3.1.Compliance Requirements
3.1.1 Mandatory Requirements
a) Compliance with the requirements of PECBC shall be mandatory for all applicable buildings discussed in clause 2.
b) All Government notifications related to energy conservation or mandatory use of any product/process or equipment shall be complied with.
c) In buildings specified in clause 2, preferably locally manufactured/ available material should be used.
3.1.2 New Buildings
New buildings shall comply with either the provisions of clause 4 through clause 8 of PECBC or the whole building performance method of Appendix B clause 10.
In case, the project is to be built in phases, then PECBC shall be applicable on the whole building load in total and not the individual buildings designed later on in phases.
3.1.3 Additions to Existing Buildings
Where the addition plus the existing building exceeds the conditioned floor area threshold of clause 2, additions shall comply with the provisions of clause 4 through clause 8. Compliance may be demonstrated in the following ways:
(a) The addition, together with the entire existing building, shall comply with the requirements of this code that would apply to the entire building, as if it were a new building.
Exception to clause 3.1.3: When space conditioning is provided by existing systems and equipment, the existing systems and equipment need not comply with this code. However, any new equipment installed must comply with specific requirements applicable to that equipment.
3.1.4 Alterations to Existing buildings
Where the existing building exceeds the conditioned floor area threshold in clause 2, portions of a building and its systems that are being altered shall meet the
Administration and Enforcement
provisions of clause 4 through clause 8. The specific requirements for alterations are described in the following sub clauses 3.1.4.1 to 3.1.4.5.
Exception to clause 3.1.4: When the entire building complies with all of the provisions of clause 4 through clause 8 as if it were a new building.
3.1.4.1: Building Envelope
Alterations to the building envelope shall comply with the requirements of clause 4 for fenestration, insulation, and air leakage applicable to the portions of the buildings and its systems being changed.
Exception to clause 3.1.4.1: The following alterations need not comply with these requirements provided such changes do not increase the energy usage of the building.
a) Replacement of glass in an existing sash and frame, provided the U-factor and SHGC of the replacement glazing are equal to or lower than the existing glazing
b) Modifications to roof/ceiling wall, or floor cavities which are insulated to full depth with insulation
c) Modifications to walls and floors without cavities and where no new cavities are created.
3.1.4.2 Heating, Ventilation and Air Conditioning
Alterations to building heating, ventilating, and air-conditioning, equipment or systems shall comply with the requirements of clause 5 applicable to the portions of the building and its systems being altered. Any new equipment or control devices installed in conjunction with the alteration shall comply with the specific requirements applicable to that equipment or control device.
3.1.4.3 Service Water Heating
Alterations to building service water heating equipment or systems shall comply with the requirements of clause 6 applicable to the portions of the building and its systems being altered. Any new equipment or control devices installed in conjunction with the alteration shall comply with the specific requirements applicable to that equipment or control device.
Administration and Enforcement
3.1.4.4 Lighting
Alterations to building lighting equipment or systems shall comply with the requirements of clause 7 applicable to the portions of the building and its systems being altered. New lighting systems, including controls, installed in an existing building and any change of building area type as listed in Table 7.1 shall be considered an alteration. Any new equipment or control devices installed in conjunction with the alteration shall comply with the specific requirements applicable to that equipment or control device.
Exception to clause 3.1.4.4: Alterations that replace less than 50% of the luminaries in a space need not comply with these requirements provided such alterations do not increase the connected lighting load.
3.1.4.5 Electric Power and Motors
Alterations to building electric power systems and motor shall comply with the requirements of clause 8 applicable to the portions of the building and its systems being altered. Any new equipment or control devices installed in conjunction with the alteration shall comply with the specific requirements applicable to that equipment or control device.
3.1.4.6 Star Labelling and Minimum Star Rating
All equipments and materials of type and specification coming under the purview of the star labeling program as notified by BEE shall have minimum three star rating or above or as notified by the State Government.
3.2 Compliance Approaches
The building shall comply with the mandatory provisions (clause 4.2, clause 5.2, clause 6.2, clause 7.2 and clause 8.2) and either of the following:
(a) Prescriptive Method (clause 4.3, clause 5.3, clause 6.3 )
Exception to clause 3.2 (a):The envelope trade-off option of clause 4.4 m a y be used in place of the prescriptive criteria of clause 4.3.
(b) Whole Building Performance Method(Appendix B clause 10)
3.3 Administrative Requirements
Administrative requirements relating to permit requirements, enforcement, interpretations, claims of exemption, approved calculation methods, and rights of appeal are specified by the authority having jurisdiction.
Administration and Enforcement
3.3.1 Authority having Jurisdiction
For the administration and enforcement of the PECBC, the State Designated Agency shall act as the “Authority having Jurisdiction” who shall be responsible for specifying permit requirements, code interpretations, approval calculation methods, worksheets and formats, compliance forms, manufacturing literature, rights of appeal, and any other data to demonstrate compliance.
3.4 Compliance Documents
3.4.1 General
Plans and specifications shall show all pertinent data and features of the building, equipment, and systems in sufficient detail to permit the authority having jurisdiction to verify that the building complies with the requirements of PECBC. Detail shall include, but are not limited to:
(a) Building Envelope: Insulation materials and their R-values, fenestration U-factors, solar heat gain coefficients (SHGC), visible light transmittance (if the trade-off procedure is used), and air leakage; overhangs and sidefins, building envelope sealing details.
(b) Heating, Ventilation, and Air-Conditioning: system and equipment types, sizes, efficiencies, and controls; economizers; variable speed drives; piping insulation; duct sealing insulation and location; requirement for balance report
(c) Service Hot Water and Pumping: solar water heating system
(d) Lighting: lighting schedule showing type, number, and wattage of lamps and ballasts; automatic lighting shutoff, occupancy sensors, and other lighting controls; lamp efficacy for exterior lamps
(e) Electrical Power: Electric schedule showing transformer losses, motor efficiencies, and power factor correction devices, electric check metering and monitoring system.
3.4.2 Supplemental Information
The authority having jurisdiction may require supplemental information necessary to verify compliance with this code, such as calculations, worksheets, compliance forms, manufacturer's literature, or other data.
Envelope