Transferable Development Rights is a tool for acquisition and development of the reserved sites and roads. Past experience shows that 11% of the area of reserved sites is acquired through this tool. Presently, the TDR awarded varies according to the potential of the zone from where it is generated. Moreover, highest award of TDR is equivalent to 1.00 FSI. The land, being the physical entity with potential of FSI, cannot be equated at par, with a TDR certificate having only FSI credit. In the result, quantum of TDR should have been more than that of land area. One more aspect need to be taken in to consideration that acquisition under land acquisition Act, provides for solatium and certain additional amount, which is absent in award of TDR. Therefore, this tool had not been proved so effective because of these basic differences and hence, this tool needs to be made rational.
A new Act, The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, came into force which provides for good compensation and equal amount of solatium which necessitates making of this tool more attractive. In this Development Plan, award of TDR is enhanced to a proportion of 1:2 for reserved sites and 1: 1.85 for Development Plan roads irrespective of zone from where it is generated. The utilisation of TDR is according to a formula which will encourage the utilization of TDR evenly across the city as elaborated in detail in DCPR.
TDR can also be awarded for development / construction of amenity and also for acquisition of old structures affected during acquisition of road land or reserved sites. The TDR utilisation limit on the plots are also have been increased substantially.
These revolutionary provisions will lead to drastic enhancement of level of implementation which is expected to reach 40% of the total cost of acquisition and 20% of cost of development / construction of amenity. It is also expected that 75% acquisition of road land shall be through this tool, which entitles owner 1:1.85 FSI in-situ.
The cost of plan to be met by this tool will be as below.
| Cost of acquisition | 40% of Rs. 4408 crores | = Rs. 1763.20 |
|---|---|---|
| Cost of development / construction | 20%of Rs. 766 crores | = Rs. 153.20153 crores. |
| Total cost to be shared by this tool | Rs. 1916.40 crores |