4.1.General
The building envelope shall comply with the mandatory provisions of clause 4.2 and either the prescriptive criteria of clause 4.3 or the trade-off option of clause 4.4.
4.2.Mandatory Requirements
4.2.1 Fenestration
4.2.1.1 U-Factors
U-factors shall be determined for the overall fenestration product (including the sash and frame) in accordance with ISO-15099, as specified in Appendix C clause 11, by an accredited independent laboratory, and labeled and certified by the manufacturer or other responsible party. U-factors for sloped glazing and skylights shall be determined at a slope of 20 degrees above the horizontal. For unrated products, use the default table in Appendix C clause 11.
4.2.1.2 Solar Heat Gain Coefficient (SHGC)
SHGC shall be determined for the overall fenestration product (including the sash and frame) in accordance with ISO-15099, as specified in Appendix C clause 11, by an accredited independent laboratory, and labeled and certified by the manufacturer or other responsible party.
Exceptions to clause 4.2.1.2:
(a) Shading coefficient (SC) of the centre glass alone multiplied by 0.86 is an acceptable alternate for compliance with the SHGC requirements for the overall fenestration area.
(b) Solar heat gain coefficient (SHGC) of the glass alone is an acceptable alternate for compliance with the SHGC requirements for the overall fenestration product.
4.2.1.3 Air Leakage
Air leakage for glazed swinging entrance doors and revolving doors shall not 2exceed 5.0 l/s-m . Air leakage for other fenestration and doors shall not exceed 22.0 l/s-m .
PUNJAB ENERGY CONSERVATION BUILDING CODE 2013
Envelope
4.2.2 Opaque Construction
U-factors shall be determined from the default tables in Appendix C clause 11 or determined from data or procedures contained in the ASHRAE Fundamentals, 2005
4.2.3 Building Envelope Sealing
The following areas of the enclosed building envelope shall be sealed, caulked, gasketed, or weather-stripped to minimize air leakage:
(a) Joints around fenestration and door frames;
(b) Openings between walls and foundations and between walls and roof and wall panels;
(c) Openings at penetrations of utility services through, roofs, walls, and floors;
(d) Site-built fenestration and doors;
(e) Building assemblies used as ducts or plenums; and
(f) All other openings in the building envelope
4.3.Prescriptive Requirements
4.3.1 Roofs
Roofs shall comply with either the maximum assembly U-factor or the minimum insulation R-value in Table 4.1. R- Value is for the insulation alone and does not include building materials or air films. The roof insulation shall not be located on a suspended ceiling with removable ceiling panels.
| Climate Zone | 24-Hour use buildings Hospitals, Hotels, Call Centers, etc. | Daytime use buildings Other Building Types | ||
| Maximum U-factor of the overall assembly (W/ m2-ºC) | Minimum R-value of insulation alone (m2-ºC/W) | Maximum U-factor of the overall assembly (W/ m2-ºC) | Minimum R-Value of insulation alone (m2-ºC/W) | |
| Composite | U-0.261 | R-3.5 | U-0.409 | R-2.1 |
Note: Punjab is covered by Composite climate zone only. For information on other climate zones, please refer relevant tables of ECBC
Envelope
4.3.1.1 Cool Roofs
Roofs with slops less than 20 degrees shall have an initial solar reflectance of no less than 0.70 and an initial emittance of no less than 0.75. Solar reflectance shall be determined in accordance with ASTM E903-96 and emittance shall be determined in accordance with ASTM E408-71 (RA1996)
4.3.2 Opaque Walls
Opaque walls shall comply with either the maximum assembly U-factor or the minimum insulation R-value in Table 4.2. R-value is for the insulation alone and does not include building materials or air films.
| Climate Zone | Hospitals,Hotels, Call Centres (24 Hour) | Other Building Types (Daytime) | ||
| Maximum U-factor of the overall assembly (W/ U-0.440 | Minimum R-value of insulation alone (m2-ºC/W) | Maximum U-factor of the overall assembly (W/ m2-ºC) | Minimum R-Value of insulation alone (m2-ºC/W) | |
| Composite | U-0.440 | R-2.10 | U-0.440 | R-2.10 |
Note: Punjab is covered by Composite climate zone only. For information on other climate zones, please refer relevant tables of ECBC
4.3.3 Vertical Fenestration
Vertical fenestration shall comply with the maximum area weighted U-factor and maximum area weighted SHGC requirements of Table 4.3. Vertical fenestration area is limited to a maximum of 60% of the gross wall area for the prescriptive requirement.
| WWR≤40% | 40% | ||
| Climate | Maximum U-factor | Maximum SHGC | Maximum SHGC |
| Composite | 3.30 | 0.25 | 0.20 |
| See Appendix C clause 11.2.1 for Default values of Unrated Fenestration | |||
Note: Punjab is covered by Composite climate zone only. For information on other climate zones, please refer relevant tables of ECBC
Exception to clause 4.3.3: Overhangs and/or side fins may be applied in determining the SHGC for the proposed design. An adjusted SHGC, accounting
Envelope
for overhangs and/or sidefins, is calculated by multiplying the SHGC of the unshaded fenestration product times a multiplication (M) factor. If this exception is applied, a separate M Factor shall be determined for each orientation and unique shading condition by Equation 12-2 and the overhang and side fins coefficients are available in Table 12.6 clause 12.
| Overhang "M" Factors for 4 Projection Factors | Vertical Fin "M" Factors for 4 Projection Overhang +Fin"M" Factors | Overhang +Fin"M" Factors for 4 Projection Factors | ||
| Project Location | Orientation | 0.25- 0.50- 0.75- 1.000.49 0.74 0.99 + | 0.25- 0.50- 0.75- 1.000.49 0.74 0.99 + | 0.25- 0.50- 0.75- 1.000.49 0.74 0.99 + |
| North latitude 15º or greater | N | 88 .80 .76 .73 | .74 .67 .58 .52 | .64 .51 .39 .31 |
| E/W | .79 .65 .56 .50 | .80 .72 .65 .60 | .60 .33 .10 .02 | |
| S | .79 .64 .52 .43 | .79 .69 .60 .56 | .60 .33 .10 .02 | |
| Less than 15º North Latitude | N | 83 .74 .69 .66 | .73 .65 .57 .50 | .59 .44 .32 .23 |
4.3.4 Skylights
Skylights shall comply with the maximum U-factor and maximum SHGC requirements of Table 4.6. Skylight area is limited to a maximum of 5% of the gross roof area for the prescriptive requirement.
| Maximum U-Factor | Maximum SHGC | |||
| Climate | With Curb | w/o Curb | 0-2% SRR | 2.1-5% SRR |
| Composite | 11.24 | 7.71 | 0.40 | 0.25 |
Note: Punjab is covered by Composite climate zone only. For information on other climate zones, please refer relevant tables of ECBC
SRR= Skylight roof ratio which is the ratio of the total skylight area of the roof, measured to the outside of the frame, to the gross exterior roof. See clause 11.2.2 for typical complying skylight constructions.
4.4.Building envelope Trade Off Option
The building envelope complies with the code if the building envelope performance factor (EPF) of the proposed design is less than the standard design, where the standard design exactly complies with the criteria in clause 4.3. The envelope trade-off equation is found in Appendix D clause12.