6.1 Risk based classification of building applications
There is a need to make provisions for fast-tracking building permission
procedures for all non-automatic approvals. Therefore, in the spirit of 'Ease of Doing Business', the buildings have been classified further on the basis of risk parameters/risk-based classification to clear the building permits on fast-track system. This kind of classification shall be used for fast tracking the sanction of building plans, which shall facilitate regulated and faster construction permits, and also aid in improving the rating of the country in World Bank's assessment in 'Ease of Doing Business'. Further, the ULB in consultation with all parastatal bodies involved, shall identify risk-based classification of industrial, commercial, and institutional buildings, and prepare risk-based matrix, in-line with those proposed in Model Building Bye Laws, 2016 for residential and storage buildings/ warehouses/ godown and accordingly prescribe the fast-tracking approval system. This exercise shall be done within a period of 3 months from the date of publication of the Local Building Bye-laws.
On the basis of above-mentioned risk matrix prepared by each of the agencies involved in approving building plans, UT Administration shall design and notify necessary legal instructions to implement risk-based mechanism with a view to fast track building permissions based on their risk classification. These instruments may include, but are not limited to, delegation of powers, out-sourcing, empowering architects/civil engineers/structural engineers, self-certifications, etc. These notifications shall be done within 3 months from the date of notification of risk matrix by each competent authority / agency as mentioned above.
For approval of the residential plotted and group housing buildings, risk-based classification:
(1) For fast-track building plan approval, the competent authority shall approve building plans considering the risk-based classification of buildings depending upon the respective risk matrices as mentioned in Sub Para 6.1 (1) - 6.1 (3)
(2) The application for approval and grant of Occupation Certificate of very-low to moderate risk buildings shall be allowed as per Sub Para 4.2 and relevant sections of Chapter-5. The application for approval and grant of Occupation Certificate of high-risk buildings shall be allowed as per Sub Para 4.1 and relevant sections of Chapter-5.
(3) For building plan approval, the competent authority shall approve building plans considering the risk-based classification of buildings
depending upon height and area. The buildings are categorized in the following categories:
i. Residential Buildings:
| Risks | Very Low | Low | Moderate | High | |
|---|---|---|---|---|---|
| Criteria | Parameters | ||||
| Size of the plot | Square Meters | Below 105 m2 | 105 – 500 m2 | Above 500 m2 | All sizes |
| Height of the building | Meters | <15 m | <15 m | <15 m | 15 m or above |
| Use of the premises | Various categories | Residential plotted | Residential plotted | Residential plotted | Group Housing |
A. Considering no other issue like Monuments, Metro, Airports etc. are involved. In case the property lies within the regulated zone of metro rail, airport etc. the online clearance from the local body concerned shall be taken
B. Group Housing area is minimum 2000 sq mt (may vary between States)
C. The Competent Authority shall empanel professionals as necessary
D. The Competent Authority shall work out and prescribe fees for submitting the building plans
E. The fees shall be derived by an automated built-in calculator in the online system of submission
Suggested Fast Tracking Tools:
For Very Low Risk Buildings:
In case of standard building plans prepared by the Authority for residential plots up to 105 sq.mt. in size and forming part of the approved layout plan, the owner shall be entitled to sign such standard plans and the required documents for submission for sanction. In such cases, certificate from professionals would not be necessary and the owner shall be bound to follow the approved standard plan in detail. The Authority shall explore options of EWS/LIG/MIG plotted housing schemes to develop pre-approved Standardized building plans of Housing Units for variable plots sizes/carpet area (in the range 30sqm-105sqm). The owner shall undertake construction of the so formed standard housing units.
For Low-Risk Buildings:
A Competent professional (qualification & competence as per Annexure-D) shall be empowered to issue the building permit, but only after submitting the plan along with requisite documents and fees to the concerned local body. If the owner/professional desires to get the building plan sanctioned by the local body, building plans prepared by the qualified competent professional will have to be submitted to the concerned local body along with the fees and other requisite documents and the local body shall grant the building permit within 07 days.
For Moderate-risk Buildings:
Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 10 days.
For High-risk Buildings:
Clearances and NOCs from department, or authority as appointed by UT Administration, and other necessary clearances from AAI, NMA and other
agencies as per Section 5.10 and other authorities as deemed necessary by the UT Administration have to be obtained. Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
ii. Storage/Warehouse Buildings
For approval of the buildings meant for use as storage buildings/warehouses/godown, risk-based classification shall be in the following categories:
| Risks | Very Low | Low | Moderate | High |
|---|---|---|---|---|
| Covered area on all floors / Built-up Area | Up to 250 m² | 250 – 2000 m² | Up to 2000 m² | Above 2000 m² |
| Height of the building | <15 m | <15 m | <15 m | <15 m |
| Abutting Road width | Min. 12 m | Min. 12 m | Min. 12 m | Min. 12 m |
| Type of Material Storage | Category A | Category A | Category B (Stacking Height – Medium) | Category B (Stacking Height – Medium) |
Note:
A. The level of Risk is classified according to the material stored in the warehouse/storehouse. Material shall be classified according to the Categories defined in Annexure "C".
B. The Urban Local Body/ Urban Development Authority shall empanel professionals as per "Annexure D".
C. The building application processing fees shall be derived by an automated built-in calculator in the online system.
Suggested modes of Fast Tracking:
For Very Low Risk Buildings:
A competent professional (qualification & competence as per Annexure-D) shall be empowered to issue the building permit, but only after submitting the plan along with requisite documents and fees to the concerned local body. If the owner/professional desires to get the building plan sanctioned by the local body, s/he shall apply online to the local body and the local body shall grant the building permit within 07 days.
For Low-Risk Buildings:
Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 10 days.
For Moderate Risk Buildings:
Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
For High-Risk Buildings:
Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 30 days.
iii. Industrial Buildings
For approval of the buildings meant for use as storage buildings/ warehouses/godowns, risk-based classification
| Risks | Low | Moderate | High | |
|---|---|---|---|---|
| Criteria | Parameters | |||
| Size of the plot | Square Meter | Up to 350 m2 | Above 350 m2 | All sizes |
| Height of the building | Meters | Less than 15 m | Less than 15 m | 15 m and above |
| Abutting Road width | Meters | Min. 12 m | Min. 12 m | Min. 12 m |
A. The level of Risk is classified according to the size and height of the industrial building proposed.
B. The Urban Local Body/ Urban Development Authority shall empanel professionals as per "Annexure D".
C. The building application processing fees shall be derived by an automated built-in calculator in the online system.
Suggested modes of Fast Tracking:
For Low-Risk Buildings:
-
Deemed Approval with Self-Certification
-
Plans to be submitted along with Structural drawings which does not require sanction
For Moderate-Risk Buildings:
-
Plans to be submitted to the empaneled professional.
-
Clearances and NOCs from department, or authority as per Section 5.10
-
Approval to be granted within 10 working days by the empaneled professional.
-
Approved plan to be submitted to ULB/DA.
For High-Risk Buildings:
-
Online application
-
Immediate acknowledgement by software
-
Clearances and NOCs from department, or authority as per Section 5.10
-
Approval by ULB/DA within 20 working days
iv. Commercial Buildings
For approval of the buildings meant for use as commercial, risk-based classification.
| Risks | Very Low | Low | Moderate | High |
|---|---|---|---|---|
| Built-up Area/Covered Area of building | Up to 250 m2 | 250 – 1000 m2 | 1000– 5000 m2 | Above 5000 m2 |
| Height of Building | < 9 m | >9 m and < 15 m | < 15 m | 15 m and above |
| Abutting Road Width | Minimum 3.5 m | Minimum 6 m | Minimum 9 m | Minimum 12 m |
| Type of Activity | Shops, small offices, clinics | Small retail, restaurants, banks | Shopping complexes, multiplexes, hotels | Malls, IT parks, convention centers, large hotels |
Notes:
A. Risk classification is based on intensity of use, built-up area, and height. C. Fees for building applications shall be auto-calculated in the online system. D. Special clearances may be required if building use involves public assembly, hazardous activities, or falls near regulated zones.
Suggested Modes of Fast-Tracking:
• Very Low Risk Buildings
Competent professional may issue building permit after submission online. Local body, if approached, shall grant approval within 7 days.
• Low Risk Buildings
Plans prepared by competent professional; submission to ULB with documents and fees; approval within 10 days.
• Moderate Risk Buildings
Plans submitted by competent professional, along with necessary clearances (fire, traffic impact, parking norms). ULB approval within 15 days.
• High Risk Buildings
Online application, automatic acknowledgement. Clearances from departments/authorities as per Section 5.10 (AAI, Fire, NMA, etc.) required. ULB to grant approval within 30 days.
v. Mixed Land Use Buildings
For approval of the buildings meant for use as Mixed land use building, risk based classification.
| Risks | Very Low | Low | Moderate | High |
|---|---|---|---|---|
| Built-up Area | Up to 300 m2(residential + small commercial at ground floor) | 300 – 1000 m2 | 1000 – 3000 m2 | Above 3000 m2 |
| Height of Building | < 9 m | >9 m and < 15 m | < 15 m | 15 m and above |
| Road Width | Minimum 9 m | Minimum 9 m | Minimum 12 m | Minimum 12 m |
| Type of Use | Residential with <25% commercial (shops/offices) | Mixed-use with ≤ 33% commercial component | Mixed-use with ≤ 50% commercial component | Mixed-use with > 50% commercial or public assembly use |
Notes:
A. Once the masterplan is notified, all Mixed use shall be permitted as per zoning regulations of Master Plan.
C. Fire safety and structural safety clearances mandatory beyond 1000 m².
Suggested Modes of Fast-Tracking:
• Very Low Risk Buildings
Deemed approval with self-certification by competent professional. ULB to verify compliance within 7 days.
• Low Risk Buildings
Plans prepared by competent professional; submission to ULB; permit to be issued within 10 days.
• Moderate Risk Buildings
Building plans with traffic and parking compliance; clearances from Fire/other concerned departments. ULB approval within 20 days.
• High Risk Buildings
Online application, immediate acknowledgement. Clearances (fire, traffic impact, environment, AAI/NMA if applicable) required. ULB approval within 30 days.