12.1. Any building above 250 sq.mts in plinth area reported to be unsafe or damaged shall be examined by a technical committee to be constituted by the Authority and shall make a written record of its finding. The Authority shall give notice to the owner or occupier to complete the specified repairs or improvements or to demolish the building within a stated time.
12.2. Other buildings below 250 sq. mts. shall be examined by the technical branch of the Authority and shall make a written record of its finding. The Authority shall give notice to the owner or occupier to complete the specified repairs or improvements or to demolish the building within a stated time.
12.3 Disregard of Notice
If the owner fails to comply with the notice, the Authority can itself demolish or remove the structure and realize the cost of demolition through suitable method, or the Authority may take assistance of the Police department to remove the structure as it deem fit.
12.4 Building to BE Vacated
The Authority may on prima facie evidence of inspections/findings that structural elements in a building or building construction appear to be unsafe, may declare the building to be vacated until such records and evidences are produced by the applicant and his/her consultant engineer. The Authority shall keep a record of its findings in detail.
13. ARCHITECTURAL CONTROL
Any building proposed to be built in an important area of the city or in the case of important monumental building or proximity to building of historical importance, the building schemes may be referred to a broad base committee comprising of a panel of Architects, Planners and non-Governmental Organizations to be chaired by Chairperson of Meghalaya Urban Development Authority who will be the agency to identify such areas.
The identified areas, which need protection, shall be referred to the committee who in turn will be made responsible to protect such areas.
14. MAINTENANCE OF BUILDINGS
In case of building older than fifty years, it shall be the duty of the owner of a building, to get his building inspected by a Registered Structural Engineer (RSE) within a year from the date of coming into force of these byelaws. The Structural Inspection Report as given in Appendix –C, shall be produced by the owner to the Authority. If any action, for ensuring the structural safety and stability of the building is to be taken, as recommended by Registered Structural Engineer, it shall completed within five years. For other buildings, the owner shall get his building inspected after the age of building has crossed forty years. The procedure shall be followed as per above byelaw.
15. PROTECTIVE MEASURES IN NATURAL HAZARD PRONE AREAS
In natural hazard prone areas identified under the land use zoning regulations, structures, buildings and installations which cannot be avoided, protective measures for such construction / development should be properly safeguarded based on the suggestion given in Section-C.
16. FEES FOR BUILDING PERMISSION
16.1. The rates for residential, commercial, institutional, apartment, educational, storage, industries, major proposals etc., shall be chargeable as per the rate approved by the Government from time to time. The rate for Special Building category shall be fixed at a higher rate
16.2. For erection of Reception & Transmission Towers, an installation fee shall be charge and subsequently annual renewal fee shall be chargeable as per the rates approved by the Government from time to time.
16.3. No fees for building permission is required for plot area less than 75 Sq.m (LIG/EWS categories).
16.4. The fixation of these fees shall be governed by the following: -
(i) For erection of new building shall be as per Schedule of Fees.
(ii) For re-erection of existing building the fees chargeable shall be the same as for erection of new building.
(iii) For addition and alteration in the existing building, the fees shall be chargeable on the added portion only.
(iv) For revised plan of an already sanctioned building a processing fee as fixed by the Authority and approved to by the Government shall be paid by the applicant.
(v) For change of use and variation of rates, the fees chargeable shall be the difference between the two, subject to the conditions that
(a) The revised plan is in conformance with the building bye laws applicable for that particular use and the building plans are compatible for that use.
(b) No fees to be refunded in case there is change of use of higher rate to lower rate, e.g. Commercial to residential use.
(vi) For renewal of building permission, the processing fees as fixed by the Authority and approved to by the Government shall be paid and the validity shall be 18 months.
17. INSPECTION
General Requirements: - The building unit intended to be developed shall be in conformity with byelaw on requirement of site. Generally all development work for which permission is required shall be subject to inspection by the Authority as deemed fit. For Grade I & II the applicant shall keep a board at site of development mentioning the holding number , plot number, sub plot number, permission number, name of owner, name of Architect on Record, Engineer on Record, Developer, Structural Engineer on Record, Construction Engineer on Record or whichever is applicable.
All construction work shall be subject to inspection as prescribed in Forms VII and VIII by the Authority periodically.
(a) On receipt of notice of commencement of work, the owner and the consultant architect/licensed technical personnel supervising the construction shall be present at site on the day and time of giving the alignment of the building(s).
(b) After excavation of the foundation pits or trenches the owner and the consultant architect/licensed technical personnel supervising the construction shall be present at site on the day and time of giving the alignment of the building(s). It is mandatory for the Authority to inspect and approve the same. Any deviations or rectifications required shall be approved to by the authority within 14 days from the date of submission of the revised layout/ structures design drawing etc by the applicant during the above period, all construction activities shall be temporarily stopped by the applicant.
(c) On completion of column upto plinth and before its casting, the owner and the consultant architect/licensed technical personnel supervising the construction shall be present at site on the day and time after giving due intimation of 14 days to the Authority for approval.
(d) Any other stages of construction.
(e) On completion of work after the receipt of completion certificate.
Non compliance on the part of the owner, the licensed technical personnel to comply with the above provisions would result in the Authority declaring the building “Unauthorized Building” and necessary action against the offenders will be initiated by the Authority.
It is incumbent on the owner and the consultants to intimate to the Authority of the association of the consultants involved in the building construction and the substitutions thereof during the period of construction till its completion.
Section – B General Building Requirements
18. REQUIREMENT OF SITES
Any piece of land shall be used as a site for construction provided;
(i) The proposed use conforms to the Master Plan, Zonal Plan under Meghalaya Town & Country Planning Act, 1973.
(ii) The site is properly drained or capable of being drained.
(iii) The site have proper means of access.
(iv) The site is not prone to land slide.
(v) Generally, no earth cutting shall be permitted in order to achieve more no. of basements and all building proposals shall follow the slope profile of the plot and such earth cutting shall be limited to a maximum of 3.00 meters only. However the Authority may relax the same owing to site conditions and the maximum earth cutting height shall be upto the crest of the RCC wall being limited to 6.00 m only.
NO Land Shall BE Used AS a Site for the Construction of Building-
(i) If the site is found to be liable to liquefaction as per soil survey report under the earthquake intensity of the area, except where appropriate protection measures are taken.
(ii) If the Authority finds that the proposed development falls in the area liable to flooding, except where protection measures are adopted to prevent flooding damage.
19. REQUIREMENT OF SITE PLAN
(i) In hilly terrain, the site plan should include location of landslide prone areas, if any, on or near the site, detected during reconnaissance. The Authority in such case shall cause to ensure that the site is away from such landslide prone areas.
(ii) The site plan on a sloping site should also include proposals for diversion of the natural flow of water coming from uphill side of the building away from the foundation.
20. EXTERIOR OPEN SPACE
The building envelop shall be governed by the following minimum clear open space and setbacks:-
(i) Front setback
(a) Every building abutting a street/footpath shall have a front setback with a minimum width of 3 meters from the front property line to the front building envelop.
(b) In case the site fronts on two streets, both of which are major roads, then the front setback shall be a minimum of 3.00 m from the edge of both the roads’ right of way.
(c) In case the plot fronts two streets, one of which is a major road and the other a minor road but having the potential of being developed into a major road and or leading to an attraction zone(s), then the front setback shall be a minimum of 3.00 m from the edge of both roads’ right of way.
(ii) Side and Rear setback
Every building shall have a minimum clear side and rear setback as prescribed in these byelaws. No use is permitted in this open space except steps and soak pit or in case this space is 3.00 m wherein parking of vehicles is allowed.
21. MINIMUM PLOT SIZES
(i) Residential: - The minimum plot size shall be 93 Sq.m. In case of govt. lease properties the minimum plot size shall be as determined by the govt. from time to time.
(ii) For commercial: - The minimum plot size shall be 50 Sq.m with a minimum width of 6 metres.
(iii) For services, light, cottage and handloom industries: - The minimum size of pot shall not be less than 50 Sq.m. For automobile workshop a minimum plot size shall be 300 sq.m.
(iv) For medium industry: - The minimum size of the plot shall be 10,000 sq.m.
(v) For auditorium, Museum, Library: - The minimum size of the plot shall be 1000 sq. mts.
(vi) For LIG/EWS Income Housing: - For categories falling under LIG/EWS, an income certificate from respective Deputy Commissioner is also required for waiving of building permission fees. Typical plan upto 50 mts sq. single storied building can be obtained from Meghalaya Urban Development Authority with nominal cost for obtaining building permission.
22. DISTANCE FROM ELECTRICITY LINES
No verandah, Balcony or the like shall be allowed to be erected or re-erected or new addition or alteration made to a building within a distance quoted in Table-II below in accordance with the Current Indian Electricity Rules and its Amendments from time to time.
TABLE-II
| Vertically | Horizontally | ||
|---|---|---|---|
| a) | Low and Medium Voltage lines and services lines | 2.5 meter | 1.2.metre |
| b) | High voltage lines upto and including 33,000 V. | 3.7 meter | 2.0 meter |
| c) | Extra high voltage lines beyond 33.00 V | 3.7. meter | 2.0 meters(plus 0.3 (plus 0.3 meter for every additional 30,000 V 30,000 V. or part thereof ) |
23. REQUIREMENT OF PARTS OF BUILDING
Table III - Minimum Size and Width of Different Competent of residential Premises
Table III
| Sl.No. | Component of Building | Min. requirement for plots upto 50 sq.mt. | Min. requirement for plots upto 50 sq.mt. |
| 1. |