(a) Any person who intends to erect, re-erect or make alternation in a building or demolish any building shall give notice in writing to the competent authority in the Form BC-I, accompanied by the following documents:
i. Ownership documents-lease deed/sale deed, proof of ownership certified by the revenue authority (Jamabandi) in the case of self-owned property and in the case of a plot allotted by the authority copy of the allotment letter and of the possession letter in the name of owner issued by the allotment authority, and a copy of the letter in the case where permission to use the land for the intended purpose issued by the competent authority,
ii. Every person who intends to erect, re-erect or make alternation in any place in a building or demolish any building shall give notice in writing to the Authority of his intention in the prescribed Form BC-I, as per Annexure – A and such notice shall be accompanied by plans and statements in sufficient copies. The plans may be ordinary prints on ferro-paper or any other type, one set of which shall be laminated. One set of such plans shall be released, and the rest retained in the office of the Authority for record after the issue of permit or refusal as the case may be.
iii. Online portal for auto-scrutiny shall always require upload of the recommended digital format of the drawings to be uploaded on the portal for use; the provision of submission, of drawings and auto-scrutiny shall be formulated by UT Administration/Local bodies or any such bodies as appointed by UT Administration/Local bodies and shall have the purview of the same. These may include but not be limited to built features, coverage and features, coverages, setbacks, provisions for universal design, parking, mezzanine, building distances, heights, chimneys, parapets, mumties, fire management, exemptions, green rating applications, access, etc.
iv. a site plan as required under these Building Bye-Laws Section 3.122,
v. details of specifications of the work to be executed in Form BC-II,
vi. Structural drawings, for record, as per Form BC-V(A1) or BC-V(A2),
vii. Fire safety design as required under Part IV of the National Building Code and as updated/revised from time to time in the case of buildings more than 15 meters in height and all non-residential buildings.
viii. Heating, ventilation, air-conditioning (H.V.A.C.) service plan wherever required,
ix. Plumbing drawings, water supply drawings and toilet drawings
x. Certificate of conformity with these Bye-Laws and structural safety for the relevant buildings (depending upon type and height) in the relevant Form BC- V(A1) or BC-V(A2),
xi. Public health services plan in un-editable compact disc/DVD or any
other electronic medium, containing drawings in “DWG” Format,
xii. A person applying for permission to carry out any development shall have to pay tree plantation deposit along with his application to the Competent Authority at the rates decided by the Competent Authority time to time. This deposit shall be refundable after the period of five years with the condition that trees planted on the site shall be grown‐up and maintained properly, otherwise the deposit shall be forfeited and shall be utilized only for tree plantation and maintenance by the Competent Authority.
xiii. Scrutiny fees (nonrefundable) at the rate of ten (10) rupees per square meter for the proposed aggregated construction area to be achieved including basement, stilt floor, service floor and mezzanine, to be deposited in favour of the competent authority through any prescribed payment mode.
xiv. No objection certificate from the Authority regarding land use as per Master/Zonal Plan, if required.
xv. Approval from the Chief Inspector of Factories in case of Industrial Buildings; as well as from the Pollution Control Board, wherever required
xvi. Approval from Chief Controller of Explosives in case of Industrial Buildings; as well as from the Pollution Control Board, wherever required
xvii.Indemnity Bond in case of proposal for the construction of a basement as given in Annexure – ‘B-1’
xviii. Approval from Chief Fire Officer, or any other authority as appointed by UT Administration, in case of building defined under Code 3.22 shall be required
xix. No-objection certificate from Civil Aviation Department wherever required by competent authority
xx. No-objection certificate from relevant Defense Authority, wherever required by competent authority
xxi. In case the site falls in the built-up area declared as slum under any Act NOC from the Competent Authority, from slum clearance and land use points of view.
xxii.In case the application is for a Farmhouse, Motel, approval/NOC from the Competent Authority from land acquisition point of view.
xxiii. In case of the leasehold plots, clearance from the lessor with regard to the lease conditions shall be obtained wherever required.
xxiv. For individual plot, wherever required, approval of the site from the Competent Authority, if not the part of already approved layout plan.
xxv. Site plan for all the authorities, and details as required by the approval authority
xxvi. Any other information/document, which the Authority may require in case of listed buildings or otherwise.
Other documents to be submitted in special cases shall be as follows:
i. For projects proposed within the Prohibited and Regulated areas as defined by AMASR Act 2010, permission /NOC from Competent Authority (NMA) shall have to be obtained as per Rules 2011 framed under the Act by submission of required documents as per rules.
ii. Additional documents required for conservation of Heritage sites including Heritage Buildings, Heritage/Precincts and Natural Features Areas (wherever required)
Note: The applicant shall submit all kinds of plans in electronic format of online portal of the competent authority. The competent authority shall convey objections/observations or sanction/refusal through online portal and or other prescribed mode.
(b)Every person applying under Code 4.1 shall appoint an architect/engineer for drawing up of building plans/structural drawings and for the supervision of erection or re-erection of the building.
(c)The supervision of erection or re-erection of residential or commercial buildings up to 9 meters height (G+2 floors including stilt floor) may be undertaken by the architect or the engineer. In case of buildings more than 9 meters in height, including stilt floor, the supervision shall be undertaken both by the architect and the engineer. In case of buildings in notified heritage zone, ecologicallyconservation zone, special protection zones, or as mentioned in Development Control Regulations and Master Plan, as well as for plots facing arterial, subarterial and collector roads, licensed architects need to approve designs, undertake feasibility study, and provide inputs regarding specific design interventions, and approval.
(d)During construction if appointed architect/engineer notices that violation(s), except compoundable, are continuing shall intimate the owner and advise him to stop further construction and rectify the violations and shall also intimate to the concernedauthority.
(e)The applicant, the architect and engineer shall digitally sign the application, plans, structural drawings, specifications, and the certificates as required in the relevant forms and documents, before making submission to the Competent Authority.