9.1 Level of Implementation of Development Plan
9.1.1 The existing Development Plan was partly sanctioned on 28/6/1993 and came into force on 16/11/1993. The remaining part was sanctioned on 15/5/1995 and came into force on 25/6/1995. Upto date, there are 538 reservations in the Development Plan covering an area of about 692.44 hectares. Out of these, 87 reservations are completely developed and 24 are partly acquired/ developed. The area of developed site is 71.65 hectares and partly acquired/ developed site is 33.47 hectares. The area acquired through TDR concept is 76.75 hectares containing 75 sites, fully or partly. The area developed under AR is 44.43 hectares containing 21 sites. The road land acquired under TDR is 109.82 hectare.
It is observed that total land reserved for various purpose in sanctioned Development Plan is 692.44 H. It means that only 22% of the land could be acquired under various tools available for acquisition of reserved sites.
Further, 21 reservations have to be deleted because of lapsing of reservations under section 127 of the Act. by the Court/ Government orders . Further some more reservations will get lapsed in view of the notices already issued under section 127 of the Act after ascertaining area and location of land involved in such notices.
This shows that reserving land in Development Plan to such extend was beyond the financial capacity of the Planning Authority.
9.2 Identification of Problems
1 There is paucity of housing for existing population. Also more housing stock will be required for future population. Moreover, houses in core area are older and many of them need redevelopment. The rates of lands and houses are increasing rapidly day by day.
-
Slum population in the Nashik city is remarkable. These slum dwellers need to be provided proper accommodation and amenities.
-
The residential and other development is taking place all over the city. However, trend of development is observed on major roads passing through city like National Highways, State Highways.
-
There is inadequate and un-coordinated traffic transportation network. The flyover on Mumbai-Agra Highway is constructed; however, there is necessity of other bypass roads to link other National and State Highways.
-
There is necessity of effective mass rapid transportation system so that congestion of vehicles on the roads gets reduced.
-
Provision of public parking is required at the places like C.B.S., M.G. Road, Main Road, Canada Corner, College Road, Gangapur Road, Bytco point, Dwarka junction etc.
-
As far as educational facilities are concerned, it seems that major burden of it is taken over by private sector. However, some provision for primary education needs to be made in view of future
population.
-
Facilities made available by the Government are reasonable. Moreover, contribution of private sector in providing health facilities is also remarkable. Existing Government hospital are 4 in numbers which meets the needs of the needy persons.
-
There are many commercial establishments however, at some busy places vegetable markets are along road side and needs to be relocated at proper places. There is no organized space for hawkers.
-
In all there are existing 144 gardens, having area 98.87 hectares. Out of which 22 are of bigger size. This works out to be 0.58 sq.m. per person which is less.
-
There are 32 playgrounds having 64.21 hectares area out of which 17 are of bigger size. This includes stadium also. This works out to be 0.38 sq.m. per person which is less.
-
For increasing population, existing facilities of cremation and burial ground is not sufficient.
-
Because of Industrial activity, extent of scrap market is increasing day by day.
-
It is necessary to make provisions for some water works and sewage treatment plant installations for future expansion.
-
Existing fire brigade stations are less in number comparing the spread of the city.
-
Implementation of Development Plan is low which invites re-thinking or paradigm shift in the process of preparation of Development Plan.
-
There is a huge protest by the farmers for reserving their lands in the Development Plan for public purposes.
-
There is no provision for cycle track and moreover, present streets do not facilitate the movements of pedestrians.
-
There are old and historical structures in the city and required to be preserved. Moreover, Nashik being a holy place because of Kumbha Mela, some provisions are to be made for this mammoth fair.