(1) Every person who intends to occupy a building or part thereof for which the building plan(s) has been sanctioned shall apply for the occupation certificate in Form BC-IV(A) or BC-IV(B), accompanied by certificates in relevant Form BC-V (1) or BC-V (2) duly signed by the architect and/or the engineer along with following documents:
(i) details of sanctionable violations from the approved building plan(s), if any in the building, jointly signed by the owner, architect, structural engineer and/or civil engineer as the case may be,
(ii) completion drawings or as-built drawings along with completion certificate from architect/ structural engineer and/or civil engineer as per Form BC-VI,
(iii) photographs of front, side, rear setbacks, front, and rear elevations of the building shall be submitted along with photographs of essential areas like cut outs and shafts from the roof top. An un-editable compact disc/ DVD/ any other electronic media containing all photographs shall also be submitted,
(IV) Permit checklist needs to be followed and permit certificate from Bureau of Energy Efficiency (BEE) Certified Energy Auditor for installation of Rooftop Solar Photo Voltaic Power Plant shall be required in accordance with orders/policies issued by the Renewable Energy Department from time to time, if applicable
(v) Construction permits and Occupancy Certificate from Bureau of Energy Efficiency (BEE) Certified Energy Auditor for constructing building in accordance with the provision of ECBC, wherever applicable
(vi) No Objection Certificate (NOC) of fire safety of building from concerned Fire Officer or an officer authorized by UT Administration for this purpose wherever applicable.
(vii) All provisions of Ladakh Energy Conservation Building Code 2021 (once notified)
Note: Online portal for auto-scrutiny shall always require upload of the recommended digital format of the drawings to be uploaded on the portal for use
(2) No owner/applicant shall occupy or allow any other person to occupy a new building(s) or part thereof until such building or part thereof has been certified by the competent authority or by any officer authorized by it in this behalf as having been completed in accordance with the permission granted and an ‘Occupation Certificate’ has been issued in Form BC-VII. However, competent authority shall charge composition charges for compoundable violations before issuance of Form BC-VII. Further, the water, sewer and regular electricity connection shall be released only after issuance of occupation certificate by the competent authority. The ‘Occupation Certificate’ to be issued shall on the basis of parameters mentioned as under:
i. minimum 25% of total permissible ground coverage, excluding ancillary zones, if any, shall be essential for issuance of occupation certificate, other than residential and industrial buildings,
ii. in the case of residential plot, a minimum 50% of the total permissible ground coverage to be constructed with minimum one habitable room, a kitchen and a toilet forming a part of submitted or the approved building plan shall be completed,
iii. debris and rubbish consequent upon the construction has been cleared from the site and its surroundings,
iv. after receipt of application, the Competent Authority shall communicate in writing/ online within five (05) days, his decision for grant or refusal of such permission for occupation of the building in Form BC-VII. The E-register shall be maintained as specified in sub para -5.8 for maintaining record in respect of Occupation Certificate, if no communication is received from the Competent Authority within five (05) days of submitting the application for “Occupation Certificate”, the owner is deemed permitted to occupy building, considering “Occupation certificate” deemed issued and the application Form BC-IV (A) or BC-IV(B) shall be the “Occupation Certificates”. However, the competent authority may check the
violations made by the owner and take suitable action with regard to the violations, and,
v. if the owner or the architect or structural engineer or civil engineer or Consultant as mentioned in sub para 4.2 and 4.10 as the case may be, submits a wrong report while making application under these Bye-Laws or if any additional construction or violation is reported to exist at site or has concealed any fact or mis-represented regarding completion of construction of building along with essential conditions of seeking occupation certificate, s/he shall be jointly and severally held responsible for such omission/commission and complaint against the architect/structural engineer/civil engineer for suspension of his registration/membership, and/or other necessary penal actions may be taken, and the owner shall be liable to pay for the penalty as may be decided by the competent authority after giving an opportunity of being heard. I it emerges during the hearing that the relevant information was concealed by architect/structural engineer/civil engineer/consultant, necessary penal proceedings of barring architect/structural engineer/civil engineer /consultant from practicing in the Union Territory of Ladakh may be enforced.