Where any building permit which has been issued by the Competent Authority before the commencement of this Code and where construction is in progress and has not been completed within the specified period from the date of such approval, the said permission shall be deemed to be sanctioned under this Code and shall only be eligible for revalidation thereunder. Accordingly, where the validity of sanction has expired and construction has not commenced, construction shall be governed by the provisions of this Building Code.
Annexure “B” – Standard Affidavit
I son/daughter/wife.., applied for building plan approval/ DPC Level/ occupation certificate vide application dated…… on Form BR………………….., and resident of …… …., hereby solemnly state & affirm as under:
That I shall not use basement as habitable space, as the same has not been included in the FAR and has not been shown as habitable space in the approved plans.
That I shall use the building only for the purpose for which approval and occupation certificate has been obtained.
That I shall comply with all the condition(s) implied by the competent authority at the time of approval of building Plan and Occupation certificate.
That …… ….(condition/ indemnity/ affirmity required by the Competent Authority)-I.
That … ….(condition/ indemnity/ affirmity required by the Competent Authority)-II.
That … …….(condition/ indemnity/ affirmity required by the Competent Authority)-III.
Place: Date:
DEPONENT
Verification
I son/daughter/wife of applied for building plan approval/ DPC Level/ occupation certificate vide application dated… on Form BR… and resident of …… …., hereby verify and affirm that the contents of this affidavit are true and correct to the best of my knowledge, belief and information in witness whereof I have signed hereunder on day of
Place: DEPONENT Date:
[112]
13.2Power of relaxation
The Government may relax any restrictions or conditions or norms stated in the Code or may issue direction to revise the Code, if the relaxation or revision is in public interest at large.
[108]
Appendix A
61 [Appendix A: Qualification and Competence of Architect/ Engineer/ Supervising Engineer/ Structural Engineer/ Proof Consultant/ Supervisor/ Geotechnical Engineer.
Sr.No.
Professional
Qualification
Competency/ Functions
1
Architect
Registered with valid membership of the Council of Architecture, India as prescribed under the Architect's Act 1972.
Prepare, sign all plans and submissions of building plans under Code 4 Further supervise construction of allbuildings and issue certificate of supervision and completion of all buildings pertaining to Architectural aspects, as stated in this code.
2
Engineer
Graduate in Civil Engineering from recognized Indian or foreign university, having Associate membership of The Institution of Engineers (India) including Architectural Engineer as specified in clause A-2.2, Annex A of Part 2 Administration of National Building Code-2016.
Supervise all building construction including preparation of service plans, structural drawings, details and calculations of buildings upto 1000 square metres plot area and 15.0 metres height referred in Form BRV(A1).
3
Supervising Engineer
Graduate in Civil Engineering from recognized Indian or foreign university, having Associate membership of The Institution of Engineers (India), with minimum three years of experience.
Supervise all building construction and issue certificate of supervision and completion of all buildings pertaining to structural aspects, as stated in this code.
4
Structural Engineer
Post-Graduate in Structural engineering from recognized Indian or Foreign University, having Associate membership of Institute of Engineer, India with
The Structural Engineer shall be competent to prepare the structural design, make calculations and design details for all
61Substituted vide memo no. Misc-2339-Loose-ULB-7/19/2023-2TCP dated 04.12.2023
[109]
minimum three years experience in structural engineering practice with designing and field work.
buildings referred in Form BR-V(A2).
5
Proof Consultant i i
i. Structural Engineer or a group/ firm of Structural Engineers having post-graduate qualification in structural engineering, having Associate membership of Institute of Engineer, India with ten years experience in structural design and evaluation thereof, for multi-storeyed and specialized structure, and/ or an institute of the following type: ii. Institute of Structural Engineers (India). ii. Central Building Research Institute, Roorkee. v. Various engineering institutes, like: a) Indian Institute of Technology; b) Punjab Engineering College, Chandigarh; c) National Institute of Technology; d) Any other institute of repute;
Evaluation/ checking of the structural design of the buildings referred in relevant Form BR-V(A2).
6
Supervisor
i. Two years diploma in Draftsman Civil with seven years experience under a qualified Architect/Civil Engineer for building design, construction and supervision; or ii. Three years diploma in Civil Engineering/Architectural Assistantship with five years experience under a
To prepare, sign and submit building plans and supervise construction of building upto 200 Sqm (8 marla) and 15 mtr. Height, under Code 4. The Supervisor shall get his/her empanelment renewed annually for the first 2 years and it shall be renewed for a period of 3 years thereafter.
[110]
qualified Architect/Civil Engineer for building design, construction and supervision; or iii) iii. B.Tech Civil, B.Tech (Building Engineering Management or equivalent);
7
Geotechnical Engineer
Post graduate in geotechnical engineering with minimum 10 year experience in geotechnical engineering practice in designing and field work. or Doctorate in civil engineering or geotechnical engineering with minimum 5 year experience in geotechnical engineering practice in designing and field work.
Evaluation/checking of the design of the buildings above 70 m height as mentioned in BR-V (A2)
“Note: Any post graduate qualification with at least 50% of the subjects relating to Structural Engineering (by credit), including research thesis, shall also be treated at par with Post Graduate in Structural Engineering.”]
[111]
Annexure “C” – Standard report format for Single Joint Inspection.
I. Inspection report Format for Pre-Construction Stage (to be conducted within 1-2 week of submission of building plan application/ self certification:
Name of applicant:.........................
Address of site/ building Plot no. .......... Khasra no............... Sector/ area........... Colony..............
Application no.:.............
Geo-coordinates of site: Lat/ Long points: (as many required to survey the site)
Area of site:....................... (in square metres)
Building use type: Residential Commercial Industrial Institutional Any other.
Name of Department
Appointed Nodal Officer for joint inspection
Inspection details
Inspection parameters
Sign of Nodal officer
Urban Local Bodies
District Town Planner/Building Inspector/Engineer
Site inspection w.r.t site dimension, area, etc.
Area of site Site dimensions along with Geo-coordinates. Physical features. Applicability of Acts on site/ HT line/ Gas line, etc.
HSIIDC
To be appointed by the Corporation.
Temporary Water Connection
Water Connection inspection
Town and Country Planning Dept.
District Town Planner
Site inspection w.r.t site dimension, area, etc.
Area of site Site dimensions along with Geo-coordinates. Physical features. Applicability of Acts on site/ HT line/ Gas line, etc.
Forest Department
To be appointed by
Inspection for any acquisition or
As per Department requirement.
[113]
the Department.
grabbing of forest land or any cutting of marked trees.
II. Inspection report Format for During-Construction Stage (to be conducted within 1 week of submission of self certified DPC level certificate:
Name of applicant:.........................
Address of site/ building Plot no. .......... Khasra no............... Sector/ area........... Colony..............
Application no.:.............
Area of site:....................... (in square metres)
Building use type: Residential Commercial Industrial Institutional Any other.
Name of Department
Appointed Nodal Officer for joint inspection
Inspection details
Inspection parameters
Sign of Nodal officer
Labour Department
Joint Director/Deputy Director/Assistant Director
Cess Assessment inspection
As per Department requirement
Urban Local Bodies
District Town Planner/Building Inspector/Engineer
DPC level inspection
Inspection at DPC level of building w.r.t approved building plan.
Town and Country Planning Dept.
District Town Planner
DPC level inspection
Inspection at DPC level of building w.r.t approved building plan.
HUDA
Junior Engineer
Inspection for temporary Water connection (only new construction) DPC level inspection (only new construction).
As per Authority requirement.
[114]
UHBVN
Concerned SDO/ OP
Inspection for Temporary Electricity Connection
As per Department requirement.
III. Inspection report Format for Pre-Construction Stage (to be conducted within 1-2 weeks of submission of building plan application/ self certification:
Name of applicant:.........................
Address of site/ building Plot no. .......... Khasra no............... Sector/ area........... Colony..............
Application no.:.............
Area of site:....................... (in square metres)
Building use type: Residential Commercial Industrial Institutional Any other.
Name of Department
Appointed Nodal Officer for joint inspection
Inspection details
Inspection parameters
Sign of Nodal officer
Labour Department
Joint Director/Deputy Director/Assistant Director
Inspection at time of completion of construction. In case of start of manufacturing in factory (Manufacturing)
As per Departm ent requirem ent
Fire Department
Fire Officer
Site inspection for Fire Safety norms and fixtures after completion of building
As per Department requiremen t
Urban Local Bodies
District Town Planner/Building Inspector/Engineer
Inspection for Occupation certificate to check that the building has been constructed as per approved plan or not Site inspection for public health services.
Site inspectio n for OC. Site inspectio n of health services
HSIIDC
To be appointed by the Corporation
Inspection for Occupation certificate to check that the building has been constructed as per approved plan or not
As per Corporatio n requiremen t.
[115]
■ Sewerage Connection
Town and Country Planning Dept.
District Town Planner/ Engineer
■ Inspection for Occupation certificate to check that the building has been constructed as per approved plan or not■ Site inspection for public health services.
■ Site inspection for OC.■ Site inspection of health services
Public Health Engineering Department
To be appointed by the Dept.
■ Inspection for potable water connection
As per Department requirement t.
PWD (B & R)
To be appointed by the Dept.
■ Inspection at the time of road cutting for laying of services like water, sewerage line, etc.
As per Department requirement t.
Pollution Control Board
To be appointed by the Board.
■ Inspection at the time manufacturing of products
As per Board requirement t.
HUDA
Junior Engineer
■ Inspection for Permanent Water connection (only new construction)■ Inspection for Occupation certificate to check that the building has been constructed as per approved plan or not.
As per Authority requirement t.
UHBVN
Concerned SDO/ OP
Inspection for Permanent Electricity Connection
As per Department requirement t.
Chief Electrical Inspector, Power Department
Concerned District Electrical Inspection
Inspection for granting NOC for installation of electrical connection and fixtures
As per Department requirement t.
HAREDA
To be appointed by the Dept.
■ Inspection for ECBC compliance.■ Inspection for solar related installation.
As per Department requirement t.
[116]
62[Annexure-D
Transit Oriented Development (as per the policy dated 09.02.2016, as amended from time to time)
TOD Zone
Maximum Permissible Ground Coverage
Maximum Permissible FAR
Minimum/Maximum Density (Persons Per Acre)
Parking norms - based on the carpet area* of the additional FAR availed
Multi storeyed Group Housing
Intense
40%
3.5
600(±10%)
Upto 100 sqm-0.5 ECS • Between 100 sq. mtr. to 150 sq. mtrs.- 1.0 ECS • More than 150 sq.mtrs.-1.5 ECS Size of ECS (Equivalent Car Space):- (i) 1 ECS = 23 sq. mts. for open parking. (ii) 1 ECS = 28 sq. mts. for stilt parking (iii) 1 ECS = 32 sq. m
Transition
40%
2.5
430(±10%)
Integrated Commercial/Office spaces/ mixed land use
Intense
60%
3.5
-
Transition
60%
2.5
-
IT/ITes
Intese
40%
3.5
-
Transition
40%
3.0
-
For the purpose of calculation of parking, the definition of Carpet Area as mentioned in the policy dated 09.02.2016, as amended from time to time, shall be followed.
Affordable Group time to time)
Density
Maximum Permissible FAR (Residential Component)
Maximum permissibl e Ground Coverage
Minimum are under organized Green spaces
Commercial component
Parking Norms
Maximum NPA permissible
Max permissi ble FAR
750- 900(persons per acre)
225
50%
15% of Net Planned Area (NPA)
8%
175
Mandatory nonchargeable 0.5 ECS for each Dwelling Unit (0.8m X 2.5m)Optional and chargeable parking space at the extent of 0.5 ECS for
62Inserted vide Misc-2339-ULB-C/7/5/2006-2TCP dated 18.10.2022
[117]
each Dwelling Unit.The balance available parking space, if any, beyond the allocated two-wheeler parking sites, can be earmarked as freevisitor-car-parking space.
Maximum FAR and Density to be permitted with TDR(as per the policy dated 19.08.2013, as amended from time to time)
Sr. NO.
Type of Colony/ Site Project
Applicable FAR
Applicable Density (persons per acre)
Maximum permissible FAR with TDR
Maximum Density (persons per acre with TDR)
1.
GH
1.50/1.75
300-400
3.0
Existing + 200
2.
AGH
2.25
750-900
3.0
Existing + 175
3.
HDGH
1.75
450
3.0
Existing + 200
4.
TOD-GH
3.5/2.5
600/430(±10%)
5.0/4.0
Existing+ 150
5.
CL
1.75
NA
3.0
NA
6.
TOD-CL
3.5/2.5
NA
5.0/4.0
NA
7.
NILP-CL
3.0
NA
4.5
NA
8.
MLU
1.75
80
3.0
Existing +70
9.
TOD-MLU
3.5/2.5
NA
5.0/4.0
NA
10.
NILP-R
1.25
300
2.5
Existing + 125
11.
CP/CC
2.5
NA
5.0
NA
12.
TOD-IT/ITES
3.0/3.5
NA
4.5/5.0
NA
13.
IIILP-IND
1.0
NA
2.0
NA
14.
CS/I-CLU
1.0/1.5
NA
2.0
NA
15.
Res. Plot
1.0 to 1.65
18
2.4/2.64 (as applicable)
Co change
Notations: 1. GH=Group Housing Components (1.5/1.75 FAR) in such colonies where permitted, except NILP; 2. AGH=Affordable Group Housing Component in all such colonies where permitted as per the Policy dated 19.08.2013, as amended from time to time 3. HDGH=High Density Group Housing Project as provided in development plan 4. TOD-GH=Group Housing Licence under TOD as per the Policy dated 09.02.2016, as amended from time to time 5. CL=Commercial Components in all colonies where permitted or Commercial CLU projects; 6. TOD-CL= Commercial Licenced Colony under TOD Policy dated 09.02.2016, as amended from time to time 7. NILP-CL= Commercial Licence granted under the NILP Policy dated 26.10.2015 as amended from time to time
8.
MLU= Mixed Land Use Licence granted under policy dated 03.01.2014, as amended from time to time
9.
TOD-MLU= Mixed Land Use Project under TOD Policy dated 09.02.2016, as amended from time to time
10.
NILP=Residential Licence granted under New Integrated Licencing Policy dated 09.02.2016, as amended from time to time
11.
CP/CC/ IT-ITES= Cyber Park/Cyber city/ IT or ITES Units
12.
TOD-IT/ITES= IT/ITES Project under TOD Policy dated 09.02.2016, as amended from time to time.
13.
IILP-IND=Industrial Component under IILP policy dated 11.10.2017, as amended from time to time
14.
CS=Community Sites in licenced colonies
15.
I-CLU= CLU Projects for Institutional Use
16.
Res. Plot= Residential Plot in a Residential Plotted colony
Note: The word ‘colony’ shall be as defined in the Act No. 8 of 1975. Further, the parameters as above shall be applicable on the specified use irrespective of such use being either the main use or and ancillary use unless specifically excluded to such effect. For example, the group housing parameters shall be applicable to the group housing components availed either in a group housing colony or in a Cyber City or in an Industrial colony and so on, except group housing components in a NILP projects for which the parameters are separately specified.]
[119]
63[ Form BR-I
[See Code 2.1(1)] Application for erection/re-erection of Building(s) (Other than building(s) applied under self-certification)
From
I/We apply for permission to erect/re-erect/add/alter a building/wall in accordance with the plans submitted herewith on Site no. Street no. at /Khasra no. Village (strike out whichever is not applicable)
i. I/We attach:
a. Site plan (in triplicate) showing the position of site proposed to be built upon as required by the Code along with an un-editable Compact Disc/DVD or any other electronic medium permissible by competent authority from time to time containing the drawings so submitted;
b. Plans, elevations and sections (in triplicate) as required by the Code along with an un-editable compact Disc/DVD or any, other electronic medium permissible by competent authority from time to time containing the drawings so submitted;
c. Drainage plans (in triplicate), as required by Code along with an un-editable compact Disc/DVD or any, other electronic medium permissible by competent authority from time to time containing the drawings so submitted;
d. Structural drawings (for record) signed by the empanelled Structural Engineer and/ or Proof Consultant/ Geo-Technical Engineer, in original, as per Form BR-V(A1)/ BR-V(A(2), as may be applicable, alongwith complete list of such drawings, certified by all concerned, i.e. structural engineer and proof consultant, in A3 size;
e. Specifications of the proposed building (in triplicate) in Form BR-II;
f. Certificate of conformity to regulation and structural safety for the relevant buildings (depending upon type and height) in Form BR-V(A1) or BR-V(A2); and
g Receipt of Scrutiny fee @ Rs. 10 per square metre deposited online on Department Portal
h. In case of revision of building plans, the reasons on account of which such changes are being proposed to be specified as follows:
63Substituted vide Memo No. MISC-720/2024/7/16/2024-TCP dated 25.07.2024
[120]
Tick mark whichever applicable
Reason for revision
Specify Block/Tower/Phase of such revision
Specify Area (in Sqm) under corresponding Block/Tower/Phase proposed for revision
Additional FAR on account of utilisation of Transferrable Development Rights Certificate
Additional FAR on account of Purchasable Development Rights
Additional FAR on account of TOD
Additional FAR on account of Green rating/ incentives
Additional FAR on account of installation of Solid Waste Management plant
Additional FAR on account of installation of solar photovoltaic power plant
On account of the following in respect of licence(s) issued under Act of 1975:-
(i) Grant of licence for additional land.
(ii) Migration of part licenced land.
(iii) De-licence of part licenced land.
(iv) Surrender of part licenced land.
Any other, specify
I/ We hereby undertake that the proposed revision of building plans is limited to the extent as indicated above and no parameter other than above is proposed or intended for revision.
ii. The construction of the building will be undertaken as per the approved building plans, Structural design and specifications as submitted by the Engineer/ Structural Engineer/Proof Consultant/Geo Technical Engineer, as applicable.
iii. The construction of the building will be got supervised through the following Architect/ Engineer/ Supervising Engineer, whichever applicable:
[121]
A.
Class of Building
Tick whichever applicable
1.
Residential
1.1.
Residential Plotted
1.1.a.
Upto 1000 sqmts and 16.5 mts height
1.1.b.
Above 1000 sqmts upto 16.5 mts
1.2.
Residential (other than plotted)
1.2.a.
Upto 1000 sqmts and 15 mts height
1.2.b.
Above 1000 sqmts upto 15 mts
1.2.c.
Above 15 mts.
2.
Commercial
2.1.
Upto 1000 sqmts and 15 mts height
2.2.
Above 1001-2000 sqm upto 15 mts height
2.3.
Above 2000 sqm upto 15 mts height
2.4.
Above 15 mts.
3.
Industrial/IT/ITES
4.
Warehousing
5.
Educational
6.
Institutional
7.
Any other, please specify
B. Technical Persons (Whichever applicable)
FOR DESIGN
(I) Architect (For all classes of buildings)i. Name:ii. Council of Architecture Registration No. ____, valid upto ____iii. Complete Addressiv. E-Mailv. Mobile no.
(II) Engineer (For 1.1.a, 1.2.a & 2.1):i. Name:ii. Qualifications:iii. Complete Addressiv. E-Mailv. Mobile no.
(IV) Empanelled Proof Consultant (For 1.1.b, 1.2.b, 1.2.c, 2.3, 2.4, 3, 4, 5, 6)i. Name :ii. Qualifications:iii. Department TPR No.iv. Complete Addressv. E-Mailvi. Mobile no.
(V) Empanelled Geo-technical Engineer (For evaluation of all classes of buildings with height more than 70 m)i. Name :ii. Qualifications:iii. Department TPR No.iv. Complete Addressv. E-Mailvi. Mobile no.
FOR SUPERVISION
(VI) Architect (For all classes of buildings)i. Name:ii. Council of Architecture Registration No. ____, valid uptoiii. Complete Addressiv. E-Mailv. Mobile no.
The materials to be used in the construction to be clearly specified under the following heads:-
Items
Specifications
(a) Foundations
(b) Walls
(c) Damp-proof course
(d) Floors
(e) Roofs
(f) Windows and Doors and other wood-work
(g) Steel work
(h) Internal finish
(i) External finish.
Signature of applicant
(No digital signatures are required)
Signature of Architect/Engineer
i. Complete Address
ii. E-Mail
iii. Mobile no.
[124]
64[ Form BR-V (A1)
(See code 1.2(1)(lxxi), (lxxxv), 2.1(1)(vii))
Certificate of conformity to Code and structural safety for Residential and Commercial Buildings upto 15 metres height.
Certificate to be submitted along with the building application in Form BR-1 duly signed by the Architect and the Structural Engineer.
Details of the building for which the certificate is issued
Plot No. , Sector , Colony
City/Town
Name of the owner
Complete address of the owner
A. Building Plan :
i. Name of Architect:
ii. Council of Architecture Registration No. ____, valid up to
iii. Complete Address
iv. E-Mail
v. Mobile no.
B. Structural Design:
i. Name of Engineer:
ii. Qualifications:
iii. Complete Address
iv. E-Mail
v. Mobile no.
Certificate
It is hereby certified that the plans submitted in Form BR-I alongwith duly signed Structural drawings (for record) as per the counter signed list enclosed with this form, are in accordance with the Haryana Building Code-2017 and the approved zoning plan of the plot. The structure has been designed in accordance with the provisions of the National Building Code and the relevant Indian Standard Code (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated
Signature of Owner
(See Code 4.2(4)) Form of Sanction
From
To
Memo No.
Dated the ………
Reference you application for permission to erect/re-erect-add to/alter a building on plot No. / Khasra no. _, Village in accordance with the plans submitted with it.
Permission is hereby-
(i) granted/sanctioned for the aforesaid construction subject to the provisions of the respective Acts and Haryana Building Code -2017 subject to the following amendments, terms and conditions;
(ii) rejected for reasons given below :-
Enclosures
Competent Authority
[130]
$^{66}$ [FORM BR-IV (A) (See Code 4.10(1)) For Residential and Commercial Buildings upto 15 metres height Application for permission to occupy
From
To
Sir,
I/We hereby give you notice that the building/part-of-building described below and sanctioned vide your order No., dated, has been completed on in all respects according to the sanctioned plans and the structural design made for the same and the suggested modifications have been carried out.
Description of Building
Plot No._, Sector_, Colony_
City/Town ____. (or)
Khasra no., Village
[131]
Name of the owner alongwith mob.no. and E-mail____.
The modifications made to the building plans and carried out at site during the course of construction are submitted herewith:
____
____
Corresponding to the above modifications made in the building plans, the necessary amendments were also carried out in the structural design and implemented a site.
Completion certificate from the architect/engineer who supervised the construction of the building is submitted herewith.
Kindly issue an occupation certificate as required by Haryana Building Code -2017
Dated ____
Signature of applicant
(No digital signatures are required)
⁶⁶ Substituted vide Memo No.Misc-2339-Loose-ULB-7/19/2023-2TCP Dated 04.12.2023
(I) For Residential sites (other than Residential plotted) and commercial sites measuring upto 1000 sqm upto 15 mts height:-
Signature of Architect and / or Engineer supervising the construction at site
i. Complete Address
ii. E-Mail
iii. Mobile no.
(II) For Residential sites (other than Residential plotted) and commercial sites above 1000 sqm upto 15 mts height:-
Signature of Architect and /or Empanelled Supervising Engineer
i. Department TPR No.
ii. Complete Address
iii. E-Mail
iv. Mobile no.]
[132]
$^{67}$ [FORM BR-IV (B) (See Code 4.10(1)) For all Buildings except as stated in Form BR-IV(A) Application for permission to occupy
From
____
____
____
To
____
Sir,
I/We hereby give you notice that the building/part-of-building described below and sanctioned vide your order No. ____, dated ____, has been completed on ____ in all respects according to the sanctioned plans and the structural design made for the same and the suggested modifications have been carried out.
Description of Building
Plot No._, Sector _, Colony _
City/Town ____. (or)
Khasra no., Village
Name of the owner alongwith mob.no.and E-mail ____.
Complete address of the owner ____.
The modifications made to the building plans and carried out at site during the course of construction are submitted herewith:
|
Corresponding to the above modifications made in the building plans, the necessary amendments were also carried out in the structural design and implemented a site.
Completion certificate (Form BR-V(2)/VI) from the Architect/ Empanelled Supervising Engineer/ Third Party Inspection Agency who supervised the construction of the building is submitted herewith.
⁶⁷ Substituted vide Memo No.Misc-2339-Loose-ULB-7/19/2023-2TCP Dated 04.12.2023
[133]
Kindly issue an occupation certificate as required under Haryana Building Code -2017
Dated ____
Signature of applicant
(No digital signatures are required)
Signature of Architect
i. Complete Address
ii. E-Mail
iii. Mobile no.
Signature of Empanelled Supervising Engineer
i, Department TPR No.
ii. Complete Address
iii. E-Mail
iv. Mobile no.]
[134]
⁶⁸ |FORM BR-V (1)
[See Code 4.10(1)]
For Residential and Commercial Buildings upto 15 metres height. Completion certificate by an Architect/Engineer in respect of building on :
Plot No._, Sector_, Colony_
City/Town ____.
Name of the owner ____.
Complete address of the owner ____.
It is hereby certified that the above work has been supervised by us and has been completed to my satisfaction in accordance with the sanctioned building plans and its structural design. The workmanship and all the material used for construction meet the specifications laid down in the National Building Code. No provision of the Haryana Building Code -2017 and no rules made, conditions prescribed or order issued thereunder has been transgressed in the course of the work.
Dated____
(I) For Residential sites (other than Residential plotted) and commercial sites measuring upto 1000 sqm upto 15 mts height:-
Signature of Architect and/ or Engineer supervising the construction at site
i. Complete Address
ii. E-Mail
iii. Mobile no.
(II) For Residential sites (other than Residential plotted) and commercial sites above 1000 sqm and upto 15 mts height:-
Signature of Architect and/ or Empanelled Supervising Engineer
i. Department TPR No.
ii. Complete Address
iii. E-Mail
iv. Mobile no.]
⁶⁸ Substituted vide Memo No.Misc-2339-Loose-ULB-7/19/2023-2TCP Dated 04.12.2023
[135]
⁶⁹ [FORM BR-V (2)
(See Code 4.10(1))
For all Buildings except as stated in Form BR-V(1)
FORM BR-VII (See Code 4.10(2), (4) and (5)) Form of Occupation Certificate
From
____, ____,
To
Memo No......
Dated ......
Whereas Shri/ Smt/ M/s ....has applied for the issue of an occupation certificate in respect of the building described below:-
City ____ Street ____
Site No._ HouseNo.(if any)_
(or) Khasra no._, Village _
Indicating description of the building, covered area, towers, nature of buildings etc.
I hereby:-
(i) grant permission for the occupation of the said building with following conditions; or
(ii) refuse permission for the occupation of the said building for reason given below:-
Competent Authority
[138]
Form of application under self-certification
Class of Building –
Residential
Commercial
Educational
Institutional
Warehousing
Industrial
From
Any other
To
Sir,
I/We apply for permission to erect/re-erect/add/alter a building/wall in accordance with the plans submitted herewith on Site No._; Street No._; at _.
2. I/We attach:
a. a site plan showing the position of site proposed to be built upon as required by the Code (in triplicate) an un-editable Compact Disc/DVD or any other electronic medium permissible by Competent Authority from time to time containing the drawings as required by Code 2.1;
b. Plans, elevations and sections as required by the Code (in triplicate) an un-editable Compact Disc/DVD or any other electronic medium permissible by Competent Authority from time to time containing the drawing as required by Code 2.2;
c. Drainage plans (in triplicate), as required by Codealongwith an un-editable Compact Disc/DVD or any other electronic medium permissible by Competent Authority from time to time containing the drawings as required under this code;
d. Structural drawings (for record) along with structure Certificate as per Form BRS-II;
e. Fire Safety design as required in the National Building Code as approved by the State Fire Authority. Alternatively an undertaking to the effect that the fire safety plans duly approved by the State Fire Authority will be submitted within sixty days;
f. Heating, Ventilation, Air conditioning (H.V.A.C.) service plans, wherever required;
g. Specifications of the proposed building (in triplicate) in Form BR-II;
h. Certificate of conformity to regulation and structural safety for the relevant buildings;
i. An affidavit from the owner and architect, as required under Code 2.2;
j. Scrutiny fee through an electronic transfer
3 The construction of the building will be undertaken as per the approved building plans, structural design given by the Structural Engineer, fire safety design as approved by the Competent Authority and got supervised through the following Architect/Engineer;
Signature of
i) Architect: a. Complete Address b. E-Mail
[139]
c. Mobile no.
ii) Structural Engineer supervising the construction at site
a. Complete Address
b. E-Mail
c. Mobile no.
[140]
Form BRS-II
(See Code 2.2(2))
Certificate for structure conforming under self-certification
Plot No._Sector_ Colony_
City/Town____
Name of the Owner____.
Complete address of the owner____.
It is hereby certified that the plans submitted in Form BRS-I for the building detailed above are in conformity with the Haryana Building Code-2017 and the approved zoning plan of the plot. The structure has been designed in accordance with the provision of National Building Code for structures resistance to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc have been kept in view while designing the same.
Dated____
Signature of Owner
(No digital signatures are required)
Signature of Architect
Signature of Structural Engineer
Mobile no.
E-mail
[141]
Completion certificate by the Architect and Empanelled Supervising Engineer in respect of building on:
Plot No. ____, Sector ____, Colony ____
City/Town ____.
Name of the owner ____
Complete address of the owner ____
It is hereby certified that the above work has been supervised by us and has been completed to our satisfaction in accordance with the sanctioned building plans and its structural design as checked and certified by the proof consultant. The workmanship and all the material used for construction meet the specifications laid down in the National Building Code. No provision of the Haryana Building Code -2017 and no rules made, conditions prescribed or order issued thereunder has been transgressed in the course of the work.
Dated____
Signature of Architect
i. Complete Address
ii. E-Mail
iii. Mobile no.
Signature of Empanelled Engineer supervising the site
i. Department TPR No.
ii. Complete Address
iii. E-Mail
iv. Mobile no.]
⁶⁹ Substituted vide Memo No.Misc-2339-Loose-ULB-7/19/2023-2TCP Dated 04.12.2023
[136]
FORM BR-VI (See Code 4.10(1)(ii)) Completion Certificate by an Architect
I do hereby certify-
i) that the following work has been supervised by me and has been completed to my satisfaction in accordance with the sanctioned plan.
ii) that no deviation from sanctioned plan is made while constructing the building/ deviation from sanction plan is made (details as below) and these deviations are duly shown on completion drawings. Due to these deviations, human safety has not been compromised (strike off whichever is not applicable).
iii) that the workmanship and the whole of the materials used are good; that no provision of the Haryana Building Code, 2017 and no requisition made, conditions prescribed or order issued there under has been violated in the course of the work.
Details of construction on (floor-wise along with covered area on each floor)
City ____ Street ____
Plot No._House No. (if any)_(or)
Khasra no. ____, Village ____
Dated
Signature of Architect
i. Complete Address
ii. E-Mail
iii. Mobile no.
[137]
FORM BRS-III [see Code 4.11(1), (2) and (3)] For Buildings Residential and Industrial Buildings applied under Code2.2 Application for permission to occupy
From
To
Sir,
I/We hereby give you notice that the building/part of building described below and sanctioned vide your order No. ____, dated ____, has been completed on ____ in all respect according to the sanctioned plans and the structural design made for the same and suggested medications have been carried out.
Description of Building
Plot No._, Sector_, Colony_
City/Town ____. (or)
Khasra no., Village
Name of the owner alongwith mob.No ____ and E-mail____.
Complete address of the owner ____.
The modifications made to the building plans and carried out at site during the course of construction are submitted herewith:
____
____
Corresponding to the above modifications made in the building plans, the necessary amendments were also carried out in the structural design and implemented a site.
Completion certificate from the architect/engineer who supervised the construction of the building is submitted herewith.
Kindly issue an occupation certificate as required by Haryana Building Code -2017
Dated ____
Signature of applicant
(No digital signatures are required)
Signature of
i) Architect:
a. Complete Address
b. E-Mail
c. Mobile no.
ii) Engineer supervising the construction at site
a. Complete Address
b. E-Mail
c. Mobile no.
[142]
Form Brs-iv
(See Code 4.11(1) and (2))
Certificate of conformity to rules and structural safety.
Certificate to be submitted along with the building application in Form BRS-III duly signed by the Architect and the Structural Engineer.
Details of the building for which the certificate is issued
Plot No. ____, Sector ____, Colony ____
City/Town ____.
Name of the owner ____.
Complete address of the owner ____
A. Building Plan :
i. Name of Architect:
ii. Council of Architecture Registration No. ____, valid up to ____.
iii. Complete Address
iv. E-Mail
v. Mobile no.
B.
Structural Design:
i. Name of Engineer:
ii. Qualifications:
iii. Complete Address
iv. E-Mail
v. Mobile no.
Certificate
It is hereby certified that the plans submitted in Form BRS-I for the building detailed above, are in accordance with the Haryana Building Code-2017 and the approved zoning plan of the plot. The structure has been designed in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated____
Signature of
i) Architect:
a. Complete Address
b. E-Mail
c. Mobile no.
ii) Engineer/ Structural Engineer supervising the construction at site
a. Complete Address
b. E-Mail
c. Mobile no.
In case of the building is above 15 metres height, the certificate shall be signed by the proof consultant, as followed:
The structural design has been checked and has been found to be in order. The design is in accordance with the provisions of the National Building Code and the relevant Bureau of Indian
[143]
Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated____
Signature of Proof Consultant along with Mob. No. & E-mail
[144]
(See Code 4.12(1) and (2))
3rd party certification for conformity to rules and structural safety.
Certificate to be submitted along with the building application in Form BRS-III duly signed by the 3rd party Architect and 3rd party Structural Engineer.
Details of the building for which the certificate is issued
Plot No. ____, Sector ____, Colony ____
City/Town ____.
Name of the owner ____.
Complete address of the owner ____.
A. Building Plan :
i) Name of Architect:
ii) Council of Architecture Registration No. ____, valid up to
iii) Complete Address
iv) E-Mail
v) Mobile no.
B. Structural Design:
i. Name of Engineer:
ii. Qualifications:
iii. Complete Address
iv. E-Mail
v. Mobile no.
Certificate
It is hereby certified that the site has been inspected and construction has been found in order as per plans submitted in Form BRS-I, in accordance with the Haryana Building Code-2017 and the approved zoning plan of the plot, for the building detailed above. The structure has been designed in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated____
Signature of
i) Architect (3rd party):
a. Complete Address
b. E-Mail
c. Mobile no.
ii) Engineer/ Structural Engineer (3rd party):
[145]
a. Complete Address
b. E-Mail
c. Mobile no.
In case of the building is above 15 metres height, the certificate shall be signed by the proof consultant ( 3rd party), as followed:
The structural design has been checked and has been found to be in order. The design is in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated____
(3rd party) along with Mob. No. & E-mail
Signature of Proof Consultant
[146]
Form Brs-v
[see Code 4.11(4)]
Occupation Certificate for Industrial Buildings applied under Code 4.11
From
____,
To
Memo No......
Dated ......
Whereas Shri/ Smt/ M/s .... has applied for the issue of an occupation certificate
in respect of the building described below:-
City ____ Street ____
Site No. ____ House No.(if any) ____
(or) Khasra no., Village
Indicating description of the building, covered area, towers, nature of buildings etc.
I hereby:-
(i) grant permission for the occupation of the said building with following conditions; or
(ii) refuse permission for the occupation of the said building for reason given below:-
Competent Authority
[147]
Form-N-I
(See Code 1.2(1) (lx), 6.3(3)(i)(a)IV)
Application form for rendering non-nuisance professional consultancy in residential premises.
Name of applicant____
Premises Number and size ____
Name of colony/change of land use site____
Sector____
Detail of floor-wise built up area____(Square metres)
Copy of approved building plan showing duly marked area upon which mixed land use is applicable.
Whether occupation certificate has been issued, if so, attested copy thereof to be attached.
Details of profession____
Numbers of anticipated visitors____
Working hours of consultancy
Detail of fee through electronic transfer as per Schedule IV A.
Affidavit to the effect that he shall abide by all the terms and conditions, which shall be imposed by Director from time to time.
Place:
Date:
Signature of Owner
(No digital signatures are required)
Mobile no.
E-mail
[148]
From
To
Memo No.
Dated:
Subject: Permission to provide non-nuisance consultancy services in the residential premises.
This is with reference to your application dated____.
Permission is hereby granted to provide ____ services, within the premises of your land/house bearing number ____ Sector ____ town/city ____. The above permission shall be subject to the following terms and conditions:-
(1) You can use the premises of your house upto 25% of the covered area of the premises or 50 square metres, whichever is less for the purpose.
(2) Total charges paid i.e. Rupees is for a period of five years.
(3) Water, sewerage and electricity charges for such premises to the extent that is being used for non-residential use would be charged at commercial rates by the service providing agency.
(4) The permission given by Competent Authority shall be valid for a period of five years which may be renewed thereafter for a period of five years and further in block of five years on payment of renewal fee @ 10% of updated commercial charges.
(5) The owners of a premises where mixed land is used is permitted should accept any other condition such as restriction with respect of provision of parking advertisement etc.
(6) Competent Authority can withdraw the permission give for mixed land use at any point of time, if the percentage area permitted under mixed land use is found to exceed the stipulated limit or for any other reason in the public interest.
(7) That the permission shall also be governed by the provision of this code.
(8) That the owners of building shall not further sublet/lease out the premises for which permission is being granted.
[149]
Signatures of Permission Issuing Authority along with seal.
(See Code 1.2(1) (lx), 6.3(3)(i)(a)IV)
Rates of conversion of residential premises into non-nuisance professional services for 25% of the covered area of the premises or 50 square metres whichever is less.
Potential Zone as notified under the Punjab Scheduled Roads and Controlled area Restriction on Unregulated Development Act, 1963 and Rules, 1965
Hyper potential
High potential
Medium potential
Low potential
Rs. 0.60 Lac
Rs. 0.50 Lac
Rs. 0.30 Lac
Rs. 0.20 Lac.
[150]
Specimenmodel Zoning Clauses for Different Building Types
1. Model Zoning Clauses for Residential Building
i. Code referred in the clause is Haryana Building Code, 2017, amended from time to time.
ii. SHAPE & SIZE OF SITE.
The shape and size of site is in accordance with the demarcation plan shown as ‘ ’ to ‘ ’, as confirmed by Competent Authority, vide drawing no…………….., issued on DD/MM/YYYY.
iii. LAND USE.
The type of buildings use permissible is residential and under no circumstance, the use of building shall be changed.
Iv. Type of Building Permitted and Land Use Zones.
The site shall be developed and building constructed thereon as indicated in and explained in the table below:
Notation
Land Use Zone
Type of Building permitted/permissible structure
Open Space Zone
Open parking, garden, landscaping features, underground services etc.
Building Zone
Building as per permissible land use in clause-iii above and uses permissible in the open space zone.
(a) The building or buildings shall be constructed only within the portion of the site marked as Building zone as explained above, and nowhere else.
(b) The proportion up to which the site can be covered with building or buildings on the ground floor and subsequent floors shall be as per Code 6.3(3)(i)(a).
(c) Maximum permissible FAR shall be as per Code 6.3(3)(i)(a).
Vi. Height of Building.
The height of the building block, subject of course to the provisions of the site coverage and FAR, shall be governed by the following:-
(a) The maximum height of the buildings shall be as Code 6.3(3)(i)(a) and Code 6.3(3)(vii).
(b) If a building abuts on two or more streets of different widths, the buildings shall be deemed to face upon the street that has the greater width and the height of the buildings shall be regulated by the width of that street and may be continued to this height to a depth of 24 metres, along the narrow street.
(c) The plinth height of building shall be as per Code 7.3.
(d) All building block(s) shall be constructed so as to maintain an inter-se distance as per Code 7.11(5).
(e) If such interior or exterior open space is intended to be used for the benefit of more than one building belonging to the same owner, then the width of such open air space shall be the one specified for the tallest building as specified in (c) above.
vii. PARKING.
(a) Adequate parking spaces, covered, open or in the basement shall be provided for vehicles of users and occupiers, within the site as per Code 7.1.
(b) In no circumstance, the vehicle(s) belonging to the plot shall be parked outside the plot area.
[151]
viii. APPROACH TO SITE.
(a) The vehicular approach to the site shall be planned and provided giving due consideration to the junctions of and the junctions with the surrounding roads to the satisfaction of the Competent Authority.
(b) The approach to the site shall be shown on the zoning plan.
Ix. BAR on Sub-division of Site.
Sub-division of the site shall not be permitted, in any circumstances.
X. Approval of Building Plans.
The building plans of the buildings to be constructed at site shall have to be got approved from the Competent Authority/ any other persons authorized by him, under the provisions of the respective Acts, before starting up the construction.
xi. BASEMENT.
Basements within the building zone of the site shall be provided as per Code 6.3(3)(i)(a) and shall be constructed, used and maintained as per Code 7.16.
xii. BOUNDARY WALL.
The boundary wall shall be constructed as per Code 7.5.
xiii. PLANNING NORMS.
The building to be constructed shall be planned and designed to the norms and standards as per Chapter-7 of the Haryana Building Code, 2017, and as approved by the Competent Authority.
Xiv. Provisions of Public Health Facilities.
The W.C. and urinals provided in the buildings shall conform to Chapter 11 of the Haryana Building Code, 2017 and National Building Code, 2005.
Xv. External Finishes.
(a) The external wall finishes, so far as possible shall be in natural or permanent type of materials like bricks, stone, concrete, terracotta, grits, marble, chips, class metals or any other finish which may be allowed by the Competent Authority.
(b) The water storage tanks and plumbing works shall not be visible on any face of the building and shall be suitably encased.
(c) All sign boards and names shall be written on the spaces provided on buildings as per approved buildings plans specifically for this purpose and at no other places, whatsoever.
(d) For building services, plumbing services, construction practice, building material, foundation and Damp Proof Course Chapter 10 of the Haryana Building Code, 2017 shall be followed.
Xvi. Lifts and Ramps:
(a) Lift and Ramps in building shall be provided as per Code 7.7.
switchover along with staircase of required width and number.
(c) If lift cannot be provided as per (b) above, ramps shall be provided conforming to the requirement of clause-3 of Annexure D-3 of Part-3 of National Building Code, 2005
xvii. BUILDING BYE-LAWS:
The construction of the building/ buildings shall be governed by provisions of the Haryana Building Code, 2017.
xviii. FIRE SAFETY MEASURES:
(a) The owner will ensure the provision of proper fire safety measures in the multi storied buildings conforming to the provisions of The Haryana Building Code,
[152]
2017/ National Building Code of India and the same should be got certified form the Competent Authority.
(b) Electric Sub Station/ generator room if provided should be on solid ground near DG/ LT. Control panel on ground floor or in upper basement and it should be located on outer periphery of the building, the same should be got approved from the Chief Electrical Inspector, Haryana.
(c) To ensure fire fighting scheme shall be got approved from the Director, Urban Local Bodies, Haryana or any person authorized by the Director, Urban Local Bodies, Haryana. This approval shall be obtained prior to starting the construction work at site.
xix. The rain water harvesting system shall be provided as per Code 8.1.
xx. That the owner shall ensure the installation of Light-Emitting Diode lamps (LED) for its building.
xxi. That the owner shall strictly comply with the Code 8.3 for enforcement of the Energy Conservation Building Codes.
xxii. That the owner shall ensure the installation of Solar Power Plant as per Code 8.2.
[153]
2. Model Zoning Clauses forCommercial Building
i. Code referred in the clause is Haryana Building Code, 2017, amended from time to time.
ii. SHAPE & SIZE OF SITE.
The shape and size of site is in accordance with the demarcation plan shown as ‘ ’ to ‘ ’, as confirmed by Competent Authority, vide drawing no…………….., issued on DD/MM/YYYY.
iii. LAND USE.
The type of buildings use permissible is commercial for retail outlet/ showroom/ shop/ etc. and under no circumstance, the use of building shall be changed.
iv. TYPE OF BUILDING PERMITTED AND LAND USE ZONES.
(a) The type of buildings permitted on this site shall be buildings designated and intended to be used for:
(i) retail outlet including saleroom for lubricants, office room, toilet, store installation of fuel pumps, air filling pumps, underground storage of petrol/ diesel, canopy and way side amenities, like repairs/services shop, ATMs & small eating place (Dhaba/ Fast Food Joint). Fuel tanks shall be provided underground within the site after leaving 1.5 mtrs from the boundary.
(ii) Showroom/ shops including sale of goods.
(b) No other building use shall not be permitted.
(c) The site shall be developed and building constructed thereon as indicated in and explained in the table below:
Notation
Land Use Zone
Type of Building permitted/permissible structure
Open Space Zone
Open parking, garden, landscaping features, underground services etc.
Building Zone
Building as per permissible land use in clause-iii above and uses permissible in the open space zone.
(a) The building or buildings shall be constructed only within the portion of the site marked as Building zone as explained above, and nowhere else.
(b) The proportion up to which the site can be covered with building or buildings on the ground floor and subsequent floors shall be as per Code 6.3(3)(ii).
(c) Maximum permissible FAR shall be as per Code 6.3(3)(ii).
vi. HEIGHT OF BUILDING.
The height of the building block, subject of course to the provisions of the site coverage and FAR, shall be governed by the following:-
(a) The maximum height of the buildings shall be as Code 6.3(3)(ii) and Code 6.3(3)(vii).
(b) If a building abuts on two or more streets of different widths, the buildings shall be deemed to face upon the street that has the greater width and the height of the buildings shall be regulated by the width of that street and may be continued to this height to a depth of 24 metres, along the narrow street.
(c) The plinth height of building shall be as per Code 7.3.
[154]
(d) All building block(s) shall be constructed so as to maintain an inter-se distance as per Code 7.11(5).
(e) If such interior or exterior open space is intended to be used for the benefit of more than one building belonging to the same owner, then the width of such open air space shall be the one specified for the tallest building as specified in (c) above.
vii. PARKING.
(a) Adequate parking spaces, covered, open or in the basement shall be provided for vehicles of users and occupiers, within the site as per Code 7.1.
(b) In no circumstance, the vehicle(s) belonging/ related to the plot/ premises shall be parked outside the plot area.
viii. APPROACH TO SITE.
(a) The vehicular approach to the site shall be planned and provided giving due consideration to the junctions of and the junctions with the surrounding roads to the satisfaction of the Competent Authority.
(b) The approach to the site shall be shown on the zoning plan.
(c) Entry and Exit shall be permitted as indicated/ marked on the plan.
(d) In case of retail outlet no gate and gatepost shall be permitted.
Ix. BAR on Sub-division of Site.
Sub-division of the site shall not be permitted, in any circumstances.
X. Approval of Building Plans.
The building plans of the buildings to be constructed at site shall have to be got approved from the Competent Authority/ any other persons authorized by him, under the provisions of the respective Acts, before starting up the construction.
xi. BASEMENT.
(a) Basements within the building zone of the site shall be provided as per Code 6.3(3)(ii) and shall be constructed, used and maintained as per Code 7.16.
(b) In case of retail outlet basement is not permitted.
Xii. Planning Norms.
The building to be constructed shall be planned and designed to the norms and standards as per Chapter-7 of the Haryana Building Code, 2017, and as approved by the Competent Authority.
Xiii. Provisions of Public Health Facilities.
The W.C. and urinals provided in the buildings shall conform to Chapter 11 of the Haryana Building Code, 2017 and National Building Code, 2005.
Xiv. External Finishes.
(a) The external wall finishes, so far as possible shall be in natural or permanent type of materials like bricks, stone, concrete, terracotta, grits, marble, chips,class metals or an other finish which ma be allowed b the Com etent Authority.
(b) The water storage tanks and plumbing works shall not be visible on any face of the building and shall be suitably encased.
(c) All sign boards and names shall be written on the spaces provided on buildings as per approved buildings plans specifically for this purpose and at no other places, whatsoever.
(d) For building services, plumbing services, construction practice, building material, foundation and Damp Proof Course Chapter 10 of the Haryana Building Code, 2017 shall be followed.
[155]
Xv. Lifts and Ramps:
(a) Lift and Ramps in building shall be provided as per Code 7.7.
(b) Lift shall be preferably with 100% standby generators along with automatic switchover along with staircase of required width and number.
(c) If lift cannot be provided as per (b) above, ramps shall be provided conforming to the requirement of clause-3 of Annexure D-3 of Part-3 of National Building Code, 2005
(d) Not applicable in case of retail outlet.
Xvi. Building Bye-laws:
The construction of the building/ buildings shall be governed by provisions of the Haryana Building Code, 2017.
[118]
(No digital signatures are
[125]
Signature of Architect
Signature of Engineer/
required)
Structural Engineer
Mobile no.
E-mail
64Substituted vide Memo No. MISC-720/2024/7/16/2024-TCP dated 25.07.2024
Enclosure to FORM BR-V (A1)
STRUCTURAL DRAWINGS : List of Plans being submitted in accordance with the Structural Design.
2...
4........ ]
[126]
65[ FORM BR-V (A2)
[See code 2.1 (1) (viii)]
Certificate of conformity to rules and structural safety for all buildings except as stated in Form BR-V(A1)
Certificate to be submitted along with the building application in Form BR-I duly signed by the Architect and Empanelled Structural Engineer, Empanelled Proof Consultant and Empanelled Geo-Technical Engineer, if applicable.
Details of the building for which the certificate is issued
Plot No. , Sector _, Colony
City/Town
Name of the owner
Complete address of the owner
A. Building Plans:
i. Name of Architect:
ii. Council of Architecture Registration No. ____, valid upto
iii. Complete Address
iv. E-Mail
v. Mobile no.
B. Structural Design
(a) Empanelled Structural Engineer:
i. Name:
ii. Qualifications:
iii. Department TPR No.
iv. Complete Address
v. E-Mail
vi. Mobile no
(b). Empanelled Proof Consultant, if applicable:
i. Name:
ii. Qualifications:
iii. Department TPR No.
iv. Complete Address
v. E-Mail
vi. Mobile no.
65Substituted vide Memo No. MISC-720/2024/7/16/2024-TCP dated 25.07.2024
[127]
(c). Empanelled Geo-technical Engineer, if applicable:
i. Name :
ii. Qualifications:
iii. Department TPR No.
iv. Complete Address
v. E-Mail
vi. Mobile no.
Certificate
It is hereby certified that the plans submitted in Form BR-1 the building detailed above, are in accordance with the Code and the approved zoning plan of the plot. The structure has been designed in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated
Signature of Owner
(No digital signatures are required)
Signature of Architect
Signature of Empanelled
Structural Engineer
354[The structural design as per the duly signed Structural drawings (for record) mentioned in the countersigned list enclosed with this form, has been checked and has been found to be in order. The design is in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated
Signature of Empanelled Proof Consultant
The structural design of the buildings above 70 m height, as per the duly signed Structuralalong with Mob. No. & E-mail drawings (for record) mentioned in the countersigned list enclosed with this form, has been checked and has been found to be in order. The design is in accordance with the provisions of the National Building Code and the relevant Bureau of Indian Standard Codes (with latest amendments) including Bureau of Indian Standard Codes for structures resistant to earthquakes and other natural hazards. The local soil conditions, its load bearing capacity and the underground water table etc. have been kept in view while designing the same.
Dated
Signature of Empanelled Geo-Technical l t FORM BR-V (A2Engineeralong with Mob. No. & E-mail
[128]
Enclosure to FORM BR-V (A2)
STRUCTURAL DRAWINGS: List of Plans being submitted in accordance with the Structural Design.