The category of urban poor for purpose of the Plan would mainly comprise the inhabitants of squatter settlements and informal service providers. Such services could include domestic help, hawkers and vendors, low paid workers in the industrial, commercial and trade / business sectors, etc. These include both existing population and future migrants. In terms of housing requirements of the city, this continues to be the single biggest challenge and would require a mix of approaches and innovative solutions.
4.2.3.1 Rehabilitation / Relocation of Slum & JJ Clusters
In so far as the existing squatter settlements are concerned, the present three-fold strategy of relocation from areas required for public purpose, in-situ up-gradation at other sites to be selected on the basis of specific parameters and environmental up-gradation to basic minimum standards shall be allowed as an interim measure. Rest of the clusters, till they are covered by either of the first two components of the strategy, should be continued.
During the Plan period 1981-2001, sites and services approach based relocation was employed in which resettlement of squatter slums was done on 18 sqm and 12.5 sqm. plots (transit accommodation)allotted to eligible persons on licence basis. This has led to a number of aberrations and there are several aspects, due to which this approach needs to be progressively abandoned and substituted by an alternate approach. Broadly, speaking this alternate approach should have the following components:
(i) Resettlement, whether in the form of in-situ up-gradation or relocation, should be based mainly on built up accommodation of around 25 sq. m with common areas and
facilities, rather than on the model of horizontal plotted development.
(ii) The concept of land as a resource should be adopted to develop such accommodation with private sector participation and investment, to the extent possible.
(iii) Incentives by way of higher FAR, part commercial use of the land and, if necessary and feasible, Transfer of Development Rights should be provided.
(iv) A cooperative resettlement model with adequate safeguards may be adopted with tenure rights being provided through the institution of Co-operative Societies.
(v) The provision of accommodation should be based on cost with suitable arrangements for funding / financing, keeping in view the aspect of affordability and capacity to pay.
(vi) In cases of relocation, the sites should be identified with a view to develop relatively small clusters in a manner that they can be integrated with the overall planned development of the area, particularly keeping in view the availability of employment avenues in the vicinity. Very large resettlement sites could lead to a phenomenon of planned slums.
(vii) Suitable arrangement for temporary transit accommodation for families to be rehabilitated should be made. This may preferably be near or at the same site and the utilization of these may be synchronised with the phases of implementation of the scheme of in-situ up-gradation.
(viii) Community Based Organisations (CBOs) and Non-Governmental Organisations (NGOs) should be closely involved in the resettlement process.
4.2.3.2 Resettlement Colonies
Most of the resettlement colonies have been provided with essential services, but the immediate need is of individual services i.e. water, sewerage and electricity. To ensure healthy and better environment, the construction of houses needs to be based on approved / standard building plans.
Co-operative societies / private developers / govt. agencies may come forward for redevelopment based on the incentives as applicable for the Squatter Rehabilitation Scheme. Reconstruction of existing plotted development, group housing should be
encouraged as per the Redevelopment Guidelines given in para 4.2.3.4.
4.2.3.3 New Housing for Urban Poor
New housing should be in the form of one or two room units, which would be developed through public and private agencies and through Cooperative societies. As this category constitutes bulk of the housing stock that has to be catered at an affordable price to the lowest income bracket as housing for Economically Weaker Sections (EWS), this is often done by cross-subsidization.
For this purpose, adequate land would be earmarked for EWS housing. The developers of group housing shall ensure that minimum ¹ [15% of proposed FAR to be] constructed for Community-Service Personnel / EWS and lower income category. ² [Employer Housing of Central Government, State Government and other Government Agencies are not required to follow the requirement of FAR or Dwelling Units for Community Service Personnel / EWS and lower income category.] In old built up areas, this may be as redevelopment schemes or industrial housing, etc., whereas, in urban extensions, the acquisition and development cost of this land should be borne by rest of the project. Such reserved lands should be handed over to a designated agency for promoting housing for low income and weaker sections.
The pattern of EWS housing shall be such as to ensure optimal utilization of land in a sustainable manner. For that purpose, multi-storied housing will be the preferred option. Apart from mandatory provision for EWS housing in all group housing projects/ schemes, the primary responsibility for creating adequate stock of housing for urban poor shall be borne by public agencies.
4.2.3.4 Slum & JJ Redevelopment Regulations and Guidelines for Collective Community Rehabilitation / Relocation - In-situ Upgradation / Rehabilitation of Slum & JJ Clusters, Resettlement Colonies, ³[schemes for rehabilitation of project-affected persons# and Unsafe Buildings*#] ⁴[and EWS public housing schemes]
¹ Modified vide S.O. 1215 (E) dated 13-05-2013
² Added vide S.O. 1277(E) dated 19-05-2009
³ Added vide S.O. 2894(E) dated 23-09-2013 and modified vide S.O. 2895(E) dated 23-09-2013
⁴ Added vide S.O. 2895(E) dated 23-09-2013
The ¹[implementing agency / corporate body concerned] should work out schemes for collective community rehabilitation/relocation and explore the possibility of involving private sector/slum cooperatives. In existing resettlement colonies, redevelopment, regular servicing and maintenance, which are overdue, are to be based on the guidelines and incentives as applicable for the Slum& JJ Rehabilitation Scheme ¹[schemes for rehabilitation of project-affected persons# and for Unsafe Buildings*#] ²[and EWS public housing schemes.]
The following guidelines with site-specific relaxations may be adopted as required. Regular monitoring of executed schemes and revision of these guidelines at the time of preparation of new schemes is essential. Group housing norms shall be applicable with the following conditions:
(i) ¹ [Minimum plot size 2000 sqm (on a min. ROW of 9m).] ¹ [In case of Public Housing, the Technical Committee of DDA may relax minimum plot size by 10 %.]
4.2.3.5 1 [Affordable Rental housing Complexes (ARHCs)
ARHCs schemes aimed at creating vibrant, sustainable and inclusive affordable rental housing avenues for urban migrants and urban poor including street vendors, rickshaw pullers, other service providers, industrial workers, migrants labours for market/trade associations, educational/health institutions, hospitality sector, long-term tourists/visitors, students or any other persons of such category.
The Modalities with respect to ARHC shall be as per the Operational Guidelines for the Affordable Rental Housing Complexes as issued by Ministry of Housing and Urban Affairs, Govt. of India. Further, these shall also adhere to the approvals as granted by DDA.]