1(a) The development of land and building for the purpose of development of Information Technology Park, Software and its associated, computer technology, Bio-Informatics units shall be certified by the appropriate authority designated by the Government for the purpose, to avail the concessions stated below and shall be in the following use zones as indicated below:
i) Primary Residential use zone
ii) Commercial use zone
iii) Industrial use zone
iv) Mixed Residential use zone
v) Institutional use zone
vi) Urbanisable use zone
vii) I.T.Corridor zone - lands along the Old Mamallapuram Road (irrespective of its land use zoning in the Master Plan / Detailed Development Plan) bounded by:
North City limit (Kottivakkam)
South CMA limit (Semmancheri village)
East Buckingham Canal
West about 500 metres from Old Mamallapuram Road, defined in Map No. MP-II/CMDA.14/2008)
(b) Areas: The proposed Information Technology development is permissible in the Chennai Metropolitan Area, subject to the provision of adequate water supply and sewage disposal arrangements to the satisfaction of the Authority in consultation with the Chennai Metropolitan Water Supply and Sewerage Board, Tamil Nadu Pollution Control Board, Local body as the case may be.
-
Activities: Manufacture of hardware, development of software and its associated computer - communication technology applications, bio-informatics units including offices, conference halls and projection theatres connected there with, only shall be permitted. No showrooms, other offices, residential uses and activities of similar nature shall be permitted. Provided that incidental activities such as staff canteen, staff recreational area, guest accommodation, watchmen quarters, and the like not exceeding 10% of the total floor area shall be permitted. Provided further that within above ceiling of 10%, each of the above incidental activities should not exceed 5% of the total floor area.
-
Road width: The proposed development shall either abut on a public road of not less than 18 metres in width or gain access from a passage of not less than 18 metres width which connects to a public road of not less than 18 metres width.
-
Site extent: The site extent shall not be less than 1500 Sq.m.
-
Height: (a) For non-multi-storeyed buildings, it shall be in conformity with the requirements prescribed in the respective Development Regulations.
(b) For Multi-Storeyed Buildings, maximum permissible height shall be 60 metres where the width of the abutting road is minimum 18 metres, and
exceeding 60 metres where the width of abutting road is minimum 30.5 metres, subject to such conditions as may be necessary.
Development charge shall be at double the normally leviable rate for the part of the building, which falls in the height exceeding 1.5 times the width of the abutting road.
- Floor Space Index: The Floor Space Index for such development shall be allowed as normally permissible in Development Regulations, if such proposals falls within the categories listed in the sub rule 1(a) above.
Provided that in case of developments where the site extent is not less than 2000 sq.metres and conforms to other regulations stated above, the Floor Space Index shall be allowed at 1.5 times of the Floor Space Index ordinarily permissible except in Primary Residential use zone within the Chennai City Corporation area.
7 Caution Deposit:
a. Caution Deposit to be made by the applicant before issue of Planning Permission shall be 10% of the guideline value of the land or 20% of the Guideline Value of the land area equal to which the additional floor area is availed, whichever is higher. The caution deposit is acceptable in the form of an irrevocable Bank Guarantee issued in the format prescribed by CMDA, in favour of Member-Secretary, CMDA from any scheduled bank in Chennai City.
b. The Bank Guarantee shall be kept alive till a final decision is taken by CMDA.
c. The Bank Guarantee towards caution deposit is returnable after a period of five years, from complete occupation and commencement of commercial operation subject to confirmation by a certificate from the Competent Authority (ELCOT) certifying that the building is put into continuous use for IT parks/Bio Informatics units for the said five years.
d. If the building is utilised for any other purpose during this period and the occupancy confirmation certificate from the Competent Authority (ELCOT) is not furnished, the Bank Guarantee shall be invoked and the caution deposit shall be forfeited by transferring the same to CMDA's account.
e. The caution deposit referred to above shall be different from and over and above the security deposit to be paid in the normal course of issue of Planning Permission.
f. The decision of CMDA is final in the invocation/release of Bank Guarantee.
-
Car Parking Standards: The covered Car Parking space will be allowed up to Ground+3 floors above ground level and the same shall not be included in the floor space index/plot coverage.
-
Other Parameters: Except for the above said rules, the developments shall conform to the Development Regulations in respect of all other parameters.