i) The above permissions for development of reservations shall be granted by the Municipal Commissioner as per the norms mentioned in these regulations. Such permission may be granted by the Municipal Commissioner where the land is not actually put to acquisition under The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 or proposal to that effect is not under process.
ii) If the area of reservation is not adequate to construct independent building as mentioned above OR When it is not possible to handover individual plot along with public amenity, then in such cases Municipal Commissioner may allow composite building on said land subject to condition that the built up area mentioned as above may be allowed to be handed over to the Planning Authority or Appropriate Authority, as the case may be, preferably on ground floor and subject to premium as may be decided by Government from time to time. If ground floor is utilised for parking, then on stilt/first floor with separate entry & exit from public street. In such cases, built-up area along with proportionate undivided share of land shall be handed over to the Planning Authority or Appropriate Authority, as the case may be. In such cases no compensation of proportionate undivided land share shall be permissible.
iii) In cases where not specifically mentioned in this regulation, if the area under the reservation is owned by more than one owners, then the owner/s may come forward jointly or the owners holding atleast 50% or more area shall be allowed to develop the reservation on such land. It is mandatory for other owners to construct amenity contiguous to the earlier development.
iv) The owner/developer shall be entitled for construction amenity TDR as per the TDR regulations after handing over the constructed amenity free of cost on the land surrendered to the planning Authority under this Regulation. For specific reservation where construction amenity is not required by the Commissioner, in such cases Municipal Commissioner should not insist for such amenity.
v) It shall be obligatory on Planning Authority to make registered agreement with the developer /owner at the time of granting the development permission subject to terms and conditions as it deem fit. Occupancy Certificate shall be issued only after compliance of all terms & conditions and getting possession of the constructed amenity.
vi) The above permissions for development of reservations shall be granted by the Municipal Commissioner as per the norms mentioned in these regulations
vii) The area / built-up area to be handed over to the Planning Authority under these Regulations shall be earmarked on the sanctioned building plan clearly mentioning the same, and registered agreement to that effect shall be executed. After completion of construction, the said amenity shall be handed over by executing the deed of transfer in this respect and expenses thereon shall be borne by the owner. The occupation certificate to the construction belonging to owner shall be granted only after handing over said amenity to the Planning Authority. The constructed amenity shall be made available to the general public by the Municipal Commissioner within 3 month from possession as per the condition as Commissioner deem fit.
viii) In cases, where permission for development under accommodation reservation principle is already granted as per earlier regulations, the same shall continue to be valid till completion of construction.
ix) Provisions of Regulations of Inclusive Housing, Amenity Space if any, shall not be applicable for development under this Regulation. Moreover Regulation of required recreational open space shall not be applicable for development of reservation other than Residential purpose as
mention at sr. no.7.
x) Not withstanding anything contained in these regulations, there shall be no cap for utilization of available in-situ FSI/and TDR potential of the entire plot on the remaining plot provided that no relaxation in side margin shall be permissible.
xi) Once sanction is granted under this regulation, the owner /developer shall have to complete the development and hand over the developed reservation to Planning Authority within the period as specified by Municipal Commissioner. Thereafter Planning Authority may levy penalty for any delay.