4.1 Application for erection or re-erection of building
(a) Any person who intends to erect, re-erect, or make alternation in a
building or demolish any building shall give notice in writing to the competent authority in the Form BC-I, accompanied by the following documents:
Other documents to be submitted in special cases shall be as follows:
i. Property Ownership Document / Proof of Title (Sale deed/Lease deed/Allotment order/Mutation certificate, etc.).
ii. Site Plan (location, access roads, surroundings).
iii. Building plan/dimension/drawings/design with front, and rear elevations as per bye-laws.
iv. Structural Stability Certificate (wherever applicable).
Further a declaration to be submitted by the Applicant Owner in the format prescribed at Annexure-E
Any additional documents required by the Competent Authority from time to time.
i. For projects proposed within the Prohibited and Regulated areas as defined by AMASR Act 2010, permission /NOC from Competent Authority (NMA) shall have to be obtained as per Rules 2011 framed under the Act by submission of required documents as per rules.
ii. Additional documents required for conservation of Heritage sites including Heritage Buildings, Heritage/Precincts and Natural Features Areas (wherever required)
Note: The applicant shall submit all kinds of plans in electronic format of online portal of the competent authority. The competent authority shall convey objections/observations or sanction/refusal through online portal and or other prescribed mode.
(b) Every person applying under sub para 4.1 may appoint an architect/civil engineer/structural engineer for drawing up of building plans/structural drawings and for the supervision of erection or re-erection of the building.
(c) The supervision of erection or re-erection of residential or commercial buildings up to 9 meters height (G+2 floors including stilt floor) may be carried out by the architect or the engineer but is not mandated. In case of buildings exceeding 9 meters in height, including stilt floor, the
supervision shall be undertaken both by the architect and the engineer (civil or structural). In case of buildings in notified heritage zone, ecologically-conservation zone, special protection zones, or as mentioned in Development Control Regulations and Master Plan, as well as for plots facing arterial, sub-arterial and collector roads, registered architects need to approve designs, undertake feasibility study, and provide inputs regarding specific design interventions, and approval.
(d) During construction, if appointed architect/engineer observes any on going violation(s), except compoundable, are continuing shall intimate the owner and advise him to stop further construction and rectify the violations and shall also intimate to the concerned authority.
(e) The applicant, the registered architect and engineer shall digitally sign the application, plans, structural drawings, specifications, and the certificates as required in the relevant forms and documents, before making submission to the Competent Authority.
(f) In case the building application is returned, it may be re-submitted within Sixty (60) days from the date of such return without fresh scrutiny fee. Such re-submission, however, may not be allowed more than two times in Sixty (60) days from the date of first return.