- 1 Short Title, Commencement, Applicability, Repeal and Savings 17
- 2 Definitions 19
- 2.1 Access 19
- 2.2 Accessory Building 19
- 2.3 Accessory Use 19
- 2.4 Addition and/or alterations 19
- 2.5 Advertising Display Infrastructure / Advertising Sign, billboards, and Hoarding 19
- 2.5A Advisor to the Administrator 19
- 2.6 Air-conditioning 19
- 2.7 Amenities 19
- 2.8 Apartment/ Flat 19
- 2.9 Application 19
- 2.10 Approved 19
- 2.11 Atrium 19
- 2.12 Authorized Officer 20
- 2.13 Appeal 20
- 2.14 Appellate Authority 20
- 2.15 Authority 20
- 2.16 Balcony 20
- 2.17 Banquet Hall 20
- 2.18 Basement 20
- 2.19 Build to Line 21
- 2.20 Building 21
- 2.21 Building Unit/Plot 22
- 2.22 Built Unit / Plot Depth 22
- 2.23 Built up Area 22
- 2.24 Built up Area, Carpet 22
- 2.25 Built up Area, Dwelling Unit 23
- 2.26 Cabin 23
- 2.27 Canopy 23
- 2.28 Celing 23
- 2.29 Chhajja/Weather Shed 23
- 2.30 Chimney 23
- 2.31 Chowk 24
- 2.32 Cold Storage 24
- 2.33 Collector 24
- 2.34 Competent Authority 24
- 2.35 Common Plot 24
- 2.36 Community Hall 24
- 2.37 Construction 24
- 2.38 Contiguous Holding 24
- 2.39 Conversion 24
- 2.40 Cornice 24
- 2.41 Corridor 24
Page No 2
- 2.42 Courtyard 25
- 2.43 Density 25
- 2.44 Developer 25
- 2.45 Development Permission 25
- 2.46 Development of land 25
- 2.47 Dharamshala 25
- 2.48 Domestic Wastewater 25
- 2.49 Drain / Drainage System 25
- 2.50 Dwelling Unit 25
- 2.51 Enclosed Staircase 25
- 2.52 Escalator 26
- 2.53 Escape Route 26
- 2.54 External Wall 26
- 2.55 Existing Development / Building / Use 26
- 2.56 Floor 26
- 2.57 Floor Area 26
- 2.58 Floor Space Index (FSI) or Floor Area Ratio (FAR) 26
- 2.59 Footing 26
- 2.60 Foundation 26
- 2.61 Front 26
- 2.62 Gallery 27
- 2.63 Garage-Private 27
- 2.64 Garage-Public 27
- 2.65 Government 27
- 2.66 Ground Coverage 27
- 2.67 Ground Level 27
- 2.68 Habitable Room 27
- 2.69 Hazardous Material 27
- 2.70 Height of a Room 27
- 2.71 Height of building 28
- 2.72 High tide line 28
- 2.73 Home Occupation 28
- 2.74 Illuminated Exit Signs 28
- 2.75 Integrated Island management Plan (IIMP) 28
- 2.76 Land 28
- 2.77 Lift/Elevators 28
- 2.78 Lobby 28
- 2.79 Loft 29
- 2.80 Margin 29
- 2.81 Mezzanine Floor 29
- 2.82 Natural Hazard 29
- 2.83 Natural Hazard Prone 29
- 2.84 No- Development Zone (NDZ) 29
- 2.85 Non-Ambulatory Disabilities 29
- 2.86 Non-Potable Water 29
- 2.87 Occupant Load 29
- 2.88 Open Space 29
- 2.89 Operational constructions 29
- 2.90 Owner 29
- 2.91 Parapet 30
- 2.92 Parking Space 30
Page No 3
- 2.93 Partition 30
- 2.94 Persons on Record 30
- 2.95 Plinth 30
- 2.96 Pergola 31
- 2.97 Pollution control Board 31
- 2.98 Porch 31
- 2.99 Premises 32
- 2.100 Prohibited Industrial Waste 32
- 2.101 Pre-school 32
- 2.102 Public Purpose 32
- 2.103 Rain water harvesting system 32
- 2.104 Renovation and Repair 32
- 2.105 Rear 32
- 2.106 Registered Architect / Structural Engineer/ Civil Engineer 32
- 2.107 Retrofitting 32
- 2.108 Road / Street 32
- 2.109 Road / Street – Public 32
- 2.110 Road / Street level or Grade 33
- 2.111 Road/ Street Line 33
- 2.112 Road width or Width of Road/ Street 33
- 2.113 Row houses 33
- 2.114 Service Apartment 33
- 2.115 Service Road 33
- 2.116 Setback Line 33
- 2.117 Solid Waste 33
- 2.118 Stair Cabin / Stair Cover / Mumty 33
- 2.119 Staircase 34
- 2.120 Stairwell 34
- 2.121 Storey 34
- 2.122 Temporary Structure 34
- 2.123 To Erect 34
- 2.124 Unauthorised Construction 34
- 2.125 Use / Occupancy 34
- 2.126 Ventilation 36
- 2.127 Warehouse 36
- 2.128 Waterbody 36
- 2.129 Water Closet (WC) 36
- 2.130 Water Course 36
- 2.131 Wayside Shop 36
- 2.132 Wholesale Establishment 36
- 2.133 Window 36
- 3 Responsibilities of Owner and / or Developer and Persons on Record 37
- 3.1 Responsibilities of Owner / Developer 37
- 3.1.1 Owner / Developer to Apply for a Development Permission 37
- 3.1.2 Responsibilities of Owner or Developer 37
- 3.2 Registration of Persons on Record (POR) 37
- 3.2.1 Registering with the Competent Authority 37
- 3.2.2 Minimum Qualifications and Competence Requirements 38
Page No 4
- 3.2.3 Registration Fees and Security Deposit 38
- 3.2.4 Cancellation of Registration 38
- 3.2.5 Penalties 38
- 3.3 Responsibilities of Individual Persons on Record (POR) 39
- 3.3.1 Responsibilities of all POR 39
- 3.3.2 Architect on Record (abbreviated as AOR) 39
- 3.3.3 Civil Engineer on Record (abbreviated as CEOR) 40
- 3.3.4 Structural Engineer on Record (abbreviated as SEOR) 41
- 4 Development Permission 42
- 4.1 Development Permission Required 42
- 4.1.1 Operational constructions 42
- 4.2 Development Permission Not Required 42
- 4.3 Grant of a Development Permission 43
- 4.3.1 Grant of a Development Permission 43
- 4.3.2 Liability 43
- 4.4 Lapse, Suspension or Cancellation of Development Permission 43
- 4.4.1 A Development Permission shall Lapse 43
- 4.4.2 A Development Permission shall Stand Suspended 43
- 4.4.3 A Development Permission shall Stand Cancelled 43
- 4.4.4 General Provisions regarding Lapse, Suspension, or Cancellation of the Development Permission 44
- 4.5 Revision of Development Permission 44
- 4.6 Extension / Revalidation of Development Permission 44
- 4.7 Unauthorized Development 44
- 4.7.1 Unauthorized Development 44
- 4.7.2 Dealing with Unauthorized Development 44
- 4.8 Relaxation, Interpretation and Conflict Resolution Mechanism 45
- 4.8.1 Grant of Relaxation 45
- 4.8.2 Appellate Authority to Clarify and Interpret Provisions of the Rules 45
- 4.8.3 Conflict Resolution Mechanism and Apples unauthorised development and refusal to grant development permission or occupancy certificate 45
- 4.9 Penalties 45
- 4.10 Obtaining Direct Development Permission 46
- 4.10.1 Application, Document and Registration 46
- 4.10.2 Fees and Charges 46
- 4.10.3 Scrutiny of Application, Registration or Cancellation of Direct Development Permission 46
- 4.10.4 Penalties 47
- 4.11 Obtaining Development Permission 47
- 4.11.1 Application 47
- 4.11.2 Fees and Charges 47
- 4.11.3 Scrutiny of Application, Grant, or Refusal of a Development Permission 47
- 4.11.4 Penalties 48
- 4.12 Revising a Direct Development Permission 48
- 4.12.1 Application, Documents and Registration 48
- 4.12.2 Fees and Charges 48
- 4.12.3 Scrutiny of Application, Registration or Refusal of Revised Direct Development Permission 48
- 4.12.4 Penalties 49
Page No 5
- 4.13 Revising a Development Permission 49
- 4.13.1 Application 49
- 4.13.2 Fees and Charges 49
- 4.13.3 Scrutiny of Application, Grant, or Refusal of a Revised Development Permission 49
- 4.13.4 Penalties 50
- 4.14 Revalidating a Lapsed/Suspended Direct Development Permission 50
- 4.14.1 Application, Documents and Registration 50
- 4.14.2 Fees and Charges 50
- 4.14.3 Scrutiny of Application, Registration or Refusal of Revised Direct Development Permission 50
- 4.14.4 Penalties 51
- 4.15 Revalidating a Lapsed/Suspended Development Permission 51
- 4.15.1 Application 51
- 4.15.2 Fees and Charges 51
- 4.15.3 Scrutiny of Application, Grant, or Refusal of a Lapsed Development Permission 51
- 4.15.4 Penalties 52
- 4.16 Temporary Construction Permission 52
- 4.16.1 Application 52
- 4.16.2 Fees and Charges 52
- 4.16.3 Scrutiny of Application, Grant, or Refusal of Permission 52
- 4.16.4 Penalties 53
- 5 Procedure During Construction 54
- 5.1 Inspection of Construction 54
- 5.1.1 Inspection of Construction at Any Time 54
- 5.1.2 Inspection where Development Permission is Granted 54
- 5.2 Information to be Prominently Displayed on Site 54
- 5.3 Documents and Drawings to be Maintained on Site 54
- 5.4 Reducing Inconvenience and Ensuring Safety during Construction 55
- 5.4.1 Stacking, Storing and Disposal of Building Material 55
- 5.4.2 Barricading the Building Unit / Plot during Construction 55
- 5.4.3 No Damage or Undue Inconvenience during Construction 55
- 5.4.4 Liability for Ensuring during Construction 55
- 5.5 Progress of Construction and Inspection 55
- 5.5.1 Notice for Commencement of Construction 55
- 5.5.2 Development Permission may Lapse if Construction Not Commenced on Time 55
- 5.5.3 Competent Authority to be Notified of Progress of Construction 56
- 5.6 Inspections 56
- 6 Occupancy Certificate/Building Use Permission 57
- 6.1 Occupancy Certificate Required 57
- 6.2 Grant of Occupancy Certificate 57
- 6.3 Cancellation of Occupancy Certificate 57
- 6.4 Unauthorized Use / Occupancy of Building / Development 57
- 6.5 Obtaining an Occupancy Certificate 57
- 6.5.1 Application 57
- 6.5.2 Fees and Charges 58
- 6.5.3 Final Inspection and Grant / Refusal of Occupancy Certificate 58
- 6.5.4 Penalties 59
- 6.6 Permission to Change Sanctioned Occupancy / Use of Development 59
- 6.6.1 Application 59
- 6.6.2 Fees 59
Page No 6
-
6.6.3 Scrutiny of Application, Grant, Refusal 59
-
6.6.4 Penalties 59
-
Part B Planning Rules
-
7 General Planning and Development Rules 62
-
7.1 General requirements 64
-
7.2 Uses Permitted in Each Category
-
7.3 Floor Space Index 68
-
7.3.1 Floor Space Index (FSI) 68
-
7.3.2 Area Exempted from Computation of Floor Space Index (FSI) 69
-
7.4 Minimum Area of Building Unit for Different Uses 71
-
7.5 Approach Road / Access to Building Unit 71
-
7.5.1 Approach Road / Means of Access. 71
-
7.5.2 Land Locked Building Unit and Required Road Width69
-
7.6 Building Height 72
-
7.7 Margins 72
-
7.7.1 Roadside Margin or Front Margin 73
-
7.7.2 Rear and Other Side Margins 73
-
7.7.3 Margins between Buildings and Common Plot 73
-
7.7.4 Permissible Uses in Margin 74
-
7.7.5 Restrictions on Development in Margin 76
-
7.8 Basement in a Building Unit 76
-
7.9 Construction of new building within the building unit 76
-
7.10 Addition to the existing Building 76
-
7.11 Row House and Tenement Type Buildings 76
-
7.11.1 Row Type Buildings 76
-
7.11.2 Tenement Type Building 77
-
7.12 Provision for Podium 77
-
7.12.1 Uses Permitted 77
-
7.12.2 General Requirements 77
-
7.13 Parking 78
-
7.14 Development of Land 80
-
7.14.1 Internal Road and Approach to Building and Common Plot 80
-
7.14.1(A) Completion Certificate for Approved Layout Plan 82
-
7.14.2 General Requirements for Internal Roads 82
-
7.14.3 Subdivision of Building-Unit 83
-
7.14.4 Common Plot 83
-
7.15 Development on Kabrastan, Burial Ground etc 86
-
7.16 Heritage / Architectural Significant Areas 86
-
7.17 Development Work to be in Conformity with the Rules 86
-
8 Electric Vehicle (eV) Charging Station 87
-
9 Advertising Display and Communication Infrastructure 88
-
9.1 Outdoor Advertising Display Infrastructure 88
Page No 7
- Communication tower 89
- Part C Performance Rules
- 10 Building and Infrastructure 91
- 10.1 Architectural Elements 91
- 10.1.1 Boundary Wall Compound Wall and Gate 91
- 10.1.2 Level of Building Unit 92
- 10.1.3 Paving in Building Unit 92
- 10.1.4 Access 92
- 10.1.5 Plinth 94
- 10.1.6 Entrance 94
- 10.1.7 Minimum Clear Heights in Buildings 94
- 10.1.8 Mezzanine 97
- 10.1.9 Loft 98
- 10.1.10 Railings / Parapet 98
- 10.1.11 Terrace 99
- 10.1.12 Staircases, Corridors and Passageway 99
- 10.1.13 Ramp 100
- 10.1.14 Habitable rooms 101
- 10.1.15 Kitchen 102
- 10.2 Parking 102
- 10.2.1 Parking to be Provided. 102
- 10.2.2 Parking Layout Specifications for Cars 102
- 10.2.3 Parking Layout Specifications for Two Wheelers 103
- 10.2.4 Parking Layout Specifications for Trucks 104
- 10.2.5 Specified Parking for Loading and Unloading 104
- 10.3 Lighting and Ventilation 104
- 10.3.1 Lighting and Ventilation of Rooms 104
- 10.3.2 Ventilation of Atrium 104
- 10.3.3 Ventilation of Bathrooms and Water Closets 104
- 10.3.4 Ventilation of Staircase for Dwelling 1 and 2 105
- 10.3.5 Ventilation of Industrial Building 105
- 10.3.6 Ventilation of Special Building 105
- 10.3.7 Change of Ventilation System 105
- 10.4 Heating and Air Conditioning 105
- 10.4.1 Air Conditioning of Special Building 105
- 10.5 Water Supply Requirements 105
- 10.5.1 Water Storage Tank 105
- 10.5.2 Drinking Water Supply 106
- 10.6 Building Signage 106
- 10.7 Letter Box 106
- 10.8 Sanitation 106
- 10.8.1 For Residential Buildings 106
- 10.8.2 For all Buildings other than Residential 107
- 10.8.3 For Special Buildings 108
- 10.9 Drainage 108
- 10.10 Electrical Infrastructure 109
- 10.11 Digital Communication Infrastructure 109
- 10.11.1 Solutions for In-Buildings and Gated Buildings 109
- 10.11.2 Provisions at the layout Level 110
- 10.11.3 Provision of In Building Solutions Components (as per NBC 2016) 110
- 10.11.4 Process for obtaining IBS-NOC for Development permission and Occupancy Certificate 111
Page No 8
- 10.12 Lifts and Elevators 111
- 10.12.1 For buildings exceeding 4 m height with following uses: Public Offices, Assembly, Educational 2, 3 111
- 10.12.2 For buildings having parking at other than ground floor 111
- 10.12.3 General Requirements for Lifts and Elevators 111
- 10.13 External Façade 113
- 11 Fire Prevention Safety and Protection 114
- 11.1 Fire and Safety Clearance Requirements 114
- 12 Special Buildings 115
- 12.1 Visibility 115
- 12.2 Mixed Occupancy 115
- 12.3 Public Offices / Hospital Buildings 117
- 12.4 Public Safety 117
- 13 Structural Safety 118
- 13.1 Applicability 118
- 13.2 Structural Stability and Maintenance of Existing Buildings 118
- 13.3 Additions and Alterations to Existing Buildings 118
- 13.4 Change of Use of Building or Part of a Building 118
- 13.5 Structural Safety Provision during Construction 118
- 13.6 Structural Safety Tests for Special Buildings 119
- 13.7 Design for Structural and Seismic Safety 119
- 13.7.1 Design Standards 119
- 13.7.2 Structural Inspection Report 120
- 13.8 Structural Safety of Display Structure 120
- 14 Environmental Management / Sustainability 121
- 14.1 Rainwater Management 121
- 14.1.1 Rainwater Disposal 121
- 14.1.2 Rainwater Harvesting 121
- 14.1.3 Open Spaces within Layouts 123
- 14.1.4 Public Open Spaces 123
- 14.2 Solid Waste Management 123
- 14.3 Grey Water Recycling 123
- 14.3.1 Applicability 123
- 14.3.2 Provisions of Recycling System 123
- 14.3.3 Quality of Water and Treatment 124
- 14.3.4 General Provisions 124
- 14.3.5 Enforcement of Rules 124
- 14.4 Tree Plantation 124
- 14.5 Solar Energy Systems 124
- 14.5.1 Solar Water Heating System 125
- 14.5.2 Roof Top Solar Energy Installations and Generation 125
- 14.6 Energy Efficient Buildings 125
- 14.7 Environment Impact Assessment 125
- 15 Pollution Control 126
- 15.1 Air Pollution 126
- 15.2 Water Pollution 126
Page No 9
- 15.3 Noise Pollution 126
- 15.4 Industrial Pollution 126
- 16 Maintenance and Upgradation 127
- 16.1 Maintenance of Buildings 127
- 16.1.1 Responsibility for Maintenance of Buildings 127
- 16.1.2 Periodic Inspection and Maintenance Certificate 127
- 16.2 Maintenance of Lifts and Escalators 127
- 16.2.1 Responsibility for Maintenance of Lift and Escalators 127
- 16.2.2 Maintenance Protocol 127
- 16.3 Maintenance of Fire Prevention and Safety Provisions 127
- 17 Conformity to other Acts and Rules 129
- 17.1 No Objection Certificates (NOC) / Approvals 129
- 17.1.1 NOC from Defence Establishment 129
- 17.1.2 Environmental Clearance 129
- 17.1.3 NOC under CZMA 129
- 17.2 Conformity to Other Acts 129
- 18 Quality Control and Inspection 130
- 18.1 Applicability 130
- 18.2 Inspection and Safety Certificate 130
- 19 Power of administrator to amend Building Bye Laws 130
Page No 10