(1) The Ministry of Environment, Forest and Climate Change has decided to integrate the environmental concerns into building plan approval process and empowering the concerned ULB/Development Authority/any other body authorized to sanction building plans, to approve and certify compliance of stipulated requirements.
(2) The new building construction proposals are classified in the following 3 categories:-
| Category | Built Up Area (sq. m) |
|---|---|
| A | 5000 - 20000 |
| B | 20000 - 50000 |
| C | 50000 - 150000 |
(3) The ULB/Development Authority/any other body authorized to sanction building plans shall approve the building plans by ensuring the stipulated conditions in
Table 37 (for above 5,000 sq. m and up to 20,000 sq. m),
Table 38 (for above 20,000 sq. m and up to 50,000 sq. m) and
Table 39 (for above 50,000 sq. m and up to 1,50,000 sq. m).
Environmental Conditions for Building and Construction (Category “A”: 5000 sq. m - 20000 sq. m)
TABLE – 37
| S. No. | Medium | Environmental Condition | Reference Clause |
|---|---|---|---|
| (A) | (B) | (C) | (D) |
| 1 | Natural Drainage | The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water. | |
| 2 | Water Conservations-Rain Water Harvesting and Ground Water Recharge | (a) A rain water harvesting plan needs to be designed where the recharge bores (minimum one per 5000 sq. m of built-up area) shall be provided. (b) The rain water harvested should be stored in a tank for reuse in household through a provision of separate water tank and pipeline to avoid mixing with potable municipal water supply. (c) The excess rain water harvested be linked to the tube well bore in the premise through a pipeline after filtration in the installed filters. | See Chapter on Rain Water Harvesting Structures and Table - 35 Provisions for Rainwater Harvesting by Building Types |
| 2(a) | The unpaved area shall be more than or equal to 20% of the recreational open spaces. | 142. Provisions for City and Site level greening: (1) Greening (d) The unpaved area shall be more than or equal to 20% of the recreational open spaces. | |
| 3 | Solid Waste Management | Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste. | 143. Sustainable Waste Management: (4) (b) Separate wet and dry bins must be provided at the ground level. |
| 4 | Energy | In common areas, LED/ solar lights must be provided. | 141. Provisions for Sanction of Building Application: (3) (c) Lighting of common areas by Solar Energy/LED devices. |
| 5 | Air Quality and Noise | Dust, smoke and debris prevention measures such as screens, barricading shall be installed at the site during construction. Plastic/ tarpaulin sheet covers must be used for trucks bringing in sand and material at the site. | |
| 5(a) | The exhaust pipe of the DG set, if installed, must be minimum 10m away from the building. In case it is less than 10m away, the exhaust pipe shall be taken up to 3m above the building. | ||
| 6 | Green Cover | A minimum of 1 tree for every 80 sq. m of land shall be planted and maintained. The existing trees will be counted for this purpose. Preference should be given to planting native species. | 142. Provisions for City and Site level greening (1) Greening (a) Provision of minimum 1 tree/every 80sqmt of plot area for plot sizes >100sqmt and planted within the setback of the plot. |
| 6(a) | Where the trees need to be cut, compensatory plantation in the ratio of 1:3 (i.e. planting of 3 trees for every 1 tree that is cut) shall be done with the obligation to provide continued maintenance for such plantations. | 142. Provisions for City and Site level greening (1) Greening (b) Compensatory Plantation for felled/transplanted tress in the ratio 1:3 within the premises under consideration |
Environmental Conditions for Building and Construction (Category “B”: 20000 sq. m - 50000 sq. m)
TABLE - 38
| S. No. | Medium | Environmental Condition | Reference Clause |
|---|---|---|---|
| (A) | (B) | (C) | (D) |
| 1 | Natural Drainage | The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water. | --- |
| 2 | Water Conservations-Rain Water Harvesting and Ground water Recharge | A rain water harvesting plan needs to be designed where the recharge bores (minimum one per 5000 sq. m of built-up area) shall be provided. The rain water harvested should be stored in a tank for reuse in household through a provision of separate water tank and pipeline to avoid mixing with potable municipal water supply. The excess rain water harvested be linked to the tube well bore in the premise through a pipeline after filtration in the installed filters. | See Chapter on Rain Water Harvesting Structures and Table - 35 Provisions for Rainwater Harvesting by Building Types |
| 2(a) | The unpaved area shall be more than or equal to 20% of the recreational open spaces. | 142. Provisions for City and Site level greening: (1) Greening (d) The unpaved area shall be more than or equal to 20% of the recreational open spaces. | |
| 3 | Solid Waste Management | Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste. | 143. Sustainable Waste Management: (4) (b) Separate wet and dry bins must be provided at the ground level. |
| 4 | Energy | In common areas, LED/ solar lights must be provided. | 141. Provisions for Sanction of Building Application: (3) (c) Lighting of common areas by Solar Energy/LED devices. |
| 4(a) | At least 1% of connected applied load generated from renewable energy source such as photovoltaic cells or wind mills or hybrid should be provided. | 141. Provisions for Sanction of Building Application (2) Solar Energy Utilization (a) Installation of Solar Photovoltaic Panels. | |
| 4(b) | As per the provisions of the Ministry of New and Renewable energy solar water heater of minimum capacity 10 litres/4 persons (2.5 litres per capita) shall be installed. | 159. Guidelines for installation of Solar Water Heating Systems (2) The recommended minimum capacity shall not be less than 25litres per day for each bathroom and kitchen subject to the condition that maximum of 50% of the total roof area is provided with the system. | |
| 4(c) | Use of flyash bricks: Fly ash should be used as building material in the construction as per the provisions of Fly Ash Notification of September, 1999 and as amended from time to time |
TABLE - 39 Environmental Conditions for Building and Construction (Category “C”: 50000 sq. m - 150000 sq. m)
| S. No. | Medium | Environmental Condition | Reference Clause |
|---|---|---|---|
| (A) | (B) | (C) | (D) |
| 1 | Natural Drainage | The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water. | --- |
| 2 | Water Conservations-Rain Water Harvesting and Ground water Recharge | A rain water harvesting plan needs to be designed where the recharge bores (minimum one per 5000 sq. m of built-up area) shall be provided. The rain water harvested should be stored in a tank for reuse in household through a provision of separate water tank and pipeline to avoid mixing with potable municipal water supply. The excess rain water harvested be linked to the tube well bore in the premise through a pipeline after filtration in the installed filters. | See Chapter on Rain Water Harvesting Structures and Table - 35 Provisions for Rainwater Harvesting by Building Types |
| 2 (a) | The unpaved area shall be more than or equal to 20% of the recreational open spaces. | 142. Provisions for City and Site level greening: (1) Greening (d) The unpaved area shall be more than or equal to 20% of the recreational open spaces. | |
| 2 (b) | The ground water shall not be withdrawn without approval from the competent authority. | --- | |
| 2 (c) | Use of potable water in construction should be minimized. | --- | |
| 2 (d) | Low flow fixtures and sensors must be used to promote water conservation. | --- | |
| 2 (e) | Separation of grey and black water should be done by the use of dual plumbing system. | --- | |
| 3 | Solid Waste Management | Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste. | 143. Sustainable Waste Management: (4) (b) Separate wet and dry bins must be provided at the ground level. |
| 3(a) | All non-degradable waste shall be handed over to authorized recyclers for which a written tie-up must be done with the authorized recyclers. | --- | |
| 3(b) | Organic waste composter/ vermiculture pit with a minimum capacity of 0.3 Kg/tenement/day must be installed wherein the STP sludge may be used to be converted to manure which could be used at the site or handed over to authorized recyclers for which a written tie-up must be done with the authorized recyclers. | --- | |
| 4 | Energy | In common areas, LED/ solar lights must be provided. |