All POR have to jointly certify Technical Audit Report as per Schedule No. 3 for all type of non-residential buildings.
3.3.1 Responsibilities of all POR
The overall responsibilities of all POR shall be as follows:
1 They shall prepare the plan of the buildings/ layout in accordance with the provisions of these Bye-laws in such a manner that they are compatible and accessible to the persons who will reside therein.
2 They shall inform the Competent Authority (Authority-I) of their resignation from any work within7 days of the date of such resignation.
3 They shall prepare and submit all plans, new or revised as applicable, documents and other details as required, in a neat, clean, and legible manner and on a durable paper properly arranged and folded in accordance with the prevailing Rules along with the soft copy of the same.
4 They shall submit plans, documents and details without any scratches or corrections. Only small corrections will be permitted with proper initials. They shall correctly represent all the site conditions including mature trees.
5 They shall personally comply with all requisitions / queries received from the Competent Authority in connection with the work under their charge, promptly expeditiously and at one time. Where they do not agree with requisitions/queries, they shall state objections in writing, otherwise for non‐compliance of any requisition / query within stipulated time, the plans and applications shall be filed forthwith, and shall not be re‐opened. In case the owner or developer is not cooperating in compliance of the points raised by the authority, an intimation to Authority-I within 15 days of this non-cooperation by PORs to this effect shall be considered a sufficient reason and accordingly the application shall be rejected.
6 They shall immediately intimate to the owners the corrections and other changes they make on the plans, documents, and details as per requisitions/queries from the Competent Authority.
7 They shall clearly indicate on every plan, document & submission, the details of their designation such as registered AOR, CEOR, SEOR, & with registration number, date, full name, and their address below the signature for identification.
8 They or their authorised agent or employee, shall not accept the employment for preparation and submission of plans‐documents and supervision of any work if the same is intended or proposed to be or being executed or already executed in contravention of these Bye-Laws or any Rules.
9 Approval of drawings and acceptance of any statements, documents, structural reports, structural drawings, progress certificates, or building completion certificates shall not absolve the owner, engineer, architect, structural designer, developer, or owner from the responsibilities imposed under these Bye-Laws.
Specific responsibilities shall be follows:
3.3.2 Architect on Record (abbreviated as AOR)
The Architect on Record shall:
1 Be the Person on Record responsible for ensuring compliance with all procedural requirements specified in these Bye-Laws.
2 Scrutinize and verify the architectural design and specifications of the proposed building.
3 Certify that the architectural design and specification of the proposed building comply with these Bye-Laws using the format prescribed in Form No. 2.
4 Immediately inform the Competent Authority (Authority-I) in writing, if in his/her opinion, the construction of the building is not being undertaken in accordance with the sanctioned design requirement in a format as per Form No. 3.
5 Inform the Competent Authority (Authority-I) in writing, within 7 working days, if for any reason he/she is relieved of his/her responsibilities or he/she relieves himself of responsibility as
Page No 39
the Architect on Record for the building using the format prescribed in Form No. 4. In case of termination of services as Architect on Record, inform the Competent Authorities (Authority-I ) about the stage of work at which services are terminated. The registered architect appointed as of the preceding architect shall inform within 7 days about his/her appointment on the job and inform the Competent Authority (Authority-I ) of any deviation that might have occurred on the site with reference to the approved drawings and the stage at which he/she is taking over the charge. After Competent Authority has inspected the site for his/her report, the newly appointed architect shall allow the work to proceed under his/her direction.
6 On behalf of the owner, submit the progress certificates, completion certificates and obtain the Occupancy Certificate as required under these Bye-Laws.
7 Inform the Competent Authority (Authority-I) immediately on termination of the services of the SEOR.
8 Instruct the relevant agency that adequate provisions are made for ensuring the safety of workers and others during excavation, construction, and erection.
9 Instruct the relevant agency that adequate provisions are made for providing safe and adequate temporary structures required for construction and development.
- Undertake all necessary measures, including but not limited to, adequate inspection during construction to ensure that the construction of the building is undertaken as per detailed design and specifications
11 Bring to the notice of the SEOR any situation or circumstances which in his opinion are liable to endanger the safety of structure.
12 Deposit with the Competent Authority (Authority-I) one set of working drawings of the works executed along with the progress certificates before proceeding to the next stage of the work.
13 Take adequate measures to ensure that no damage is caused to the work under construction and the adjoining properties.
3.3.3 Civil Engineer on Record (abbreviated as CEOR)
The Civil Engineer on Record shall:
1 Be the Person on Record responsible for ensuring compliance with all procedural requirements specified in these Bye-Laws.
2 Scrutinize and verify the structural design and specifications of the proposed building.
3 Certify that the structural design and specification of the proposed building comply with these Bye-Laws using the format prescribed in Form No. 2.
4 Immediately inform the Competent Authority (Authority-I ) in writing, if in his/her opinion, the construction of the building is not being undertaken in accordance with the sanctioned design requirements, in the format stipulated in Form No. 3.
5 Inform the Competent Authority (Authority-I) in writing, within 7 working days, if for any reason he/she is relieved of his/her responsibilities or he/she relieves himself/herself of responsibility as the Civil Engineer on Record for the building using the format prescribed in Form No. 4. In case of termination of services as Civil Engineer on Record, inform the Competent Authority (Authority-I) about the stage of work at which services are terminated. The registered Civil Engineer appointed as replacement of the preceding Engineer shall inform within 7 days about his/her appointment on the job and inform the Competent Authority (Authority-I) of any deviation that might have occurred on the site with reference to the approved drawings and the stage at which he/she is taking over the charge. After Competent Authority has inspected the site for his/her report, the newly appointed Civil Engineer shall allow the work to proceed under his/her direction.
6 On behalf of the owner, submit the progress certificates, completion certificates and obtain the Occupancy Certificate as required under these Bye-Laws.
Page No 40
7 Inform the Competent Authority (Authority-I) immediately on termination of the services of the Structural Engineer on Record.
8 Instruct the relevant agency that adequate provisions are made for ensuring the safety of workers and others during excavation, construction, and erection.
9 Instruct the relevant agency that adequate provisions are made for providing safe and adequate temporary structures required for construction and development.
- Undertake all necessary measures, including but not limited to, adequate inspection during construction to ensure that the construction of the building is undertaken as per detailed design and specifications
11 Bring to the notice of the SEOR any situation or circumstances which in his opinion are liable to endanger the safety of structure.
12 Deposit with the Competent Authority (Authority-I) one set of working drawings of the works executed along with the progress certificates before proceeding to the next stage of the work.
13 Take adequate measures to ensure that no damage is caused to the work under construction and the adjoining properties.
3.3.4 Structural Engineer on Record (abbreviated as SEOR)
The Structural Engineer on Record shall:
1 Scrutinize and verify the structural design and specifications of the proposed building.
2 Prepare a report of the structural design.
3 Supply two copies of structural drawings to the Owner/developer
4 Advise the Owner/developer for arranging for tests and their reports for soil, building material etc. for his evaluation and design consideration.
Submit the certificate of structural safety and over all structural soundness of the proposed building and its compliance to the Rules to Competent Authority (Authority-I) using the format prescribed in Form No. 2.
6 To prepare detailed structural design and to prescribe the method and technique of its execution strictly on the basis of the National Building Code or relevant Indian Standard specifications.
7 Detailed structural drawings and specifications for execution indicating thereon, design live loads, safe soil bearing capacity, specifications of material, assumptions made in design, special precautions to be taken by contractor to suit the design assumptions etc. whatever applicable.
8 Immediately inform the Competent Authority (Authority-I) in writing, if in his opinion, construction of the building is not being undertaken in accordance with the structural design and specifications stipulated by him, in the format stipulated in Form No. 3
9 Inform the Competent Authority (Authority-I) in writing, within 7 working days, if for any reason he is relieved of his responsibilities as the Structural Engineer on Record for the building, using the format prescribed in Form No. 4