(i) All provisions of Byelaws except items given below shall not be compounded/ regularized and shall have to be rectified by alteration/demolition at the risk and cost of owner.
Compoundable Items:
(2) FLOOR AREA RATIO (FAR) – Maximum 2%
Set back – upto 0.30 m
(4) Open space - maximum 10% reduction
(5) Total height of building - 10%
(6) Unauthorized construction, if it is within the norms of Building Byelaws subject to satisfaction of the Authority.
(7) Additional of extra floor to accommodate area within compoundable FLOOR AREA RATIO (FAR).
Non compoundable Items:
(1) Use of building
(2) Addition of extra floor
(3) Parking norms
(4) Projection/ encroachment of public land.
Note: Additional floors will mean additional floors beyond the compoundable FLOOR AREA RATIO (FAR).
(ii) Compoundable Items
If a building or part thereof has been constructed unauthorisedly i.e. without obtaining the required building permit from the Authority as required by Building Byelaws the same shall be compounded at the following rates provided the construction otherwise conforms to the provisions of Building Byelaws & Master Plan and Zoning Regulations. For this party shall have to submit the request for permission in the prescribed procedure as per Assam Building Construction (Regulation) Act, 2022.
(iii) Rates for compounding shall be as given in the Schedule-I
(iv) Corporations, Urban Local Bodies (ULBs), and Gaon Panchayats (GP) shall initiate action as per provisions of respective Acts and byelaws for building constructed in deviation from the approved plan. Guwahati Metropolitan Development Authority and other development Authorities, DD/AD TCP shall also initiate action as per provision of the respective Acts and Byelaws on detection of deviation. For buildings permissions granted prior to byelaws of 2014 for GMA, Authority granting permission shall initiate action. For other areas, buildings permitted prior to coming into force of this Unified Byelaws of 2022, Authority granting permission shall initiate action. In general after coming into force of the Unified Byelaws of 2022, the building permit issuing Authority shall take action against deviations /violations in construction for buildings permitted under this byelaw..
Note: The Authority may however refuse regularisation of construction even with penalties as specified in the above provisions if in the opinion of the Authority this may infringe public safety and general environment of adjoining area.
(vi) Any deviation from approved plan shall be corrected by demolition of the unauthorized part of the construction except that If a building or part thereof has been constructed without obtaining the required building permit from the Authority but in conformity with Building Byelaws, the same shall be compounded at the rates prescribed in Schedule-I.