3.1 Clearances at Master Plan level :
Individual construction proposals should not generally require separate clearances from various authorities each time. Such clearances should be integrated into the DCR of the Master/Development Plan of the concerned city. The areas unaffected by any of the restrictions should be clearly marked out and mapped on a GIS platform. Area zones of differential control regulations (within the city) by any of these agencies may also be mapped accordingly. This will result in a composite map of the city with various control regulations as per the various agencies clearly marked on the map. Thus, the sites which are located outside these restricted/regulated areas would not require clearance from the respective authorities, thereby reducing the clearance
process significantly. Following are the clearances which should be integrated into the city Master Plan:—
| S. No. | Name of Agency | Type of Clearance | Area of Influence |
|---|---|---|---|
| 1 | National Monuments Authority through Local BPIA | Ancient Monument approval | As prescribed in the AMASAR (Amendment and Validation) Act, 2010 for protection of monuments. And J&K Archaeology/Heritage Preservation Act |
| 2 | Ministryof Environment, Forest and Climate Change | Environment Clearance (EC) | As prescribed in the statutory provisions for EIA and clearance based on the size of the project in accordance with Environment Protection Act, 1986 |
| 3 | Central Ground Water Authority through Local BPIA | Bore-well Registration Certificate | As per Guidelines/criteria for evaluation of proposals/requests for Ground Water Abstraction, 2012 |
| 4 | Ministry of Civil Aviation | AAI Height. NOC | Critical and non-critical area as identified by AAI |
| 5 | Ministry of Defence | Defence Clearance | Areas in and around Defence Establishments as identified by MoD. |
| 6 | Ministry of Railways | Area Clearance | Buffer zonesasprescribed by RailwaysalongtheRail tracks/ depots/yards etc. |
3.2 Options for reducing the timelines for approvals :
The above suggested steps are only indicative, however, there is scope for streamlining the procedures for clearances to be obtained from various departments in the least possible number
51
of procedures and number of days. Some of the options which can reduce the time taken for various procedures are:—
a) Online sanctions : ULBs/Development Authorities have introduced online sanction for issuing building plan and completion certificate. The process involves use of software tools for scrutiny of building plans. All the documents are required to be submitted electronically using a portal. In case the building plans do not conform to the DCR the deviations are listed out in form of a report and intimated to the applicant/engaged Competent Professional for building plan design, vide an online ID in his account.
b) Empowering Professionals : Empowering Competent Professionals as prescribed for building plan design will facilitate to streamline the procedure for obtaining approvals. The urban local body or urban local authority or by the Housing and Urban Development of the UT of J&K shall empanel such professionals based on their qualifications and track record. The empowered professionals can, also on behalf of developers/builders submit the documents required at the time of various clearances. This has been comprehensively defined in the Chapter 2.
c) Creating a Cell in ULBs : There is a need for creating a specialized cell in ULBs and UDAs which is manned by qualified personnel conversant with the procedures and the interpretation of development regulations. The cell should be headed by a qualified Town Planner who should inter alia lead a team of Architects, Engineers, Environment Specialist and Legal Experts among others. The cell should have the dedicated provision for online submissions and conveying the online approvals as well. This will require robust software and hardware system capable of handling large digital files.
d) Single Window System : All agencies involved in the process need to be integrated in a single electronic facility with proper coordination and monitoring of timelines. The
[No. 39-4
Municipal Corporation/Council/Committee needs to constitute teams comprising of experts from various agencies to be formed under the overall supervision of a Town Planner designated to assist developers/builders with complex projects and to constantly improve the sanction process by cutting down delays.
e) Integration of agencies outside the ULBs for online clearances : Various agencies like AAI, NMA, SUAC, Fire Services, Department of Industries, Ministry of Defence, etc. grant NOC clearance to the building plans in certain specific cases. This may be streamlined for Ease of Doing Business by following 2 directions as given below:—
i. Building permission for specific areas/sizes are to be examined by the external agencies. These areas should be plotted on GIS based colour-coded map which may be made available in the public domain on the agency’s website, with clearly identified coordinates so that building falling only in these areas need to approach the concerned agencies for obtaining clearances. These maps may also be made available on the website of the concerned municipal bodies.
3.3 Development of an IT enabled team to operate the Building Permission Online :
a) The IT person shall be able to analyse and identify the issues regarding the building permit in the existing system as well as for the system of Single Window Clearance to be adopted in the future.
b) The IT team shall enable a preview selection mode so that the applicants after submitting all the documents can preview it before final submission in the existing online system.
c) The IT team shall also add the total time-frame for clearance at each step in the existing online system dashboard.
d) The IT person shall coordinate with various departments which issues NOCs and shall also identify the total time required in issuing it.
e) Various issues in cross verifying the uploaded documents for e. g. uploading of digital signature, online payments, inspection etc. shall be listed in order to improve the existing online approval system as well as for shifting to the automated building approvals in the future.
f) The physical submission of building permit documents shall be removed by introduction of Pre-DCR software to the applicants.
g) The IT team shall enable online tracking system of NOCs if applicable through the existing online system for the applicants.
h) The IT team shall provide a Pre-DCR formatted software to the consultants (Architects/Engineers/Draftsman etc.) till the time automated building approval system is not introduced.
i) The IT team shall issue an applicant no. through which if an applicant uploads the requisite documents thereafter after verification by the IT team can download the Occupancy Certificate.
3.4 Other Suggestions to enhance Ease of Doing Business :
Some other suggestions, regarding Fast Track construction permits are—
a) Citizens’ Charter :
A Citizens’ charter lists out the timelines and upper limits of time for the delivery of citizen services of the organization.
[No. 39-4
The objective of issuing the charter is to improve the quality of public service in terms of timely delivery. Such charters should be brought out by all municipalities to maintain high standards of accountability and transparency. The standards of service to be provided, the maximum number of days required for building approvals and the standards procedures should be listed out in the citizens’ charter. Some states have gone a step further and introduced a Citizen Service Delivery Guarantee Act whereby the timelines prescribed by a citizen charter are made statutory and binding on officials.
b) Capacity Building :
Capacity building measures are to be adopted for such functionaries to identify Training Needs (TNA) and other technical requirement of duties that they are required to discharge. Fresh recruitments commensurate to the technical qualification/experience are to be made by the UT, if there is complete absence of the technical expertise needed for the said services.
c) Empowered Committees :
The Authorities may also consider constituting ‘Empowered Committees’ or ‘Peer Expert Groups’ for undertaking scrutiny and approval. This committee can be manned as per the requirement and area of more than one municipality can be put under its jurisdiction. This has special significance for tall buildings.
d) Simplification of Bye-laws :
The Building Bye-laws have been simplified for easy comprehension of lay person as well as professionals involved in developmental activities. The simplification process should also include the process of application, the filling up of forms and streamlining the process of application.