11.1 Two pipe system in drainage
(1) The drainage system of building shall be of two pipe system in which the soil and waste pipes are distinct and separate. The soil pipes being connected to the drain direct and waste pipes through a trapped gully. All traps of all appliances are completely ventilated in this system.
(2) In Group housing, commercial complexes, commercial (other than plotted), institutional, industrial, other building specified by the competent authority in accordance with Code 8.4, the water from waste pipes shall be treated within the premises from appropriate treatment plant. The treated water shall be used for flushing, horticulture and cooling tower purposes. Further, no soil/ waste pipe shall be allowed in common wall.
11.2 Minimum sanitary facilities required for various type of buildings
(1) Dwellings with individual convenience shall have at least the following fitments namely:-
(i) one bath room provided with a tap;
(ii) one water closet; and
(iii) for kitchen wash basin, one nahani trap in the floor or a sink trap raised from the floor shall be provided.
Where only one water closet is provided in a dwelling, the bath and water closet shall be separately provided.
All waste water outlets shall be provided with suitable traps for preventing back flow of water or foul smell or both.
(2) Dwellings (tenements) without individual conveniences shall have the following fitments namely: -
(i) one water tap with draining arrangements in each tenement;
(ii) one water closet and one bath for every two tenements; and
(iii) water tap in common bath room and common water closet.
(3) The requirements for fitments for drainage and sanitation, in case of buildings other than residences such as office buildings, factories, cinemas, concert halls, theatres, hospitals, hotels, restaurants, schools and hostels shall be in accordance with relevant Bureau of Indian Standards of “Basic Requirements for Water Supply, Drainage and Sanitation” with such modifications as may be made from time to time.
11.3 Method of disposal
(1) Every water borne drainage installation shall be connected with the public sewer, but in case no public sewer exists in the vicinity of the said premises the drainage
system may as a temporary measure and subject to the previous written approval of the Competent Authority be connected to a septic tank from which the effluent shall be drained off –
(i) into absorption pits; or
(ii) by sub-soil drain:
Provided that no absorption pit shall be allowed in the case of any premises or area in which domestic supply is taken from sub soil water:
Provided further that if in future a public sewer is constructed in the nearby area, which can serve the premises, the owner shall at his own expense cause the said drainage system to be connected to the sewer.
(2) Effective arrangements shall be made to treat the effluents upto the parameters/ guidelines issued from time to time by Central Pollution Control Board (CPCB) or Haryana State Pollution Control Board from the sewer system so as to ensure that the untreated effluents do not enter any canal, river or water body.
11.4 Septic tank
(1) No septic tank shall be located -
(i) at a distance of less than 25 metres from a dwelling unit or any other building used for human habitation or for work or recreation;
(ii) within a public through fare;
(iii) within 60 (sixty) metres from any percolation well, watercourse or stream used or likely to be used for drinking or domestic purposes or for manufacture or preparation of any article of food or drink for human consumption and it shall be readily accessible so as to permit cleaning operation being carried out without interference with the operation of any water borne sanitary installation as a whole.
(2) Every septic tank intended to serve a population of 24 (twenty four) or more persons shall be constructed into two separate compartments so that one compartment when required can be put out of use for cleaning purposes. The capacity of every compartment of the septic tank shall be 2½ (two and half) times the total water supply allowances for the total number of residents of the buildings in premises.
(3) Every inlet pipe into a septic tank shall be effectively trapped.
(4) The design of septic tank shall be in accordance with the National Building Code and guidelines issued by Public Works Department, Haryana.
11.5 Absorption pit
(1) In the matter of location, every absorption pit shall conform to same restrictions as are laid down for a septic tank in Code 11.4.
(2) No absorption pit shall have any outlet into, a means of communication with any sewer, storm water drain and surface drain.
(3) The walls of every absorption pit shall be at least 0.5 metres above ground level so as to exclude effectively the entry of storm water into the absorption pit.
(4) The absorption pits shall be constructed in duplicate so that one pit can be put out of use for cleaning purposes. The capacity of the absorption pit shall be as approved by the Competent Authority.
(5) Other details shall conform to the National Building Code.
11.6 Sub-soil irrigation for disposal of effluent
(1) No Sub-soil irrigation work for disposal of effluent from a septic tank shall be laid out within a premise till a suitable area of open land, the situation and extent and sub-soil of which is previously approved by the Competent Authority, is set apart within the premises to be used as a farm or a garden.
(2) The area set apart shall be one hectare for every 25,000 liters of effluent per day.
(3) No part of any area reserved for sub soil irrigation, shall be within a distance of 25 metres from the nearest point of any dwelling unit or any other building used for human habitation or for work or for recreation and of any canal or irrigation well.
(4) No such works shall be laid out within a distance of 75 metres from any percolation well, tube well, or water-course or stream used or likely to be used for drinking or domestic purposes or for the manufacture or preparation of any articles of food or drink for human consumption.
11.7 Zero waste water discharge
(1) The group housings, industries, commercial, institutions and any other building specified by the competent authority shall ensure zero waste water discharge to main sewer line and shall install suitable treatment plant for treatment of waste water. The applicant shall submit completion certificate of installation of treatment plant from independent expert agency along with the application of Occupation Certificate.
(2) For water conservation in the building, provision shall be made whereby the waste water generated from the sources such as dishwashing or washing machines, is used for sub-surface irrigation, or if treated, for non-potable purposes e.g. to flush toilets and for washing cars.
Note: The above restriction shall not apply in case of plots upto 4000 square metres.
11.8 Notice and certificate of completion of work
No connection to any public sewer shall be made nor any water borne sanitary and drainage installations intended to be connected through the connection, shall be brought into use until a certificate after completion of these works, has been applied
for by the applicant to the Competent Authority and a certificate has been issued by the letter to the effect that the sanitary installations and drainage have been satisfactorily completed in compliance with this Code. If no decision is communicated on the application for a certificate within 30 days of the receipt of the application, the certificate shall be deemed to have been granted.
11.9 Application for connection with public sewer
(1) After the grant of a certificate referred to in the building Code or in the event of the said certificate having been deemed to have been granted, every person intending to connect a drain to a public sewer shall apply to the Competent Authority at least seven days before the date on which such connection is required.
(2) The application shall be accompanied by a certificate referred to the Code 11.8 and such amount as may be laid down from time to by the Competent Authority and calculated on the basis of the current schedule of rates to meet the cost of the proposed connection.
(3) On receipt of the application and subject to the requirement of the foregoing clauses, the Competent Authority shall sanction or reject the request.
(4) In the event of the required connection having been sanctioned, it shall be made only under the supervision of an officer authorized by the Competent Authority.
11.10 Sewer connection
(1) Every drain discharging into a public sewer shall join the sewer obliquely in the direction of the flow of the sewer.
(2) If practicable, the connection shall be made at an existing junction in the sewer and if not possible, then there shall be an intercepting manhole before the connection.
11.11 Drainage of roof
The roof of every building shall drain rain water into gutters, chutes or trough and shall be carried down through adequate number of down pipes without causing dampness in any part of the wall or foundation of the building or any adjacent building:
Provided that in the case of detached or semidetached building not exceeding one storey, in height, rain water pipe, khasi or exposed parnalas may be provided for so long as these do not discharge into any public roadway, footpath or on private land of adjoining owner.
11.12 Inspection of work
Every person by or for whom any water borne sanitary installation or drainage installation or any other work in connection therewith is carried out for any existing or new building or any other premises, shall at all reasonable times, afford the
Competent Authority or any other officer/official duly authorised by him, free access to such water borne sanitary installations or drainage installations or work in connection therewith, for the purpose of inspection.
11.13 Effect on the transferred areas
Where the planned areas are transferred to the Competent Authority then the norms/ bye-laws/ zoning bye-laws applicable to them at the time of transfer of these areas shall remain same, as defined by the concerned Department/ Authority.