(a) The construction shall be commenced within 18 months from the date of sanction.
(b) The sanction accorded is valid for 6 years in case of High Rise Buildings, Multiplex and Group Development Schemes and 3 years in case of Non High Rise Buildings from the date of sanction.
(c) The permit shall be got revalidated before the expiry of this period. The revalidation shall be considered in case of projects commence within stipulated period. Where construction has not commenced the revalidation shall be subject to rules in force.
(d) The Building Permit Fee shall be paid for revalidation of the permit.
(e) No building activity can be carried out after the expiry of validity of such building permit.
(f) No completion/occupancy shall be entertained after the expiry of valid extension of time for construction.