i. In case of plots upto 60 sqm. common parking shall be provided.
ii. In case of plots of size 500 sqm and above, the utilities such as E.S.S., underground water storage tank, roof top water harvesting system, separate dry and wet dustbins, solar heating / lighting system etc. shall be provided within the plot.
iii. Identified Service Centres shall be planned as per plotted industrial area norms.
iv. Development of IT hardware and software permissible under industrial use.
v. ² [Banquet hall shall be permissible in Industrial premises subject to specifications / regulations as may be prescribed, along with conversion charges as prescribed by the Government from time to time.]
vi. ³[Industrial units / plots abutting roads of 24m ROW and above shall be eligible for conversion to commercial use within the existing development control norms, subject to payment of conversion charges ⁴{computed on current market value of commercial area and cost of parking as decided by the Government from time to time. The activities permissible in Community Centre will be permitted in such plots.} In addition, multilevel parking shall be permissible activity. However, this shall not be permitted on non-conforming / regularized industrial cluster. The above provision shall not affect the Supreme Court orders in any way.]
vii. ⁵ [Industrial plots abutting roads of 24m ROW and above shall be eligible for conversion to ⁶ {Hospital / Tertiary Health Care Centre} (up to 100 beds) within the existing development control norms, subject to the conditions (a) the number of
¹ Modified vide S.O. 3904(E) dated 29-10-2020
² Substituted vide S.O. 2034(E) dated 12-08-2008
³ Added vide S.O. 1215(E) dated 13-05-2013
⁴ Modified vide S.O. 1215(E) dated 13-05-2013
⁵ Added vide S.O. 1215(E) dated 13-05-2013
⁶ Modified vide S.O. 3904(E) dated 29-10-2020
beds to be accommodated on a plot shall be worked out ¹{@ 100 sqm-80 sqm} of gross floor area per bed and (b) payment of conversion charges as prescribed by the government from time to time. The activities permissible in ² {Hospital / Tertiary Health Care Centre} (Table 13.20) shall be permitted in such plots. However, this shall not be permitted on non-conforming/ regularized industrial cluster. The above provision shall not affect the Supreme Court orders in any manner.
viii. In the redevelopment of industrial plots, 1.5 times of permissible FAR has already been notified in Notification S.O. 683 (E) dated 01.04.2011 regarding Regulations and Guidelines for Existing Planned Industrial Area, therefore, the incentive of 1.5 times of permissible FAR shall be allowed on all permissible uses on industrial plot.
ix. Banquet Hall, Restaurant, Recreational Club, Hostel & Old age home, Community and Recreational hall, Nursing Home & Health Centre are permitted as part of modification in layout plan of industrial area where also enhanced FAR 1.5 times of permissible FAR of respective Use shall be allowed.
x. As per the Notification S.O. 683 (E) dated 01.04.2011, minimum plot size eligible for redevelopment is given 1000 sqm. whereas some of the plots are less than 50-100 sq.mts from area limit of 1000 Sq.mts. In such redevelopment relaxation in area upto 5% in lower limit of plot size shall be permitted.
xi. The development control norms i.e. Ground Coverage, FAR etc. of respective use premises while allowing redevelopment/ reconstruction on the individual industrial plots shall be adhered to and there shall be no height restriction. ³ {The height permitted shall be subject to clearance from AAI, Delhi Fire Services and other statutory bodies.} In case of addition, alteration or change of use within permissible category in existing building to achieve permissible FAR, already sanctioned ground coverage shall continue, if parking requirement or sufficient open space around building is made available.
xii. In existing Industrial Units/ plots with an area of 3000 sq.mtrs. or above abutting road of 24mtr. ROW and above shall be eligible for Residential use (Group Housing) within development control norms of group housing along with incentive 1.5 times FAR of permissible FAR of Group Housing subject to payment of Conversion charges as prescribed by the Government from time to time for respective use. Required Commercial preferably and PSP activity for residential population, and working space up to 15% of Permissible FAR shall also be allowed. Sub-division of larger Industrial plot or amalgamation of smaller Industrial plots will be allowed in existing areas as well as approved schemes/ layouts/ building plans on these Industrial Plots. Rain water harvesting preferably with Rain water storage for re-use & STP, Dual piping system use of solar electricity shall be provided to minimize the additional burden on infrastructure services. This provision shall not affect any Court Orders.]
¹ Modified vide S.O. 2893(E) dated 23-09-2013
2-3 Modified vide S.O. 3904(E) dated 29-10-2020
ANNEXURE –1[7.0 (I)]