Criteria for Considering an Application for Exemption
Application Fees: The applicants seeking exemption under this rule shall apply in writing to the Secretary in form in Appendix N along with challan receipt remitting the application fee in the Government treasury as detailed below.
i) Single family residential building of built up area up to 100 sq.m …. No application fee
ii) Single family residential building of built up area up to 100 -300 sq.m - Rs 1000
iii) All other buildings with built up area up to 100 sq.m - Rs 2000
iv) All other buildings with built up area exceeding 100 sq.m but up to 1000 sqm …Rs10000
v) All other buildings with built up area exceeding 1000 sq.m - Rs 20000
Technical remarks: The Secretary shall submit the applications to the Chief Town Planner and Chief Town Planner shall submit the application to the Government with technical remarks for consideration.
Rules exempted: The following occupancies / rules will not be considered for exemption
| 1 | Occupancy group not considered for exemption from these rules. | Group G2- Industrial II, Group I-Hazardous ,Group J - Multiplex Complex, |
|---|---|---|
| 2 | Rules not considered for exemption from these rules | Rules under chapter II and III, R26 (3) ( provision of set back at ground itself), R 27- FSI, R 28 ( Access), R 30 (lay out approval),R 31 (land sub division and plot development), R 35 (2)(1) ( Fire escape stair case), ,R 36 (Travel distance to emergency exits),R -40 (Lift/ Escalator), R 41 (1) ( lighting and ventilation),R 41(7)- light and ventilation conformity with ECBC provisions, R 42 (Provisions for differently abled, Elderly and children), Rules under chapter X (Construction in plots part of which have been surrendered free of cost for road development), Rules under chapter XIII ( Special provisions for certain constructions), Rules under chapter XIV (Wells, Rainwater harvesting),Rules under chapter XV (Solar assisted water heating /lighting system), Rules under chapter XVI (waste disposal), Rules under chapter XVII ( safety provisions for high rise buildings), Rules under chapter XVIII(Telecommunication towers) and Rules under chapter XIX,XX. |
Criteria and Fee for exemption
The appeal application will be considered for exemption from the rules based on the criteria stipulated in table given below. The fee for exemption from various rules mentioned in the table will be cumulative and total fee will be calculated by summing of the exemptions fees individually for each rules as per the fee stipulated against each rules. However the exemption fee for Single family residential building & commercial building having built up area up to 100 sq.m is limited to Rs 5000/- and exemption fee for Single family residential building having built up area above 100 upto 300 sq.m is limited to Rs 20000/-
| Rules/Occupancy | Criteria | Exemption Fee | |
|---|---|---|---|
| 1 | Rule 26 - exterior and interior open space (except R 26 (3) ) | Constructions which are deficient up to 15 % (including tolerance as specified in rule 20(3) of the mandatory exterior and interior open space as per Rule will only be considered for exemption. | 1) Deficient by 0-10% - 10 times that of the permit fee. 2) Above10 up to 15 %- 25 times that of permit fee |
| 2 | Rule 27 - Coverage | Constructions which exceeds up to 5 % of the permissible value as per this rule will only be considered for exemption | Fair value of land in rupees per sq.m multiplied by additional plinth area in excess of that permissible as per this rule + Rs 8000 per sq m of built up area in excess of that permissible as per the rule. |
| 3 | Rule 29- Parking | Constructions which are deficient up to 10 % of the permissible value as per this Rule will only be considered for exemption | Fair value of land in rupees per sq.m multiplied by 15 sq m per parking subject to a minimum of Rs 3,00,000 per deficient car parking |
| 4 | Other Rules-R 32(Mezzanine floor),R 33(Height of rooms) R 34 (sanitation facilities),R 35 (1) (stair cases),R 35(2) ( fire escape stair case) 35 (3)-Ramp, R (37)-exit width 38- doorways,R39- corridor,R41 (2 to 6)- details of light and ventilation, 43 (Other provisions for apartment buildings),R 44(Other provisions for assembly buildings),R 45-(other provisions regarding Group G1), R 46-(other provisions regarding Group H ), R 49 (special provisions for hut),R 50(special provisions for construction in small plot), R 51(special provisions for row buildings), Rules under chapter VIII (provisions for construction under approved schemes), Rules under chapter XI (Accessory buildings and sheds) | The authority for exemption can consider all other rules for exemption taking in to account the type of construction and condition of site, subjected to a maximum deviation of 10% of the requirement. | 15 times that of the permit fee for each rule to be exempted |
For all other rules not mentioned here, the respective rules will prevail