6.1 Risk based classification of building applications
There is a need to make provisions for fast-tracking building permission procedures for all non-automatic approvals. Therefore, in the spirit of ‘Ease of Doing Business’, the buildings have been classified further on the basis of risk parameters/ risk-based classification to clear the building permits on fast-track system. This kind of classification shall be used for fast tracking the sanction of building plans, which shall facilitate regulated and faster construction permits, and also aid in improving the rating of the country in World Bank’s assessment in ‘Ease of Doing Business’. Further, the ULB in consultation with all parastatal bodies involved, shall identify riskbased classification of industrial, commercial and institutional buildings and prepare risk-based matrix, in-line with those proposed in Model Building Bye Laws, 2016 for residential and storage buildings/ warehouses/ godown and accordingly prescribe the fast-tracking approval system. This exercise shall be done within a period of 3 months from the date of publication of the Local Building Bye-laws.
On the basis of above-mentioned risk matrix prepared by each of the agencies involved in approving building plans, UT Administration shall design and notify necessary legal instructions to implement risk-based mechanism with a view to fast track building permissions based on their risk classification. These instruments may include, but are not limited to, delegation of powers, out-sourcing, empowering architects, self-certifications, etc. These notifications shall be done within 3 months from the date of notification of risk matrix by each competent authority / agency as mentioned above.
For approval of the residential plotted and group housing buildings, risk-based classification:
(1) For fast-track building plan approval, the competent authority shall approve building plans considering the risk-based classification of buildings depending upon the respective risk matrices as mentioned in Code 6.1 (1) – 6.1 (3)
(2) The application for approval and grant of Occupation Certificate of very-low to moderate risk buildings shall be allowed as per Code 4.2 and relevant sections of Chapter-5. The application for approval and grant of Occupation Certificate of high-risk buildings shall be allowed as per Code 4.1 and relevant sections of Chapter-5.
(3) For building plan approval, the competent authority shall approve building plans considering the risk-based classification of buildings depending upon height and area. Thebuildings are categorized in the following categories:
i. Residential Buildings:
| Risks | Very Low | Low | Moderate | High | |
| Criteria Size of the plot | Parameters Square Meters | Below 105 m2 | 105 - 500 m2 | Above 500 m2 | All sizes |
| Height of the | Meters | <15 m | <15 m | <15 m | 15 m or above |
| building | |||||
| Use of the | Various | Residential | Residential | Residential | Group |
| premises | categories | plotted | plotted | plotted | Housing |
A. Considering no other issue like Monuments, Metro, DUAC, Airports etc. are involved. In case the property lies within the regulated zone of metro rail, airport etc. the online clearance from the local body concerned shall be taken
B. Group Housing area is minimum 2000 sq mt (may vary between States)
C. The Urban Local Body/ Urban Development Authority shall empanel professionals as necessary
D. The Urban Local Body/ Urban Development Authority shall work out and prescribe fees for submitting the building plans
E. The fees shall be derived by an automated built-in calculator in the online system of submission.
Suggested Fast Tracking Tools:
For Very Low Risk Buildings:
In case of standard building plans prepared by the Authority for residential plots up to 105 sq.mt. in size and forming part of the approved layout plan, the owner shall be entitled to sign such standard plans and the required documents for sanction. In such cases, certificate from professionals would not be necessary and the owner shall be bound to follow the approved standard plan in detail. The Authority shall explore options of EWS/LIG/MIG plotted housing schemes to develop pre-approved Standardized building plans of Housing Units for variable plots sizes/carpet area (in the range 30sqm-105sqm). The owner shall undertake construction of the so formed standard housing units.
For Low-Risk Buildings:
A Competent professional (qualification & competence as per Annexure-D) shall be empowered to issue the building permit, but only after submitting the plan along with requisite documents and fees to the concerned local body. If the owner/ professional desires to get the building plan sanctioned by the local body, building plans prepared by a qualified architect/ engineer will have to be submitted to the concerned local body along with the fees and other requisite documents and the local body shall grant the building permit within 10 days.
For Moderate-risk Buildings:
Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
For High-risk Buildings:
Clearance from Fire department, or authority as appointed by UT Administration, and other necessary clearances from AAI, NMA and other agencies have to be obtained. Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
ii. Storage/Warehouse Buildings
For approval of the buildings meant for use as storage buildings/ warehouses/godown, riskbased classification shall be in the following categories:
| Risks | Very Low | Low | Moderate | High |
|---|---|---|---|---|
| Covered area on all floors / Built-up Area | Up to 250 m<sup>2</sup> | 250 - 2000 m<sup>2</sup> | Up to 2000 m<sup>2</sup> | Above 2000 m<sup>2</sup> |
| Height of the building | <15 m | <15 m | <15 m | <15 m |
| Abutting Road width | Min. 12 m | Min. 12 m | Min. 12 m | Min. 12 m |
| Type of Material Storage | Category A | Category A | Category B (Stacking Height -Medium) | Category B (MSetadciukmin)g Height - |
A. The level of Risk is classified according to the material stored in the warehouse/storehouse. Material shall be classified according to the Categories defined in Annexure “C”.
B. The Urban Local Body/ Urban Development Authority shall empanel professionals as per “Annexure D ′ .
C. The building application processing fees shall be derived by an automated built-in calculator in the online system.
Suggested modes of Fast Tracking:
For Very Low Risk Buildings:
A competent professional (qualification & competence as per Annexure-D) shall be empowered to issue the building permit, but only after submitting the plan along with requisite documents and fees to the concerned local body. If the owner/ architect/ engineer desires to get the building plan sanctioned by the local body, he shall apply online to the local body and the local body shall grant the building permit within 10 days.
For Low-Risk Buildings:
Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
For Moderate Risk Buildings:
Building plans will have to be prepared by a competent professional and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local body shall grant the building permit within 20 days.
For High-Risk Buildings:
Building plans will have to be prepared by a qualified architect and the building plans will have to be submitted to the concerned local body along with the fees and other requisite documents. The local
body shall grant the building permit within 30 days.
iii. Industrial Buildings
For approval of the buildings meant for use as storage buildings/ warehouses/godowns, riskbased classification
| Risks | Low | Moderate | High | |
|---|---|---|---|---|
| Criteria | Parameters | |||
| Size of the plot | Square Meters | Up to 350 m<sup>2</sup> | Above 350 m<sup>2</sup> | All sizes |
| Height of the building | Meters | Less than 15 m | Less than 15 m | 15 m and above |
| Abutting Road width | Meters | Min. 12 m | Min. 12 m | Min. 12 m |
A. The level of Risk is classified according the size and height of the industrial building proposed.
B. The Urban Local Body/ Urban Development Authority shall empanel professionals as per “Annexure D”.
C. The building application processing fees shall be derived by an automated built-in calculator in the online system.
Suggested modes of Fast Tracking:
For Low-Risk Buildings:
-
Deemed Approval with Self-Certification
-
Plans to be submitted along with Structural drawings which does not require sanction
For Moderate-Risk Buildings:
-
Plans to be submitted to the empaneled professional.
-
Fire/Structural safety certification by Fire Services/ Structural Engineers
-
Approval to be granted within 10 working days by the empaneled professional.
-
Approved plan to be submitted to ULB/DA.
For High-Risk Buildings:
-
Online application
-
Immediate acknowledgement by software
-
Fire/Structural safety certification by Fire Services/ Structural Engineers
-
Approval by ULB/DA within 20 working days.