6.0 Occupancy Certificate/Building Use Permission
6.1 Occupancy Certificate Required
It is mandatory to obtain an Occupancy Certificate (also called Building Use Permission) from the Competent Authority (Authority I) prior to occupancy or use being made of any development or part of a development. In case occupancy is sought for a part of the development then it will also have to be sought when the development is completed.
6.2 Grant of Occupancy Certificate
Grant of Occupancy Certificate by the Competent Authority (Authority I) shall mean an acceptanceby the Competent Authority that the development has conformed to the sanctioned design and specifications and that the Owner may use the development in conformitywith the Sanctioned Use of the development.
Issue or grant of anOccupancy Certificate does not constitute acceptance of correctness, confirmation, approval, orendorsement of and shall not bind or render the Competent Authority liable in any way inregard to:
1 Title, ownership, and easement rights of the plot on which development / building is proposed.
2 Workmanship, soundness of material and structural safety of the development / building.
3 Variation in area from recorded areas of a buildingunit.
4 Location and boundary of buildingunit.
5 Safety of the users of the building.
6 NOC from Appropriate Authority.
7 Structural reports and structural drawings.
6.3 Cancellation of Occupancy Certificate
Cancellation of anOccupancy Certificate shall mean that the Occupancy Certificate is no longer valid and that the Competent Authority (Authority I) has withdrawn the permission granted to make use of thedevelopment. Occupancy Certificate may be revoked for part of a development.
2 Occupancy Certificate can be revoked if there is a major change in occupancy and no change of occupancy is sought as per Rule 6.6.
3 After Cancellation of Occupancy Certificate, use may no longer be made of the whole of or part of the development for which the Occupancy Certificate has been suspended.
4 Notice of Cancellation of anOccupancy Certificate shall be issued by Competent Authority (Authority I) in writing, in the format specified in Form No. 24.
6.4 Unauthorized Use/ Occupancy of Building / Development
1 Use of any building or part of a building, without a building use permission or in a manner that does not conform with its permission granted or after issue of building use permission has been revoked, shall be deemed to be unauthorized use of building.
Also, the Competent Authority (Authority I) may declare the use of any building to be an unauthorized use if it deems the building to be unsafe for habitation or if its use poses a danger to public health or safety.
6.5 Obtaining anOccupancy Certificate
6.5.1 Application
1 The Owner and the Architect / Engineer on Record for the building shall be responsible for notifying the Competent Authority (Authority I) of completion of construction, for certifying
Page No 57
that the construction complies with the sanctioned design & specifications and applying for grant of OccupancyCertificate.
2 Notice of Completion of Construction and Compliance Certification shall be made in the format prescribed in Form No. 21.
3 Application for Occupancy Certificate may be made to the Competent Authority (Authority I) in the format stipulated in Form No. 22A and Form No. 22B and shall be accompanied by documents and drawings as prescribed by the Competent Authority in Schedule No. 8. The format for submission of drawings, specifications and documents is specified in Schedule No.5B.
4 Application for Part Occupancymay be made to the Competent Authority (Authority I) in the format stipulated in Form No. 22A and shall be accompanied by documents and drawings as prescribed by the Competent Authority in Schedule No. 8. The format for submission of drawings, specifications and documents is specified in Schedule No. 5B.
5 Upon the request of the building permit owner/developer, the Authority has the discretion to issue a part occupancy certificate for a building or a specific portion thereof, even before the completion of the entire project as specified in the building permit. This issuance, however, is contingent upon the owner/ developer implementing adequate precautionary measures to guarantee the provision of essential infrastructure facilities, public safety, and health standards.
6.5.2 Fees and Charges
All fees and charges for obtaining Occupancy Certificate are listed in Schedule No. 4B.
The fees and charges shall be determined by the Competent Authority from time to time.
6.5.3 Final Inspection and Grant / Refusal of Occupancy Certificate
The Competent Authority (Authority I) on receipt of Notice of Completion of Construction and a duly completed application for Occupancy Certificate, shall verify its compliance to the sanctioned design and specifications within 21 days from the date of receipt of the application.
Upon receipt of the Notice of Completion of Construction and Compliance Certification, the Competent Authority (Authority I) shall forward the same to Authority-II. Authority-II shall, in turn, transmit the documents to Authority-IV and Authority-V for technical verification and inspection of the constructed building. Upon completion of verification, a joint report shall be submitted by Authority-IV and Authority-V to Authority-II. Subsequently, Authority-II shall forward the compiled report to the Competent Authority (Authority I).
If the construction is found not complying with sanctioned design and specifications, the Competent Authority (Authority I) shall communicate queries regarding the construction and/or directions to ensure compliance to the Owner and the Architect on Record or Engineer on Record. Failure to comply with directions, as may be issued by the Competent Authority, may result in cancellationof the Occupancy Certificate. The Architect on Record or Engineer on Record shall respond to queries and notify the Competent Authority of having undertaken compliant modifications.
6.6 Permission to Change Sanctioned Occupancy / Use of Development
6.6.1 Application
1 No building or premises shall be changed or converted to a use other than the sanctioned use without prior permission of the Competent Authority (Authority I) in writing. Change of use not in conformity with these Rules shall not be permissible.
2 Application for obtaining Permission to change sanctioned use of building shall be made by the owner, for which a change in use is proposed and the Persons on Record, in the format prescribed in Form No. 25 Drawings, specifications, and documents to be submitted along with the application shall be as is specified in Schedule No. 5B.
6.6.2 Fees
All fees and charges for obtaining Permission to Change Sanctioned Use of Building are listed in Schedule No. 4A.
The fees and charges shall be determined by the Competent Authority from time to time.
6.6.3 Scrutiny of Application, Grant, Refusal
The Competent Authority shall undertake scrutiny of the Application for Permit to ChangeSanctioned Occupancy of Development and communicate to the applicant the date and time forplot inspection, if required, within 15 working days of the date of acceptance of the application.
Upon receipt of the Application for Permit to Change Sanctioned Occupancy of Development, the Competent Authority (Authority I) shall forward the same to Authority-II. Authority-II shall, in turn, transmit the documents to Authority-IV and Authority-V for technical verification and inspection of the constructed building. Upon completion of verification, a joint report shall be submitted by Authority-IV and Authority-V to Authority-II. Subsequently, Authority-II shall forward the compiled report to the Competent Authority (Authority I).
2 Lack of compliance with Rules and/or queries pertaining to the application shall becommunicated in the format prescribed in Form No. 23 within 21 working days of thedate of acceptance of the application.
3 Acceptance or rejection of compliant modifications in the application and responses toqueries shall be communicated in the format prescribed in Form No. 23within 10working days of receipt of the modifications and responses. Acceptance or rejection offurther compliant modifications in the application and responses to queries shall also be.
4 A Permit to Change Sanctioned Occupancy of Development, in the format prescribed in FormNo. 25 shall be issued to the applicant when the Competent Authority (Authority I) is satisfied that the proposed change of Occupancy of the development complies with these Bye-Laws. Reasonsfor rejection of application shall be communicated in the format prescribed in Form No.25.
6.6.4 Penalties
Any development undertaken shall be in conformity of these Bye-laws. Financial penalty, for different conditions of occupancy, shall be levied as prescribed in Schedule No. 4D for unauthorised use of development.