Where any building permit which has been issued by the Competent Authority before the commencement of this Code and where construction is in progress and has not been completed within the specified period from the date of such approval, the said permission shall be deemed to be sanctioned under this Code and shall only be eligible for revalidation thereunder. Accordingly, where the validity of sanction has expired and construction has not commenced, construction shall be governed by the provisions of this Building Code.
89[Annexure “B” – Standard Affidavit
I son/daughter/wife ….., applied for building plan approval/ DPC Level/ occupation certificate vide application dated… on Form BR………………….., and resident of …… …., hereby solemnly state & affirm as under:
That I shall not use basement as habitable space, as the same has not been included in the FAR and has not been shown as habitable space in the approved plans.
That I shall use the building only for the purpose for which approval and occupation certificate has been obtained.
That I shall comply with all the condition(s) implied by the competent authority at the time of approval of building Plan and Occupation certificate.
That ……… ….(condition/ indemnity/ affirmity required by the Competent Authority)-I.
That … ….(condition/ indemnity/ affirmity required by the Competent Authority)-II.
That … ….(condition/ indemnity/ affirmity required by the Competent Authority)-III.
Place: Date:
DEPONENT
Verification
I son/daughter/wife applied for building plan approval/ DPC Level/ occupation certificate vide application dated… on Form BR…… and resident of … …., hereby verify and affirm that the contents of this affidavit are true and correct to the best of my knowledge, belief and information in witness whereof I have signed hereunder on day of
Place: Date:
DEPONENT]
89 Inserted/amended vide memo no. Misc-138A-Loose/7/5/2006-2TCP dated 22.12.2017
[116]
92[ Form BR-I
[See Code 2.1(1)] Application for erection/re-erection of Building(s) (Other than building(s) applied under self-certification)
From
Sir,
I/We apply for permission to erect/re-erect/add/alter a building/wall in accordance with the plans submitted herewith on Site no. ; Street no. at /Khasra no. Village (strike out whichever is not applicable)
i. I/We attach:
a. Site plan (in triplicate) showing the position of site proposed to be built upon as required by the Code along with an un-editable Compact Disc/DVD or any other electronic medium permissible by competent authority from time to time containing the drawings so submitted;
b. Plans, elevations and sections (in triplicate) as required by the Code along with an un-editable compact Disc/DVD or any, other electronic medium permissible by competent authority from time to time containing the drawings so submitted;
c. Drainage plans (in triplicate), as required by Code along with an un-editable compact Disc/DVD or any, other electronic medium permissible by competent authority from time to time containing the drawings so submitted;
d. Structural drawings (for record) signed by the empanelled Structural Engineer and/ or Proof Consultant/ Geo-Technical Engineer, in original, as per Form BR-V(A1)/ BR-V(A(2), as may be applicable, alongwith complete list of such drawings, certified by all concerned, i.e. structural engineer and proof consultant, in A3 size.
93[dd. Proof regarding registration on Dust portal in case of plots measuring 500 sq m and above falling in National Capital Region (NCR) as per jurisdiction specified by Commission for Air Quality Management (CAQM), from time to time.]
e. Specifications of the proposed building (in triplicate) in Form BR-II;
f. Certificate of conformity to regulation and structural safety for the relevant buildings (depending upon type and height) in Form BR-V(A1) or BR-V(A2); and
g. Receipt of Scrutiny fee @ Rs. 10 per square metre deposited online on Department Portal
92Substituted vide memo no. Misc-720/2024/7/16/2024-TCP dated 25.07.2024
93Inserted vide memo no. Misc-2339-ULB-Vol-I/7/8/2025-2TCP dated 12.05.2025
[124]
h. In case of revision of building plans, the reasons on account of which such changes are being proposed to be specified as follows:
Tick mark whichever applicable
Reason for revision
Specify Block/Tower/Phase of such revision
Specify Area (in Sqm.) under corresponding Block/Tower/ Phase proposed for revision
Additional FAR on account of utilisation of Transferrable Development Rights Certificate
Additional FAR on account of Purchasable Development Rights
Additional FAR on account of TOD
Additional FAR on account of Green rating/ incentives
Additional FAR on account of installation of Solid Waste Management plant
Additional FAR on account of installation of solar photovoltaic power plant
On account of the following in respect of licence(s) issued under Act of 1975:-
(i) Grant of licence for additional land.
(ii) Migration of part licenced land.
(iii) De-licence of part licenced land.
(iv) Surrender of part licenced land.
Any other, specify
I/ We hereby undertake that the proposed revision of building plans is limited to the extent as indicated above and no parameter other than above is proposed or intended for revision.
ii. The construction of the building will be undertaken as per the approved building plans, Structural design and specifications as submitted by the Engineer/ Structural Engineer/Proof Consultant/Geo Technical Engineer, as applicable.
iii. The construction of the building will be got supervised through the following Architect/ Engineer/ Supervising Engineer, whichever applicable:
[125]
A.
Class of Building
Tick whichever applicable
1.
Residential
1.1.
Residential Plotted
1.1.a.
Upto 1000 sqmts and 16.5 mts height
1.1.b.
Above 1000 sqmts upto 16.5 mts
1.2.
Residential (other than plotted)
1.2.a.
Upto 1000 sqmts and 15 mts height
1.2.b.
Above 1000 sqmts upto 15 mts
1.2.c.
Above 15 mts.
2.
Commercial
2.1.
Upto 1000 sqmts and 15 mts height
2.2.
Above 1001-2000 sqm upto 15 mts height
2.3.
Above 2000 sqm upto 15 mts height
2.4.
Above 15 mts.
3.
Industrial/IT/ITES
4.
Warehousing
5.
Educational
6.
Institutional
7.
Any other, please specify
B. Technical Persons (Whichever applicable)
FOR DESIGN
(I) Architect (For all classes of buildings)i. Name:ii. Council of Architecture Registration No. ____, valid upto ____iii. Complete Addressiv. E-Mailv. Mobile no.
(II) Engineer (For 1.1.a, 1.2.a & 2.1):i. Name:ii. Qualifications:iii. Complete Addressiv. E-Mailv. Mobile no.
(IV) Empanelled Proof Consultant (For 1.1.b, 1.2.b, 1.2.c, 2.3, 2.4, 3, 4, 5, 6)i. Name :ii. Qualifications:iii. Department TPR No.iv. Complete Addressv. E-Mailvi. Mobile no.
(V) Empanelled Geo-technical Engineer (For evaluation of all classes of buildings with height more than 70 m)i. Name :ii. Qualifications:iii. Department TPR No.iv. Complete Addressv. E-Mailvi. Mobile no.
FOR SUPERVISION
(VI) Architect (For all classes of buildings)i. Name:ii. Council of Architecture Registration No. ____, valid uptoiii. Complete Addressiv. E-Mailv. Mobile no.
The materials to be used in the construction to be clearly specified under the following heads:-
Items
Specifications
(a) Foundations
(b) Walls
(c) Damp-proof course
(d) Floors
(e) Roofs
(f) Windows and Doors and other wood-work
(g) Steel work
(h) Internal finish
(i) External finish.
Signature of applicant
(No digital signatures are required)
Signature of Architect/Engineer
i. Complete Address
ii. E-Mail
iii. Mobile no.
[128]
94[FORM BR-V (A1)
(See code 1.2(1)(lxxi), (lxxxv), 2.1(1)(vii))
Certificate of conformity to Code and structural safety for Residential and Commercial Buildings upto 15 metres height.
Certificate to be submitted along with the building application in Form BR-1 duly signed by the Architect and the Structural Engineer.
Details of the building for which the certificate is issued
Plot No. , Sector , Colony
City/Town
Name of the owner
Complete address of the owner
A. Building Plan :
i. Name of Architect:
ii. Council of Architecture Registration No. ____, valid up to
iii. Complete Address
iv. E-Mail
v. Mobile no.
[129]
B. Structural Design:
i. Name of Engineer:
ii. Qualifications:
iii. Complete Address
iv. E-Mail
v. Mobile no.
Certificate
It is hereby certified that the plans submitted in Form BR-I alongwith duly signed Structural drawings (for record) as per the counter signed list enclosed with this form, are in accordance with the Haryana Building Code-2017 and the approved zoning plan of the plot. The structure has been designed in accordance with the provisions of the National Building Code and the relevant Indian Standard Code (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated
Signature of Owner
(See Code 4.2(4)) Form of Sanction
From
To
Memo No.
Dated the ………
Reference you application for permission to erect/re-erect-add to/alter a building on plot No. / Khasra no. _, Village in accordance with the plans submitted with it.
Permission is hereby-
(i) granted/sanctioned for the aforesaid construction subject to the provisions of the respective Acts and Haryana Building Code -2017 subject to the following amendments, terms and conditions;
(ii) rejected for reasons given below :-
Enclosures
Competent Authority
[134]
13.2Power of relaxation
The Government may relax any restrictions or conditions or norms stated in the Code or may issue direction to revise the Code, if the relaxation or revision is in public interest at large.
[112]
88[Appendix “A”:
Qualification and Competence of Architect/ Engineer/ Supervising Engineer/ Structural Engineer/ Proof Consultant/ Supervisor/ Geotechnical Engineer.
Sr.No.
Professional
Qualification
Competency/ Functions
1
Architect
Registered with valid membership of the Council of Architecture, India as prescribed under the Architect's Act 1972.
Prepare, sign all plans and submissions of building plans under Code 4 Further supervise construction of allbuildings and issue certificate of supervision and completion of all buildings pertaining to Architectural aspects, as stated in this code.
2
Engineer
Graduate in Civil Engineering from recognized Indian or foreign university, having Associate membership of The Institution of Engineers (India) including Architectural Engineer as specified in clause A-2.2, Annex A of Part 2 Administration of National Building Code-2016.
Supervise all building construction including preparation of service plans, structural drawings, details and calculations of buildings upto 1000 square metres plot area and 15.0 metres height referred in Form BRV(A1).
3
Supervising Engineer
Graduate in Civil Engineering from recognized Indian or foreign university, having Associate membership of The Institution of Engineers (India), with minimum three years of experience.
Supervise all building construction and issue certificate of supervision and completion of all buildings pertaining to structural aspects, as stated in this code.
4
Structural Engineer
Post-Graduate in Structural engineering from recognized Indian or Foreign University, having Associate membership of
The Structural Engineer shall be competent to prepare the structural design, make calculations and design
88Substituted vide memo no.Misc-2339-Loose-ULB-7/19/2023-2TCP dated 04.12.2023
[113]
Institute of Engineer, India with minimum three years experience in structural engineering practice with designing and field work.
details for all buildings referred in Form BR-V(A2).
5
Proof Consultant i i
i. Structural Engineer or a group/ firm of Structural Engineers having post-graduate qualification in structural engineering, having Associate membership of Institute of Engineer, India with ten years experience in structural design and evaluation thereof, for multi-storeyed and specialized structure, and/ or an institute of the following type: ii. Institute of Structural Engineers (India). ii. Central Building Research Institute, Roorkee. v. Various engineering institutes, like: a) Indian Institute of Technology; b) Punjab Engineering College, Chandigarh; c) National Institute of Technology; d) Any other institute of repute;
Evaluation/ checking of the structural design of the buildings referred in relevant Form BR-V(A2).
6
Supervisor
i. Two years diploma in Draftsman Civil with seven years experience under a qualified Architect/Civil Engineer for building design, construction and supervision; or ii. Three years diploma in Civil
To prepare, sign and submit building plans and supervise construction of building upto 200 Sqm (8 marla) and 15 mtr. Height, under Code 4. The Supervisor shall get his/her empanelment renewed annually for the first 2 years and it shall be
[114]
Engineering/Architectu ral Assistantship with five years experience under a qualified Architect/Civil Engineer for building design, construction and supervision; or iii) iii. B.Tech Civil, B.Tech (Building Engineering Management or equivalent);
renewed for a period of 3 years thereafter.
7
Geotechnical Engineer
Post graduate in geotechnical engineering with minimum 10 year experience in geotechnical engineering practice in designing and field work. or Doctorate in civil engineering or geotechnical engineering with minimum 5 year experience in geotechnical engineering practice in designing and field work.
Evaluation/checking of the design of the buildings above 70 m height as mentioned in BR-V (A2)
“Note: Any post graduate qualification with at least 50% of the subjects relating to Structural Engineering (by credit), including research thesis, shall also be treated at par with Post Graduate in Structural Engineering. ”]
[115]
96[FORM BR-IV (A) omitted ] 97[FORM BRS(TP)-III [See Code 4.10(1)] For all High Risk Category Buildings Application for permission to occupy
From
To
Sir,
I/We hereby give you notice that the building/part of building described below and sanctioned vide order No. , dated , has been completed on in all respect according to the sanctioned plans and the structural design made for the same and suggested medications have been carried out.
Description of Building
Plot No./khasra no., whichever applicable
Block/Street No., if applicable
Sector, if applicable
City / Name of Revenue Estate, whichever applicable
District
Licence no. and date of grant of licence / Colony Name, if applicable
Validity of building plans
Period of project completion
Name of the owner alongwith mob. No. and Email_
Complete address of the owner
The modifications made to the building plans and carried out at site during the course of construction are submitted herewith:
Corresponding to the above modifications made in the building plans, the necessary amendments were also carried out in the structural design and implemented a site.
Completion certificate from the architect/empanelled engineer who supervised the construction of the building is submitted herewith.
The following documents are also duly enclosed with the application:-
96Omitted vide memo no. Misc-2339-ULB-Vol-I/7/8/2025-2TCP dated 08.12.2025
97Substituted vide memo no. Misc-2339-ULB-Vol-I/7/8/2025-2TCP dated 08.12.2025
[135]
i. Detail of compoundable violations from the approved building plans, if any in the building, jointly signed by the owner, Architect and Engineer Supervising Construction at Site along with documentary evidence regarding due payment for composition charges of such violations at the rates determined by the Competent Authority shall be submitted along with Form BRS(TP)-III.
ii. Complete Completion drawings or as-built drawings along with completion certificate from Architect as per BRS-VI.
iii. Photographs of front, side, rear setbacks, front and rear elevation of the building shall be submitted along with photographs of essential areas like cut Sir, Plot No./khasra no., whichever applicable Block/Street No., if applicable Sector, if applicable City / Name of Revenue Estate, whichever applicable District Licence no. and date of grant of licence / Colony Name, if applicable Validity of building plans Period of project completion 8 outs and shafts from the roof top. An un-editable compact disc/ DVD/ any other electronic media containing all photographs shall also be submitted.
iv. Completion certificate from Bureau of Energy Efficiency (BEE)Certified Energy Auditor for installation of Rooftop Solar Photo Voltaic Power Plant in accordance to orders/ policies issued by the Renewable Energy Department from time to time.
v. Completion Certificate from HAREDA or Bureau of Energy Efficiency (BEE) Certified Energy Auditor for constructing building in accordance to the provision of ECBC, wherever applicable.
vi. No Objection Certificate (NOC) of fire safety of building from concerned Chief Fire Officer or an officer authorized for the purpose.
vii. A certification from Third Party empanelled Structural Engineer and Proof Consultant (wherever applicable) (other than the Structural Engineer/Proof Consultant involved in designing, construction and supervision of the building) in Form BRS-IVA that the building has been inspected in all respect and no provision of the Haryana Building Code, 2017 and structural safety codes/standards has been violated excluding compoundable violations.
viii. No Dues Certificate issued by Competent Authority specifying that there are no outstanding dues against the proponent in the project as well as documentary evidence regarding validity of the permission.
Kindly issue an occupation certificate as required by Haryana Building Code -2017.
Dated
Signature of applicant
(No digital signatures are required)
Signature of
i) Architect:
a. Complete Address
b. E-Mail
c. Mobile no.
ii) Empanelled Engineer supervising the construction at site a. Complete Address b. E-Mail c. Mobile no.”
[136]
90[Annexure “C” – Standard report format for Single Joint Inspection.
I. Inspection report Format for Pre-Construction Stage (to be conducted within 1-2 week of submission of building plan application/ self certification:
Name of applicant:.........................
Address of site/ building Plot no. .......... Khasra no............... Sector/ area........... Colony..............
Application no.:.............
Geo-coordinates of site: Lat/ Long points: (as many required to survey the site)
Area of site:....................... (in square metres)
Building use type: Residential Commercial Industrial Institutional Any other.
Name of Department
Appointed Nodal Officer for joint inspection
Inspection details
Inspection parameters
Sign of Nodal officer
Urban Local Bodies
District Town Planner/Building Inspector/Engineer
Site inspection w.r.t site dimension, area, etc.
Area of site Site dimensions along with Geo-coordinates. Physical features. Applicability of Acts on site/ HT line/ Gas line, etc.
HSIIDC
To be appointed by the Corporation.
Temporary Water Connection
Water Connection inspection
Town and Country Planning Dept.
District Town Planner
Site inspection w.r.t site dimension, area, etc.
Area of site Site dimensions along with Geo-coordinates. Physical features. Applicability of Acts on site/ HT line/ Gas line, etc.
90 Inserted/amended vide memo no. Misc-138A-Loose/7/5/2006-2TCP dated 22.12.2017
[117]
Forest Department
To be appointed by the Department.
Inspection for any acquisition or grabbing of forest land or any cutting of marked trees.
As per Department requirement.
Inspection report Format for During-Construction Stage (to be conducted within 1 week of submission of self certified DPC level certificate:
Name of applicant:.........................
Address of site/ building Plot no. .......... Khasra no............... Sector/ area........... Colony..............
Application no.:.............
Area of site:....................... (in square metres)
Building use type: Residential Commercial Industrial Institutional Any other.
Name of Department
Appointed Nodal Officer for joint inspection
Inspection details
Inspection parameters
Sign of Nodal officer
Labour Department
Joint Director/Deputy Director/Assistant Director
Cess Assessment inspection
As per Department requirement
Urban Local Bodies
District Town Planner/Building Inspector/Engineer
DPC level inspection
Inspection at DPC level of building w.r.t approved building plan.
Town and Country Planning Dept.
District Town Planner
DPC level inspection
Inspection at DPC level of building w.r.t approved building plan.
HUDA
Junior Engineer
Inspection for temporary Water connection (only new construction) DPC level inspection (only new construction).
As per Authority requirement.
UHBVN
Concerned
Inspection for
As per
[118]
SDO/ OP
Temporary Electricity Connection
Department requirement.
III. Inspection report Format for Pre-Construction Stage (to be conducted within 1-2 weeks of submission of building plan application/ self certification:
Name of applicant:.........................
Address of site/ building Plot no. .......... Khasra no............... Sector/ area........... Colony..............
Application no.:.............
Area of site:....................... (in square metres)
Building use type: Residential Commercial Industrial Institutional Any other.
Name of Department
Appointed Nodal Officer for joint inspection
Inspection details
Inspection parameters
Sign of Nodal officer
Labour Department
Joint Director/Deputy Director/Assistant Director
Inspection at time of completion of construction. In case of start of manufacturing in factory (Manufacturing)
As per Departm ent requirem ent
Fire Department
Fire Officer
Site inspection for Fire Safety norms and fixtures after completion of building
As per Department requiremen t
Urban Local Bodies
District Town Planner/Building Inspector/Engineer
Inspection for Occupation certificate to check that the building has been constructed as per approved plan or not Site inspection for public health services.
Site inspectio n for OC. Site inspectio n of health services
HSIIDC
To be appointed by the Corporation
Inspection for Occupation certificate to check that the building has been constructed as per approved plan or
As per Corporatio n requiremen t.
[119]
not■ Sewerage Connection
Town and Country Planning Dept.
District Town Planner/ Engineer
■ Inspection for Occupation certificate to check that the building has been constructed as per approved plan or not■ Site inspection for public health services.
■ Site inspection for OC.■ Site inspection of health services
Public Health Engineering Department
To be appointed by the Dept.
■ Inspection for potable water connection
As per Department requirement t.
PWD (B & R)
To be appointed by the Dept.
■ Inspection at the time of road cutting for laying of services like water, sewerage line, etc.
As per Department requirement t.
Pollution Control Board
To be appointed by the Board.
■ Inspection at the time manufacturing of products
As per Board requirement t.
HUDA
Junior Engineer
■ Inspection for Permanent Water connection (only new construction)■ Inspection for Occupation certificate to check that the building has been constructed as per approved plan or not.
As per Authority requirement t.
UHBVN
Concerned SDO/ OP
Inspection for Permanent Electricity Connection
As per Department requirement t.
Chief Electrical Inspector, Power Department
Concerned District Electrical Inspection
Inspection for granting NOC for installation of electrical connection and fixtures
As per Department requirement t.
HAREDA
To be appointed by the Dept.
■ Inspection for ECBC compliance.■ Inspection for solar related installation.
As per Department requirement t.]
[120]
91[Annexure-D
Transit Oriented Development (as per the policy dated 09.02.2016, as amended from time to time)
TOD Zone
Maximum Permissible Ground Coverage
Maximum Permissible FAR
Minimum/Maximum Density (Persons Per Acre)
Parking norms - based on the carpet area* of the additional FAR availed
Multi storeyed Group Housing
Intense
40%
3.5
600(±10%)
Upto 100 sqm-0.5 ECS • Between 100 sq. mtr. to 150 sq. mtrs.- 1.0 ECS • More than 150 sq.mtrs.-1.5 ECS Size of ECS (Equivalent Car Space):- (i) 1 ECS = 23 sq. mts. for open parking. (ii) 1 ECS = 28 sq. mts. for stilt parking (iii) 1 ECS = 32 sq. m
Transition
40%
2.5
430(±10%)
Integrated Commercial/ Office spaces/ mixed land use
Intense
60%
3.5
-
Transition
60%
2.5
-
IT/ITes
Intese
40%
3.5
-
Transition
40%
3.0
-
For the purpose of calculation of parking, the definition of Carpet Area as mentioned in the policy dated 09.02.2016, as amended from time to time, shall be followed.
Affordable Group Housing (as per the policy dated 19.08.2013, as amended from time to time)
Density
Maximum Permissible FAR (Residential Component)
Maximum permissibl e Ground Coverage
Minimum are under organized Green spaces
Commercial component
Parking Norms
Maximum NPA permissible
Max permissi ble FAR
750- 900(persons per acre)
225
50%
15% of Net Planned Area (NPA)
8%
175
Mandatory nonchargeable 0.5 ECS for each Dwelling Unit (0.8m X 2.5m) Optional and chargeable parking space at the extent of 0.5 ECS for each Dwelling Unit. The
91Inserted vide memo no. Misc-2339-ULB-C/7/5/2006-2TCP dated 18.10.2022
[121]
balance available parking space, if any, beyond the allocated two-wheeler parking sites, can be earmarked as freevisitor-car-parking space.
Maximum FAR and Density to be permitted with TDR(as per the policy dated 19.08.2013, as amended from time to time)
Sr. NO.
Type of Colony/ Site Project
Applicable FAR
Applicable Density (persons per acre)
Maximum permissible FAR with TDR
Maximum Density (persons per acre with TDR)
1.
GH
1.50/1.75
300-400
3.0
Existing + 200
2.
AGH
2.25
750-900
3.0
Existing + 175
3.
HDGH
1.75
450
3.0
Existing + 200
4.
TOD-GH
3.5/2.5
600/430(±10%)
5.0/4.0
Existing+ 150
5.
CL
1.75
NA
3.0
NA
6.
TOD-CL
3.5/2.5
NA
5.0/4.0
NA
7.
NILP-CL
3.0
NA
4.5
NA
8.
MLU
1.75
80
3.0
Existing +70
9.
TOD-MLU
3.5/2.5
NA
5.0/4.0
NA
10.
NILP-R
1.25
300
2.5
Existing + 125
11.
CP/CC
2.5
NA
5.0
NA
12.
TOD-IT/ITES
3.0/3.5
NA
4.5/5.0
NA
13.
IIILP-IND
1.0
NA
2.0
NA
14.
CS/I-CLU
1.0/1.5
NA
2.0
NA
15.
Res. Plot
1.0 to 1.65
18
2.4/2.64 (as applicable)
Co change
Notations: 1. GH=Group Housing Components (1.5/1.75 FAR) in such colonies where permitted, except NILP; 2. AGH=Affordable Group Housing Component in all such colonies where permitted as per the Policy dated 19.08.2013, as amended from time to time 3. HDGH=High Density Group Housing Project as provided in development plan 4. TOD-GH=Group Housing Licence under TOD as per the Policy dated 09.02.2016, as amended from time to time 5. CL=Commercial Components in all colonies where permitted or Commercial CLU projects; 6. TOD-CL= Commercial Licenced Colony under TOD Policy dated 09.02.2016, as amended from time to time 7. NILP-CL= Commercial Licence granted under the NILP Policy dated 26.10.2015 as amended from time to time 8. MLU= Mixed Land Use Licence granted under policy dated 03.01.2014, as amended from time to time 9. TOD-MLU= Mixed Land Use Project under TOD Policy dated 09.02.2016, as amended
from time to time
10.
NILP=Residential Licence granted under New Integrated Licencing Policy dated 09.02.2016, as amended from time to time
11.
CP/CC/ IT-ITES= Cyber Park/Cyber city/ IT or ITES Units
12.
TOD-IT/ITES= IT/ITES Project under TOD Policy dated 09.02.2016, as amended from time to time.
13.
IILP-IND=Industrial Component under IILP policy dated 11.10.2017, as amended from time to time
14.
CS=Community Sites in licenced colonies
15.
I-CLU= CLU Projects for Institutional Use
16.
Res. Plot= Residential Plot in a Residential Plotted colony
Note: The word ‘colony’ shall be as defined in the Act No. 8 of 1975. Further, the parameters as above shall be applicable on the specified use irrespective of such use being either the main use or and ancillary use unless specifically excluded to such effect. For example, the group housing parameters shall be applicable to the group housing components availed either in a group housing colony or in a Cyber City or in an Industrial colony and so on, except group housing components in a NILP projects for which the parameters are separately specified.]
[123]
98[FORMS BR-V (1) and BR-V (2) omitted ]
99[FORM BRS-VI (See Code 4.10(1)(ii)) Completion Certificate by an Architect
I do hereby certify-
i) that the following work has been supervised by me and has been completed to my satisfaction in accordance with the sanctioned plan.
ii) that no deviation from sanctioned plan is made while constructing the building/ deviation from sanction plan is made (details as below) and these deviations are duly shown on completion drawings. Due to these deviations, human safety has not been compromised (strike off whichever is not applicable).
iii) that the workmanship and the whole of the materials used are good; that no provision of the Haryana Building Code, 2017 and no requisition made, conditions prescribed or order issued there under has been violated in the course of the work.
Details of construction on (floor-wise along with covered area on each floor)
City Street
Plot No. House No. (if any) (or)
Khasra no. _, Village
Dated
Signature of Architect
i. Complete Address
ii. E-Mail
iii. Mobile no.]
98Omitted vide memo no. MISC-2339-ULB-Vol-I/7/8/2025-2TCP dated 08.12.2025
99Renamed vide memo no. MISC-2339-ULB-Vol-I/7/8/2025-2TCP dated 08.12.2025
[137]
(No digital signatures are
Signature of Architect
Signature of Engineer/
required)
Structural Engineer
Mobile no.
E-mail
94Substituted vide memo no. MISC-720/2024/7/16/2024-TCP dated 25.07.2024
Enclosure to FORM BR-V (A1)
STRUCTURAL DRAWINGS : List of Plans being submitted in accordance with the Structural Design.
2...
[130]
95[FORM BR-V (A2)
[See code 2.1 (1) (viii)]
Certificate of conformity to rules and structural safety for all buildings except as stated in Form BR-V(A1)
Certificate to be submitted along with the building application in Form BR-I duly signed by the Architect and Empanelled Structural Engineer, Empanelled Proof Consultant and Empanelled Geo-Technical Engineer, if applicable.
Details of the building for which the certificate is issued
Plot No. , Sector , Colony
City/Town
Name of the owner __ _.
Complete address of the owner
A. Building Plans:
i. Name of Architect:
ii. Council of Architecture Registration No. ____, valid upto
iii. Complete Address
iv. E-Mail
v. Mobile no.
B. Structural Design
(a) Empanelled Structural Engineer:
i. Name:
ii. Qualifications:
iii. Department TPR No.
iv. Complete Address
v. E-Mail
vi. Mobile no
(b). Empanelled Proof Consultant, if applicable:
i. Name:
ii. Qualifications:
iii. Department TPR No.
iv. Complete Address
v. E-Mail
vi. Mobile no.
(c). Empanelled Geo-technical Engineer, if applicable:
i. Name :
[131]
95 Substituted vide memo no. MISC-720/2024/7/16/2024-TCP dated 25.07.2024
ii. Qualifications:
iii. Department TPR No.
iv. Complete Address
v. E-Mail
vi. Mobile no.
Certificate
It is hereby certified that the plans submitted in Form BR-1 the building detailed above, are in accordance with the Code and the approved zoning plan of the plot. The structure has been designed in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated
Signature of Owner (No digital signatures are required) Mobile no. E-mail
Signature of Architect
Signature of Empanelled Structural Engineer
The structural design as per the duly signed Structural drawings (for record) mentioned in the countersigned list enclosed with this form, has been checked and has been found to be in order. The design is in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated
Signature of Empanelled Proof Consultant along with Mob. No. & E-mail
The structural design of the buildings above 70 m height, as per the duly signed Structural drawings (for record) mentioned in the countersigned list enclosed with this form, has been checked and has been found to be in order. The design is in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated
Signature of Empanelled Geo-Technical Engineer Enclosure to FORalong with Mob. No. & E-mail
[132]
Enclosure to FORM BR-V (A2)
STRUCTURAL DRAWINGS: List of Plans being submitted in accordance with the Structural Design.
100[FORM BRS-VII (See Code 4.10(2), (4) and (5)) Form of Occupation Certificate for High Risk Category
From
To
Memo No…….
Dated …
Whereas Shri/ Smt/ M/s ………………….., R/o …………….. has applied for the issue of an occupation certificate in respect of the building described below:-
Plot No./khasra no., whichever applicable
Block/Street No., if applicable
Sector, if applicable
City / Name of Revenue Estate, whichever applicable
District
Licence no. and date of grant of licence / Colony Name, if applicable
Validity of building plans
Period of project completion
The description of the building, covered area, towers, nature of buildings etc. is as follows:
Sr.no
Floor Name
Description
Area in Sqm
FAR Area in Sqm
Non FAR Area in Sqm
1.
2.
...
n
The following fee/charges have been deposited by the applicant, which have been found to be in order:-
S.No
Type of fee/Charge
Tick mark, if applicable
Amount deposited (in Rs.)
Acknowledgement receipt No.
i.
Charges for Purchasable FAR
ii.
SIDC for
100Substituted vide memo no. Misc-2339-ULB-Vol-I/7/8/2025-2TCP dated 08.12.2025
[138]
additional FAR under Code 6.5
iii.
Composition charges
iv.
Labour Cess
v.
Any other fee/charges
The undersigned has duly examined the submitted application alongwith the documents and completion drawings viz-a-viz approved building plans as well as provisions of HBC, Structural safety report issued by , public health services functionality report issued by , report from fire safety point of view issued by , fee/charges deposited by the applicant, No Dues Certificate issued by competent authority as well as validity of permission.
It is hereby certified that the site has been inspected and construction has been found to be in order as per plans submitted in Form BRS-I, in accordance with the Haryana Building Code-2017 and the approved zoning plan of the plot, for the building detailed above. It is also duly certified that the structure has been designed and construction carried out totally in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards as certified by the empanelled technical persons. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same and executing the construction work. Also it has been confirmed by undersigned that the permission is valid and there are no outstanding dues payable to the competent authority.
I hereby:-
(i) grant permission for the occupation of the said building with following conditions; or
(ii) refuse permission for the occupation of the said building for reason given below:-
(Signatures of Architect under 3rd party certification)
Name
Council of Architecture
Registration No.
Validity of Reg. No.
Address
E-mail ID
[139]
Endst. No:
A copy is forwarded to the followings for information and necessary action:-
• Director, TCP/ MD HSIIDC / CA HSVP / Director, DULB/ any other relevant authority along with duplicate copy of file of Occupation Certificate.
• District Town Planner, Field office / Estate Officer, HSVP/ Estate Manager, HSIIDC/ any other relevant authority along with duplicate copy of file of Occupation Certificate
• Project proponent.
• HSVP in view of public health services functionality report issued vide.
• Concerned Assistant Divisional Fire Officer/Fire Station Officer in respect of fire safety certificate issued vide..................].
[140]
Form-BRS-I
(See Code 2.2(1))
Form of application under self-certification
Class of Building –
Residential
Commercial
Educational
Institutional
Warehousing
Industrial
Any other
From
To
Sir,
I/We apply for permission to erect/re-erect/add/alter a building/wall in accordance with the plans submitted herewith on Site No.____; Street No.____; at ____.
2. I/We attach:
a. a site plan showing the position of site proposed to be built upon as required by the Code (in triplicate) an un-editable Compact Disc/DVD or any other electronic medium permissible by Competent Authority from time to time containing the drawings as required by Code 2.1;
b. Plans, elevations and sections as required by the Code (in triplicate) an un-editable Compact Disc/DVD or any other electronic medium permissible by Competent Authority from time to time containing the drawing as required by Code 2.2;
c. Drainage plans (in triplicate), as required by Codealongwith an un-editable Compact Disc/DVD or any other electronic medium permissible by Competent Authority from time to time containing the drawings as required under this code;
d. Structural drawings (for record) along with structure Certificate as per Form BRS-II;
e. Fire Safety design as required in the National Building Code as approved by the State Fire Authority. Alternatively an undertaking to the effect that the fire safety plans duly approved by the State Fire Authority will be submitted within sixty days;
f. Heating, Ventilation, Air conditioning (H.V.A.C.) service plans, wherever required;
g. Specifications of the proposed building (in triplicate) in Form BR-II;
h. Certificate of conformity to regulation and structural safety for the relevant buildings;
i. An affidavit from the owner and architect, as required under Code 2.2;
j. Scrutiny fee through an electronic transfer
[141]
The construction of the building will be undertaken as per the approved building plans, structural design given by the Structural Engineer, fire safety design as approved by the Competent Authority and got supervised through the following Architect/Engineer;
Signature of
i) Architect:
a. Complete Address
b. E-Mail
c. Mobile no.
ii) Structural Engineer supervising the construction at site