(A). Notice to be given
Every person who intends to erect, or make material alteration in any place in a building shall give notice in writing to the Authority of such intention in Form – A and the notice shall be accompanied by plans and statements in triplicate drawn or prepared in accordance with this Bye-Laws.
(B). Plans Accompanying Notice
Every person giving the notice referred to in Bye-Laws shall submit therewith the following:-
(a) A copy of the title deed of the site, on which the construction or reconstruction is proposed. In case of non-cadastral area only a certificate regarding the ownership of the site from competent Revenue Authority, may be submitted in lieu of the title deed.
(b) Receipt for having paid the application fee to be specified by the Authority.
(c) A site plan in triplicate drawn to appropriate scale and shall show:-
(i) The boundaries of the site with dimensions in metres/ft. Corner angles of the site to be indicated, if they are not 90°.
(ii) The position of the site in relation to neighbouring street(s). The approach road clearly marked on the site plan.
(iii) The exact location of the proposed building on site with dimensions showing distances from the boundary lines at front, rear and sides.
(iv) The name(s) if any of the neighbouring street(s).
(v) All existing building standing on the site together with distance from each other as well as from the proposed building.
(vi) For the sites situated on sloping ground, the slope shall be indicated either with contour lines or spot levels to facilitate convenience for graphical study of drainage pattern of the site.
(vii) The position of rainwater drains, wastewater drains from kitchen and bathroom, the soil pipe from tank to soak pit.
(viii) The Geographical north line.
(ix) The proposed use of the building. If more than one use is proposed a list of such uses together with floor area proposed for each category of use shall be given.
(x) The Authority may specify such other particulars as may be required from time to time.
(xi) Usage of adjacent plots to be mentioned
(d) The plans in triplicate of all floors of the building in mts/ft shall be drawn to scale of not less than 1:100 and will have the name and signature of the applicant. The front elevation and other elevation together with section drawn in the same scale as adopted for plans may also be submitted. The plan shall show:-
(i) All rooms with dimensions and proposed uses of each of them.
(ii) All doors and windows with schedule of openings.
(iii) (a) Water supply and Plumbing Lay-out
(b) Electrical Lay-out
(c) Fire escape
(d) Exact location service e.g. sink, bath and water closet.
(iv) Proposed method of drainage or disposal of rain water, waste water and tank effluent.
(e) For all frame structures, the plan and drawing as per Bye-Laws 4(A) and 4(B) shall be prepared by Architect(s) registered by the Council of Architecture, India. The structural components of such buildings should be designed by a certified structural engineer after conducting the various soil tests and should take into consideration all those loads that are going to act on the building during its life time and carry out the entire necessary test. For such buildings, separate drawing(s) is to be submitted with details of all structural members including foundation and to be signed by the Structural Engineer on Record. The Structural Engineer on Record shall submit a Structural Design Basis Report (SDBR) along with structural design and details.
(C). Form of Application
Every person who gives notice under relevant section of the Act shall furnish all information in forms and format prescribed herein and as may be amended from time to time by the Competent Authority. For multi-storey buildings more than 15 metres height and lifeline buildings even if less than 15 metres height, these provisions shall be made mandatory. The following particulars and documents shall also be submitted along with the application.
*Certificate of Undertaking: Certificate in the prescribed Form No. 1 by the “Owner, Developer, Structural Engineer on Record and Architect on Record”, Form No. 2 by the “Architect on Record / Engineer on Record” and Form No. 3 by the “Structural Engineer on Record”, Form No. 4 by the “Construction Engineer on Record” as pre-scribed in Appendix C.
*( The regulations marked by asterisk under this sub-section may be waived till it is made mandatory at a later stage subject to approval of the State Government as deemed fit)
(D). Documents to be furnished with the Application
(a) The forms, plans, sections and descriptions to be furnished under these Development Control Regulations shall all be signed by each of the following persons:
(i) A person making application for development permission under relevant section of the Act.
(ii) A person who has prepared the plans and sections with description who may be Architect on Record or Engineer on Record
(iii) A person who is responsible for the structural design of the construction i.e., a Structural Engineer on Record.
(iv) *A Construction Engineer on Record who is to look after the day-to-day supervision of the construction
(v) *A Developer, Promoter
(b) *A person who is engaged either to prepare plan or to prepare a structural design and structural report or to supervise the building shall give an undertaking in Form No. 1, Form No. 2, Form No. 3 and Form No. 4 prescribed under these Development Control Regulations.
(c) Approval of drawings and acceptance of any statement, documents, structural report, structural drawings, progress certificate, or building completion certificates shall not discharge the Engineer on Record, Architect on Record, Construction Engineer on Record, Structural Engineer on Record, Developer and Owner from their responsibilities imposed under the Act, the Development Control Regulations and the laws of tort and local Acts.
(d) The landowner shall he held responsible if any Unauthorised Construction, addition & alteration is done without prior permission of Competent Authority.
*(Those regulations marked by asterisk under this sub-section may be waived till it is made mandatory at a later stage subject to approval of the State Government as deemed fit)
5 Requirements of Building Site
No land shall be used as a site for the construction of building
i) If the site is found to be liable to liquefaction by the Competent Authority under the earthquake intensity of the area, except where appropriate protection measures are taken.
ii) If the Competent Authority finds that the proposed development falls in the area liable to storm surge during cyclone, except where protection measures are adopted to pre-vent storm surge damage.
6 Demarcation
The limit of the site shall be demarcated by boundary pillars or wall on the ground and shall be retained on a permanent basis.
7 Notice for Alteration Only
When the notice is only for a material alteration of the building, only such plans and statement as may be necessary shall accompany the notice.
i) The provision of these Bye-Laws shall apply in case where the use of the building is proposed to be changed to wholesale, commercial, godown, industry, and warehouse even if no material alteration of the building is proposed.
ii) Extension or alteration portion should be marked by red ink along with site plan.
8 Repairs
No notice for repairs e.g. plastering, painting, reflooring etc. in an existing building in accordance with bye-laws is required.