In case of existing developed areas, all wholesale markets generated with hazardous materials should be developed in decentralized manner and shifted to the areas assigned for these. All unauthorized encroachments / projections on roads / government land should be removed to facilitate easy movement of traffic. Further extension of the wholesale activity in the Walled City and its Extension shall be totally stopped by giving incentives and disincentives as under:
i) Incentives:
a) The liasioning offices of the traders/ agents to continue in the present location;
b) Development of New counter markets for wholesale trade and warehousing;
c) The new counter markets should have access from National Highway, arterial networks and connectivity with MRTS; and
d) Incentives such as Transferable Development Rights (TDR) and reduced taxes to enable start up / expanding of activity in the new markets.
ii) Disincentives:
a) Restriction on the entry of heavy goods vehicles in the Special area;
b) Storage of hazardous / inflammable commodities like paper, plastic / PVC, chemicals, petroleum and its products; should be discouraged.
c) Restriction on storage / warehousing of bulky commodities like food grains, fruits and vegetables, dairy, poultry / fish products, iron and steel, and building materials; and
d) Non-renewal of trade licenses for Wholesale Trade in non-conforming areas.
Sadar Bazar
The old congested built up areas like Sadar bazaar have serious problems of traffic congestion, inadequate physical and social infrastructure, lack of open spaces etc. The wholesale market of Sadar bazaar needs to be redeveloped at the same location with necessary infrastructure and parking required for wholesale trade.
6.1.2 Proposed Wholesale Markets Within Integrated Freight Complexes
It is proposed to develop new wholesale markets as counter markets to cater to the demands of the growing population of Delhi only, near the rail and road entry points of NCTD. These should be linked with the proposed Wholesale Markets within Integrated Freight Complexes where the wholesale business could be operated more efficiently in a better environment. The break up of land requirement for different commodities at various locations should be decided at the time of preparation of schemes for the complex by the implementing agency.
Wholesale markets within Integrated Freight Complexes are to be developed as per requirement.
The new wholesale markets shall provide facilities for:
i) Intra-urban freight movement and interchange of mode.
ii) Warehousing and storage facilities.
iii) Servicing, lodging and boarding, idle parking and other required facilities.
6.2Sub-city Level Markets
Delhi has become an agglomeration of cities over a period of time. Sub-City level wholesale markets shall cater to the needs of population at local level. These markets of medium size need to be dispersed throughout the city to enable even distribution of commodities from these complexes to the retail outlets.
Most of the existing planned markets and warehousing were developed in early seventies for specific commodities. Due to their proximity to residential area, these markets need to be redeveloped to overcome the environmental and traffic problems. ¹ [To incentivize the redevelopment, a maximum overall FAR of 50% over and above the permissible FAR shall be given.] The traders associations shall share the responsibility of redevelopment to modern wholesale markets. The beneficiaries will have to pay the betterment charges to the implementing agency. Space for commodities that are not permissible in mixed use streets under para 15.6. shall be made available in wholesale city level market and sub-city level market to enable their relocation.
Some of the existing planned Wholesale Markets, Warehousing and Transport Centres are as given in Table 6.1.
Table 6.1Sub-City Level Markets
S. No.
Location
Commodity / Activities
i)
Azadpur
Fruit and vegetable
ii)
Okhla
Fruit and vegetable
iii)
Keshopur
Fruit and vegetable
iv)
Naraina
Iron and Steel
v)
Sanjay Gandhi Transport Centre
Transport / Warehousing
vi)
Rohtak Road Transport Centre
Transport / Warehousing
vii)
Narela
Food grains
viii)
Najafgarh
Food grains
2[ix]
Kirti Nagar
Timber]
In addition to above, the following wholesale markets are to be developed:
i) Loni Road
ii) Rohini Ph-IV / V
iii) Dwarka Sub-City
iv) Narela Sub-City
In Urban Extension, about 8-10 ha. of land for about one million population should be provided for such Sub-City level markets. The different commodities to be provided at various locations should be decided at the time of preparation of schemes by the implementing agency. These markets shall have adequate parking, repair and servicing facilities. Land should be identified in each zone accordingly.
Chapter 6
6.0 Wholesale Trade
Delhi is the biggest consumption centre in North India. It has attained the status of a major distribution centre by virtue of its geographical location and other historical factors.
As per Economic Survey of Delhi 2001-2002, there are about 37,000 wholesale enterprises in Delhi with an employment of about 1.6 lakh. In addition there are about 6,500 enterprises of storage and warehousing providing employment to 27,000 persons. It is expected that the number of enterprises in wholesale trade may increase to about 66,000 by 2021 leading to increase in employment to about 2.85 lakh persons. Some of the major commodities involved in the wholesale trade are textile and related products, food items, auto-parts and machinery, hardware and building materials, paper and stationery, fruits and vegetables and Iron and Steel.
Around 20% of the total wholesale trade enterprises of urban Delhi are located in the walled city, accounting for around 12% of the employment. The average enterprise in the Walled City has less employment but high turnover in comparison to units in other areas. In order to decentralise wholesale trade, the planned markets were developed at Azadpur, Naraina, Okhla, Narela, Keshopur, etc.
¹ Added vide S.O. 1215(E) dated 13.05.2013
² Added vide S.O. 2690(E) dated 11-08-2016
6.3Storage of OIL, CNG and LPG
Shakurbasti Oil Depot has been shifted to a site between Ghevra and Tikri Kalan, which will be a major storage site for oil. The land thus vacated should be partly utilized for Disaster Management Centre and rest for recreational activities.
No new Depots for oil and LPG shall be developed in NCT of Delhi. The new depots required for the increased energy requirement shall be developed in the National Capital Region and the supply of Oil / LPG / CNG etc. to Delhi should be through pipelines.
Table 6.2Development Controls – Wholesale Trade
Use/ Use Premises
Maximum
Parking StandardECS/100 sq.m. of floor area
Definition
Activities Permitted
Ground Coverage%
FAR
Height (m)
Integrated Freight Complex / Wholesale Market
30
80
No Restriction subject to (i)
3
Wholesale Market. A premise from where goods and commodities are sold and delivered to retailers. The premises include storage and godown, loading and unloading1[facilities].
Wholesale shop, Godown and storage, Commercial office (restricted to 25% of the total floor area), 2[Night Shelter]
Notes:
i) Height subject to clearance from Airport Authority of India, Fire Department and other statutory bodies.
ii) In case of plots upto 300 sqm. common parking is to be provided.
iii) In case of plots of size 300 sqm and above, the utilities such as E.S.S., underground water storage tank, roof top water harvesting system, separate dry and wet dustbins, solar heating / lighting system etc. are to be provided within the plot.
iv) In case of individual plots not forming part of any comprehensive / integrated development scheme, the development controls shall be as per already approved scheme / layout plan.
1-2 Added vide S.O. 2894(E) dated 23-09-2013
1[6.4 Norms for Redevelopment of Godown Clusters Existing in Non-conforming Areas
The National Capital Territory of Delhi Laws (Special Provisions) Seconds Act-2011 provides for formulation of “policy or plan for orderly arrangement regarding schools, dispensaries, religious institutions, cultural institutions, storages, warehouses and godowns used for agricultural inputs or produce (including dairy and poultry) in rural areas built on agricultural land and guidelines for redevelopment for existing Godown clusters (including those for a storages of non- agricultural goods) required to cater to the needs of the peoples of the National Capital Territory of Delhi”
6.4.1 Norms for Redevelopment of Godown Clusters in Non Conforming Areas
Following norms will be followed in redevelopment process, keeping in view the existing ground realities as well as the imperatives of planned development.
6.4.1.1 Stand alone Godown plots which do not form part of any cluster shall be governed with the following conditions:
i. Stand alone godowns (storage of non polluting / non hazardous materials) shall be allowed only which are having direct access from minimum 30 mtr ROW road.
ii. In village abadi (laldora area) and extended laldora areas, storage godowns of non-polluting / non-hazardous materials shall be allowed only which are having direct access from a. 9 mtr. RoW with plot size upto 300 sq.m (7.5 mtr. in case the road is defined / approved by the revenue deptt.) b. 12 mtr. RoW for plot size above 300 sqm .
iii. These godowns shall be allowed subject to fulfillment of parking requirements within the plot and NOC from the Traffic Police Deptt. and the Fire Deptt. of GNCTD.
iv. The loading / unloading facility from the vehicles shall be provided within the plot.
v. Owners of standalone godowns needs to get the plans approved 2{by 31.12.2023}. The owners of plots falling in nonconforming areas and existing godowns located on less than 30.0 m 1{ROW} will have to shift to the other conforming
1 Added vide S.O. 3027(E) dated 21-06-2018
2 Modified vide S.O. 3405 (E) dated 19-08-2021
areas / godown clusters 1{by 31.12.2023}. Such godowns functioning in non-conforming areas shall have to close down within the above said time period.
6.4.1.2 Non-conforming clusters of godowns / warehousing activities of minimum 2 Ha. contiguous area and having concentration of more than 55 percent of the plots within the clusters may be considered for redevelopment of area identified on the basis of actual surveys.
After notification of such clusters by the local bodies / GNCTD, the redevelopment scheme will have to be prepared by the society (to be formed by the land owners) based on following norms / conditions and thereafter approval by concerned local body.
i. The cluster should have direct access from a road of minimum 30mt RoW.
Formation of group or society shall be mandatory to facilitate preparation of redevelopment scheme / plan, development of services, parking and maintenance, pollution control and environment management.
iii. Amalgamation and reconstitution of plots shall be permissible for redevelopment within the scheme area.
iv. Owners of the godowns shall have to obtain the requisite statutory clearances from the concerned agencies, wherever necessary. After approval of the Layout Plan for redevelopment by the society, the identified clusters will be processed for change of land use on receiving the proposal from local body.
6.4.2 Other Conditions
6.4.2.1. Development control norms for the godown plot incorporating the risk based classification as per Table 3.2 of UBBL 2016, shall be as follows:
Plot Size (in sq m)
Max. Gr. Coverage(%)
Max. FAR
Max. Height
Parking
Up to 500
70
140
Below 15 m
- Common parking to be provided in case of plots upto 300 sq.m. - 3 ECS / 100 sq.m. of floor area for plots above 300 sq.m.
Above 500 - 2000
60
120
Below 15 m
Above 2000 - upto10,000
50
100
Below 15 m
Above 10,000
40
80
Below 15 m
Wherever the building regulations are given for different categories of plots, the covered area and the floor area shall in no case be less than the permissible covered area and floor area respectively for the largest size of plot in the lower category.
Conformity to fire safety norms based on Risk based classification as per UBBL 2016; Delhi Fire Services Act.
Common parking shall be provided for plots up to 300sqmt. size and front setback shall be provided without boundary wall for use of parking and loading / unloading purposes.
For plots above 300 sq.m, provision for parking and loading / unloading shall be made by the owners within their plots.
Provision / use of basement shall be as per the stipulations of MPD-2021.
Workroom / Office (not exceeding 25% of the permissible FAR) related to godown activity within godown premises shall be allowed in a covered permanent structure with proper arrangements of dust and pollution control subject to clearance from statutory bodies.
6.4.2.2. The remaining plot owners shall be allowed to continue with existing use or conversion to godowns or any permissible use as per provisions stipulated in the MPD / UBBL / policy guidelines and after obtaining clearances / permissions from all statutory bodies.
6.4.2.3. All the Redevelopment Schemes under these guidelines shall conform to all the statutory provisions and Master Plan stipulations / UBBL, 2016.
6.4.2.4. The concerned local body and the stakeholders will work out the mechanism for the recovery of stipulated levies / charges.
6.4.2.5. In case of surrender of land for road widening, the FAR of the original plot will be permissible.
6.4.2.6. The implementation of these regulations be brought out by the Local Body as part of User Friendly Guide covering the Frequently Asked Questions (FAQs) for such projects.
v. Other stipulations shall include:
a) About 10% area is to be reserved for circulation / roads / service lanes.
b) About 10% area of semi permeable surface for common parking, idle parking and loading / uploading areas.
c) About 10% of the area to be reserved for associated infrastructure requirement such as Electric Sub-stations, Fire Station, Police Post, servicing, lodging and Boarding and informal market areas etc. as per the norms.
d) Preparation of Plan for water supply from DJB / Central Ground Water Authority (wherever required) along with
1 Modified vide S.O. 3405 (E) dated 19-08-2021
1-2 Modified vide S.O. 3844 (E) dated 24.10.2019
requirement for pumping stations, storage tanks, ground water recharging / rainwater harvesting and Drainage plan as per norms.
e) About 8% of the area shall be reserved for parks / green buffer.
f) Utilities such as ESS, underground water storage tank, rain water harvesting system, solar heating / lighting systems etc. will be provided within the plot.
g) All plots within the scheme should have direct access from road of minimum12 mts RoW.
vi. Other provisions / development control norms shall be applicable as prescribed.
Note: Subject to availability of land for these facility mentioned at v) (a, b, c, e) within godown cluster or in the surrounding area be considered.
vii. Requisite conversion charges and any other levies as decided by the Government from time to time (wherever applicable) would be required to be paid to the concerned Authority.
viii. Redevelopment plans of individual clusters will have to be prepared by the society and thereafter approved by the concerned local authority / MCD. The redevelopment shall be completed within three years from the date of approval of the plans.
ix. Clusters, which fail to complete the redevelopment proposals within the period specified as above, shall have to shift to other conforming areas and these godowns functioning in non-conforming clusters shall have to close down. In such cases, the licensing authority will not renew the licenses to such godowns without obtaining land use clearance from the competent authority. Further, no new licenses will be issued in non-conforming areas, without obtaining land use clearance.
6.4.2.7. The following areas shall not be eligible for godown clusters redevelopment scheme: Bungalow Zones (New Delhi & Civil
Lines), the Ridge, River Bed (Zone-O), areas along water bodies, canals, sensitive areas from security point of view, conservation & heritage areas, reserved/protected forests, DDA flats, Cooperative Group Housing Societies, Government flats/bungalows/employer housing etc. and their immediate proximity.]