3.1.1 In order to demonstrate compliance with the code, the building shall comply with all of the mandatory requirements stated in Chapter 4 along with either of the two approaches
a) Prescriptive approach as mentioned in Chapter 5
b) Points based system approach as mentioned in Chapter 6
3.1.2 Table 1 below gives the minimum ENS score required to be obtained as per eligible project category:
| Project Category | Minimum ENS Score |
|---|---|
| Low rise buildings | 47 |
| Affordable Housing | 70 |
| High rise buildings | 100 |
3.1.3 Low Rise Buildings: A building equal or below 4 stories, and/or a building up to 15 meters in height (without stilt) and up to 17.5 meters (including stilt).
3.1.4 Affordable Housing Projects: Affordable houses are Dwelling Units (DUs) with Carpet Area less than 60 sqm. It also includes Economically Weaker Section (EWS) category and Lower Income Group (LIG) category (LIG-A: 28-40 sq. m. and LIG-B 41-60 Sq.m.). For details, refer chapter 7.
3.1.5 High Rise Buildings: A building above 4 stories, and/or a building exceeding 15 meters or more in height (without stilt) and 17.5 meters (including stilt).
3.1.6 Compliance for Mixed Mode Buildings
a) In a mixed-use building, having both commercial and residential building use, each category of a building use must be classified separately, and –
i. If a part of the mixed-use building classification (residential or commercial) is less than 10% of the total above grade floor area, the mixed-use building part shall show compliance based on the building sub-classification having higher percentage of above grade floor area.
ii. If a part of the mixed-use building has different classification (residential or commercial) and one or more sub-classification is more than 10% of the total above grade floor area, the compliance requirements for each sub-classification, having area more than 10% of above grade floor area of a mixed-use building, shall be determined by the requirements for the respective building classification.
iii Basement and common area services, designed for a particular building use or documented with respective buildings for compliance with authority having jurisdiction, needs to show compliance with the clauses for the respective building requirement.
b) In a mixed mode building with different category of residential buildings in the same project and including one or more category listed in 3.1.2 (low rise building, affordable housing, and/ or High-rise building)
i. Compliance for site marked for affordable housing, as per the applicable bye law, shall be shown separately.
ii. The overall point to be achieved for ENS building for site marked for affordable housing is 70.
iii If the site area with low rise buildings in the overall project is more than or equal to 20% of the total site area, the site marked for low rise building, as per the applicable bye law, shall be shown separately to other residential building type. The overall point to be achieved for ENS building for the site marked for this low-rise building is 47.
iv. If the site area with low rise buildings in the overall project is less than 20% of the total site area, the site marked for low rise building, as per the applicable bye laws, shall be shown together with other residential building category. The overall point to be achieved for ENS Compliance for the overall site is 100. In such projects:
-
Mandatory points – compliance to be shown only for the components which are provided in the project and is necessary as per the applicable building bye law.
-
Additional points –
a. to claim the additional points of any component in building services and indoor area services mentioned in section 6.5 and 6.6, except for requirements for basement lighting, project needs to install the component for minimum 80% of the total above grade area (AGA) or for component designed for 80% of total AGA.
b. to claim the additional points for requirements of basement lighting mentioned in section 6.5, ENS building to show compliance for total basement area designed in the project and as per applicable building by-law.
c. to claim the additional points of any component in building envelope mentioned in section 6.4, project needs to install the component as mention in section of the component for overall project.
3.1.7 Prescriptive Method
i. In order to demonstrate compliance with the code through the Prescriptive Method, the ENS building shall meet mandatory requirements specified under chapter 4 and all prescriptive requirements as per chapter 5, for compliance purpose.
3.1.8 Point System Method
i. In order to demonstrate compliance with the code through the Point System Method, the ENS building shall meet all applicable mandatory requirements specified in chapter 4 and obtain a minimum ENS Score as per section 6.1 in chapter 6, for this purpose:
• All Low-rise residential buildings must obtain minimum 47 points from ‘Building Envelope’ under section 6.4.
• All Affordable housing scheme must obtain minimum 70 points from ‘Building Envelope’, and ‘Building Services’ under section 6.4 and 6.5 respectively.
All High-rise residential buildings must obtain minimum 100 points from ‘Building Envelope’ and ‘Building Services’, ‘Indoor Electric End-Use’ and ‘Renewable Energy Systems’ under section 6.4, 6.5, 6.6 and 6.7, respectively.
• The Table 2 below gives the component wise distribution of points for each building component to achieve minimum ENS Score.
| Section | Components | Minimum points | Additional Points | Maximum Points |
| 6.4 | Building Envelope | |||
| Building Envelope | 47 | 40 | 87 | |
| 6.5 | Building Services | |||
| Common area and exterior lighting | 3 | 6 | 9 | |
| Elevators | 13 | 9 | 22 | |
| Pumps | 6 | 8 | 14 | |
| Electrical Systems | 1 | 5 | 6 | |
| 6.6 | Indoor Electrical End-Use | |||
| Indoor Lighting | 12 | 12 | ||
| Comfort Systems | 50 | 50 | ||
| ENS Score | 70 | 130 | 200 |
ii. The code also provides additional 20 points for renewable energy as mentioned in Table 3 which can be availed after fulfilling the minimum points criteria as per Table 3.
| Section | Components | Minimum Points | Additional Points | Maximum Points |
| 6.7 | Renewable Energy Systems |