineers of misconduct and for debarring or blacklisting the Architect or Civil Engineer from doing all practice, especially for the Departments of the State Government or Authorities. All rectifications shall be at the risk and cost of the owner and no plea of the owner shall be entertained for any default committed by the Architect or Civil Engineer engaged by him. In all such cases, the procedure of self-certification shall stand aborted.
(vi) If a building is erected or re-erected or construction work is commenced in contravention to any of the building regulations, the competent authority or any other person authorized by him shall be competent to require the building to be altered or demolished, by a written notice delivered to the owner. Such notice shall also specify the period during which such alteration or demolition has to be completed and if the notice is not complied with, the competent authority or any other person authorized by him may demolish the said building at the expense of the owner.