(1) The Competent Authority shall constitute such Committees for the purpose specified in Code 2.5, for scrutiny of applications received as specified under Code 2.1 and for submission of recommendations for sanction/ refusal of such applications.
(2) The Committee shall consist of officer/ official as decided by the Competent Authority and shall meet every week or as may be decided by the Competent Authority;
(3) The recommendations of the members of the committee shall be forwarded to the Competent Authority for consideration and approval, with or without change.
(4) The committee or any officer authorized shall pass on order and convey the decision of sanction or rejection in Form BR-III.
Validity of sanctioned plans
(1) Every sanction for the erection or re-erection of any building shall remain valid for two years in case of building height is less than 15 metres and for multi-storeyed buildings (fifteen metres or above in height) the sanction shall remain valid for five years from the date of sanction.
If a building is not completed within two years (or five years, as the case may be) of the date of permission, the sanction will be deemed to have lapsed with respect to that portion of the building which has not been completed. In regard to the incomplete portion of a building, a fresh application shall be submitted in accordance with Code 2.1 and prescribed scrutiny fee.
(3) The temporary buildings, permitted by Competent Authority, shall not be allowed to stand three months beyond the validity of the sanctioned plans.
[27]
4.4 Re-validation of building plans
After sanction of building plan, in case the construction could not be started within two years (or five years, as the case may be) or has been started but could not be completed within the stipulated period, the owner/ applicant may apply for the revalidation of building plans before the sanction has lapsed simply by submitting re-validation fee @ Rs 10/- (rupees ten only) per square metre for the proposed covered area requested for re-validation. This revalidation of of submission of revalidation fee.
4.5 Deemed sanction
10[The Competent Authority shall pass an order within a period of twenty days of submission of building plans, accompanied by all necessary documents as mentioned in Code 2.1, either sanctioning or rejecting it. The building plan shall be deemed to be sanctioned, if it is in conformity with building Code and in accordance with the permitted land use of the area and all leviable fee/ charges have been deposited by the applicant but no orders have been passed by the Competent Authority within the specified time.